Denial of access?
32During the afternoon of the hearing on 18 August 2011 there was much argument and some evidence concerning complaints having been made to the Second Respondent about possible breaches of the law by Ashton in respect of Aboriginal items, and the company's decision to decline requests for Aboriginal interests to have access to the land until official investigation of those complaints was complete.
33Ashton's Brian Wesley deposed (in his affidavit read on that day, pars 53-55) as follows, regarding questions of access:
53 On 11 July 2011, ACOL received a request from Mr Lester for access to the site referred to as the Grinding Groove site GG1 (i.e. the waterhole site).
54 On 14 July 2011, ACOL wrote to Mr Lester regarding his request for access advising that it was considering his request.
55 On 20 July 2011, ACOL wrote to Mr Lester regarding his request for access. Annexed hereto and marked ' BF-07 ' (sic - BW-07) is a copy of the letter to Mr Lester.
34The letter in the relevant annexure to Mr Wesley's affidavit says as follows:
Dear Mr Lester
Request for site visit - Ashton Coal Project
We refer to your email dated 11 July 2011 and your request for access to that part of the Ashton Coal Project referred to in Dr Dan Witter's 2002 report as grinding groove site GG1.
We advise that Ashton Coal Operations Pty Ltd (ACOL) has determined that at this time it does not consider it appropriate to allow access to the GG1 site. The reasons for this include the current legal proceedings in the National Native Title Tribunal (NF11/1) and in the Land and Environment Court (case no. 10335/2011). We also note that the site is the subject of an investigation by the Office of Environment and Heritage.
When the above matters have been resolved or when ACOL considers it appropriate, ACOL proposes to provide access to the site for all Registered Aboriginal Parties through a coordinated consultation process.
35Mr Oshlack cross-examined Mr Wesley on 18 August regarding the access question, and the following exchange occurred (T 18.8.11, p 83, L 28 - p 84 L11, with emphasis added):
Q. Why is it inappropriate to allow access as per the conditions of consent for Mr Lester or Mr Franks and/or Mr Franks to inspect the sites that they to inspect the areas that they believe may have been damaged?
A. We haven't denied access for time. We've we need to be the complaints that were made have been duly investigated by OEH and they are the logical people to be doing that. And subsequent to those inspections, or investigation, we would allow both those individuals and we also find it very important that we involve all our Aboriginal representatives, and not just a couple of individuals .
Q. So the reason that you're denying access is because of this ongoing investigation?
A. It's appropriate for the investigation to be completed and following that, then all Aboriginal registered parties will be informed of the results of that investigation .
Q. Yes but this is to do with them accessing. You're saying when the investigation is finished, you will allow access to the sites?
A. Yes I believe so.
Q. When you say, "I believe so" -
A. I believe it will, yes. It will have to be accessed at that point in time, but that's certainly our intention at this point in time.
Q. Do you know why you are being investigated?
A. No.
Q. Not at all? No one's -
A. Not we haven't been told the as far as to the best of my knowledge we haven't been informed of the nature of the complaints .
Q. How many days of investigations can you tell us has been undertaken on the mine site since the complaints were made?
A. I haven't' personally been involved. I'd certainly I'm not exactly sure to be honest. It's at least two, maybe more. I can't I don't specifically know.
36The parties acknowledged that the departmental investigation of activities on the subject site, carried out prior the grant of the AHIP on 26 August, was still proceeding as at the further hearing on 27 September (T 27.9.11, p8, L50). The site investigation now includes the Department of Planning ( Exhibit L 5, T 27.9.11, p22, LL22-24, and p34, L37- p35, L5). Neither the Minister for Planning, nor his Department, is involved in the present proceedings, but the Minister is a respondent to the other Class 4 matter recently commenced by Mr Lester.
37During the resumed hearing on 27 September the following documentary evidence relevant to the question of access was tendered.
38Exhibit A1 is a letter from Ashton to Mr Lester dated 12 September 2011 in the following terms:
Dear Mr Lester
Request for site visit - Ashton Coal Project
We refer to our letter of 20 July 2011, Ashton Coal Operations Pty Ltd ( ACOL ) is now able to offer you the opportunity to access GG1 at the Bowmans Creek waterhole site.
In accordance with recommendations from the Office of Environment and Heritage and ACOL's occupational health and safety requirements - access to the waterhole GG1 site must be supervised and managed by ACOL.
The opportunity to visit the waterhole GG1 site has also been offered to the Ashton Coal Project's registered Aboriginal parties from Tuesday 13 September 2011.
ACOL is also able to provide access to you for the waterhole site from Tuesday 13 September 2011, or at a later date by arrangement.
Please let me know by 20 September 2011 if you are able accept this invitation.
39Exhibit A2 is a letter from the solicitors for Ashton to Mr Oshlack dated 20 September, urging a review of the Applicant's prayers for relief in the light of the orders of 26 August and the decision of Craig J. In respect of Prayer 7 the letter said: " Prayer 7 should fall away. By email dated 12 September 2011, our client invited the applicant to make an appointment to access the site ". The letter urged that Prayers 3, 7, 8 and 9 in the amended summons not go forward, and invited Mr Oshlack to seek leave from the court to further amend, deleting Prayers 3, 6, 7, 8 and 9, and foreshadowed a NOM to have them dismissed (along with a strike-out of the corresponding paragraphs of the APOC, including paragraphs 3, 5, 15, 16, 17 and 17A.)
40Only Prayer 9 and POC 16 to 17A are now not pressed. In the Applicant's amendments of 27 September, alterations were made to the other contentious prayers and to the POC, and additional prayers and POC were added. The Applicant no longer seeks any relief in respect of the Class 1 proceedings. (Relevant further detail will be presented later in this judgment).
41Mr Galasso noted that the contents of Exhibits A1 and A2 constituted a variation of the position taken by Mr Wesley, in his oral evidence on 18 August, in respect of access. He also noted that the access for heritage related purposes, provided for in condition 3.33 ([4] above), and envisaged by Exhibit A1 ([38] above), should be contrasted with any access granted by the court pursuant to Rule 23.8 (T 27.9.11, p6).
42Exhibit L5 contains an email exchange between Mr Franks and Diane Crosdale, Manager, Planning and Aboriginal Heritage Section, Environment Protection and Regulation, of the Second Respondent, on Monday 26 September.
43The email from Franks to Crosdale on 26 September said:
Diane,
Can you please confirm that you will be issuing a STOP WORK ORDER on the Ashton Ahip, as it is quite clear that sites have been now be destroyed with in this AHIP area and non compliance has occurred with the conditions of the Ahip. Could you also advise why you have stated that your department is not responsible for the investigation, and the Dop is when your department control and manage AHIP requirements.
Could you also advise why your department supported an AHIP that was overlapping someone else land that Ashton Coal do not own or control. At what stage did your department Ashton coal and the Land owner site down and discuss this Ahip.
Could you please also explain why the Ahip Holder AHSTON Coal and your department did not advise the other property owners of the Ahip and their obligation.
Regards,
Scott Franks
44Ms Crosdale replied:
Scott,
Thank you for your email below.
I refer to our conversation this morning. As I advised this morning, the matter is under investigation and the Department of Planning and Infrastructure is the lead agency in consultation with Office of Environment. Kylie Seretis of Department of Planning and Infrastructure is the contact in this regard (phone 9228 6510). All parties are entitled to natural justice. As decisions are made you will be advised.
Regards
Diane Crosdale