Q. Was that ever discussed with Mr Williams?
A. No, because we didn't realise that the airport was - we were told it was closed, and it was not until after we figured out that it wasn't closed.
231 Whatever be the real reason for Dame Kiri not wanting to perform at the Concerts, I am satisfied that it was the reason that Mittane ceased negotiations. However, commercial morality is not the barometer for determining the existence of commercial contracts and when parties are pursuing millions of dollars in turnover and/or profits, they must expect that those with whom they are dealing may insist on the rigorous application of the law of contract. I am satisfied that the plaintiff and Mitani and/or Mittane had not concluded a binding agreement by 16 December 2003 as pleaded. The plaintiff's contract claim fails.
Collateral warranty
232 The plaintiff claimed that Mitani and Mittane warranted that Dame Kiri had read and understood the agreement, and agreed to perform all of the services required under the agreement. In final submissions, Mr Evans submitted (tr 428-429):
The Mitani letter, of course, was much earlier than the Mittane letter, but it still had the same effect, and was an early warranty, which was reinforced by a subsequent warranty, provided in the Mittane letter. That was a collateral warranty to induce the plaintiff to make the contract that was on foot prior to 15 December.
In respect of the Mittane letter, it was collateral to the plaintiff agreeing to enter into a contract with Mittane, the consideration being, firstly, entering into the contract, or, alternatively, agreeing to a variation as to the letter of credit, as sought by Mittane.
233 The warranty claim as pleaded and outlined by the plaintiff is premised on a finding that there was a binding contract. Having regard to my finding that the plaintiff's contract claim fails this claim also fails.
Claim for expenses
234 The plaintiff made the following claim in paragraph 20 of its Commercial List Statement under the heading "Equitable Estoppel Claim":
Between July 2003 and February 2004 the Defendants, and/or each of them, by words, writings and conduct made representations to the Plaintiff and in so doing created and fostered the belief, assumption and understanding of the Plaintiff that [Dame Kiri] would perform at the Concerts.
235 Some of the particulars to this claim are extremely broad: for instance, there is reliance on "telephone calls" between Mr Williams and Dame Kiri in August and October 2003 ((Par 20.1), and between Mr Williams and Mr Grace between July 2003 and February 2004 (20.2); and "e-mails" and/or letters between the plaintiff and Dame Kiri and Mr Grace between July 2003 and February 2004 (20.3). The only 'precision' I was able to obtain in respect of these claims, when I pressed counsel for the plaintiff for assistance, was the Schedule (Ex Z) which, as I have already said, listed over 70 documents in the Court Book by number with nothing more, and then listed conversations by reference to paragraph numbers in affidavits and statements with nothing more.
236 There are particulars of more precision being: the provision by Dame Kiri of her signature for use in the sponsorship invitations for the Launch (20.4); Dame Kiri's participation in the organisation of the Launch (20.5); the provision by Dame Kiri of material for use in the sponsorship package (20.6); Dame Kiri's unqualified agreement to attend the Launch (20.7); Dame Kiri's request for specific travel and accommodation arrangements to be made for her to attend the Launch (20.8); Dame Kiri's request for the Auckland meeting (20.9); Dame Kiri's attendance at the Auckland meeting (20.10); the approval of the budgets for the Concerts (20.11); the request to the plaintiff to agree to have the Mittane contract to provide Dame Kiri's services (20.12); the provision of a draft contract by Mittane to procure Dame Kiri's services (20.13); Dame Kiri's approval of the Concert dates (20.14); and the approval of the venues (20.15).
237 The claim in the Commercial List Statement is that the plaintiff relied upon these "representations" and was induced by them to understand, believe and expect that Dame Kiri would perform at the Concerts and by reason of that understanding, belief and expectation, the plaintiff acted to its detriment in funding, organising and promoting the Concerts (21 - 22, 25). The plaintiff also claimed that the defendants well knew, or should have known, that the plaintiff was spending substantial sums of its own monies in promoting the Concerts (23), and that it was "unconscionable" for the defendants to resile from the assumption that Dame Kiri would perform at the Concerts. The plaintiff claims that the defendants are liable to the plaintiff for its wasted expenditure in funding the organisation and promotion of the Concerts (26).
238 The plaintiff submitted that the facts of this case "fit very neatly" into the "principle" to be found in the following passage of Sheppard J's judgment in Sabemo Pty Ltd v North Sydney Municipal Council [1977] 2 NSWLR 880 at 902-903:
[W]here two parties proceed upon the joint assumption that a contract will be entered into between them, and one does work beneficial for the project, and thus in the interests of the two parties, which work he would not be expected, in other circumstances, to do gratuitously, he will be entitled to compensation or restitution, if the other party unilaterally decides to abandon the project, not for any reason associated with bona fide disagreement concerning the terms of the contract to be entered into but for reasons which, however valid, pertain only to his own position and do not relate at all to that of the other party.
239 In Sabemo the plaintiff was the successful tenderer to the defendant for a proposal to lease land owned by the defendant and redevelop it into a Civic Centre. It was agreed that the acceptance of the tender did no more than bring the parties together, so that they could plan the project until the point was reached where they would enter into a contractual relationship, namely the proposed lease. The plaintiff's expert employees prepared a number of planning schemes and one that was submitted for approval was rejected because of the height of a particular proposed tower. Further work needed to be done, but before proceeding the plaintiff advised the defendant that it had already incurred costs of $300,000, and requested compensation before proceeding further. The defendant suggested that the cost of the further work should be shared equally. The plaintiff prepared a further scheme that was satisfactory and development approval was granted. Whilst all this work was occurring the solicitors for the parties were negotiating the terms of the proposed lease. The negotiations between the solicitors took some time and in the interim, a councillor of the defendant proposed a far less ambitious scheme for the Centre. Subsequently, the defendant resolved to "drop" the approved scheme in respect of which the plaintiff had provided its services. The plaintiff rendered an account for $426,000 to the defendant for work done "for the defendant" which was not paid. The plaintiff then sued successfully for its recovery.
240 Sheppard J observed that the plaintiff's claim was not in contract and that if it arose it was "quasi ex contractu" (at 882), an expression that has since been labelled "heretical", except where it is used as an historical explanation: K Mason and JW Carter, Restitution Law in Australia (1995) par [125]; see also the similar observations of Young J, as the Chief Judge in Equity then was, in relation to the expression "quasi contractual" in Cadorange Pty Ltd (in liq) v Tanga Holdings Pty Limited (1990) 20 NSWLR 26 at 34. After an exhaustive review of the relevant authorities Sheppard J said at 899-900:
The question I must ask myself is whether, at this stage of the development of the law in this country, it is right to say that in some circumstances, in a case of this kind, there will be occasions when the law, irrespective of the common intention of the parties, will impose on one an obligation to pay the other for work done. After due reflection I have reached the conclusion … that there is such a principle in existence.
241 Sheppard J resisted the suggestion that he should fix a limitation that would circumscribe the extent of the right to recovery, and said at 900-901:
It is enough for me to say that I think there is one circumstance here which leads to the conclusion that the plaintiff is entitled to succeed. That circumstance is the fact that the defendant deliberately decided to drop the proposal. It may have had good reasons for doing so, but they had nothing to do with the plaintiff, which, in good faith over a period exceeding three years, had work assiduously towards the day when it would take a building lease of the land and erect thereon the Civic Centre.