© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWCA 291
Court of Appeal (NSW)
2017-08-22
Meagher JA, Payne JA, White JA, Stevenson J
Original judgment source is linked above.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
headnote [This headnote is not to be read as part of the judgment] The appellant (Kawasaki) and the respondent (Laing O'Rourke) are parties to a contract with JKC, the head contractor of a cryogenic tank project near Darwin (the Subcontract). Under the Subcontract, the parties agreed to provide project services to JKC. The Subcontract also required Kawasaki and Laing O'Rourke to provide performance bonds and advance payment bonds to JKC. To regulate their joint and several obligations under the Subcontract, Kawasaki and Laing O'Rourke entered into a Consortium Agreement. This agreement outlined the scope of work each party was responsible for under the Subcontract. By clause 14, Kawasaki agreed to take responsibility for providing the performance bonds and advance payment bonds to JKC. In the same clause of the Consortium Agreement, Laing O'Rourke agreed to provide surety bonds to Kawasaki. By a third agreement (the LORAC Subcontract), Laing O'Rourke agreed to perform some of the work allocated to Kawasaki by the Consortium Agreement. The LORAC Subcontract in Article 6 also provided for the procurement of bonds on behalf of Laing O'Rourke to Kawasaki. Under the Consortium Agreement, Laing O'Rourke and Kawasaki agreed to a regime for the determination of all disputes between them by international arbitration in Singapore. However, that regime allowed for interlocutory relief to be sought from a court of competent jurisdiction. Following a dispute, Kawasaki made a call on the bonds. Laing O'Rourke applied to the Supreme Court of New South Wales restrain Kawasaki from calling on the bonds on the basis that there was a serious question to be tried about whether Kawasaki was entitled to call on the bonds in circumstances where JKC had yet to call on the corresponding bonds provided to JKC under the Subcontract. The primary judge ordered the continuation of the interlocutory injunction. The main issues on appeal were: (i) whether there was a serious question to be tried that, on the proper construction of the Consortium Agreement and the LORAC Subcontract, Kawasaki was not entitled to call on the surety bonds until JKC had called on the Kawasaki bonds; (ii) whether the primary judge should have determined the proper construction of the Consortium Agreement and the LORAC Subcontract "as if on a final basis"; and (iii) whether the primary judge erred by finding that the balance of convenience favoured the continuation of the interlocutory injunction. The Court (Meagher, Payne and White JJA) dismissing the appeal, held: In relation to issue (i), at [86]: There was a serious question to be tried about whether Kawasaki was entitled to call upon the performance bonds issued on behalf of Laing O'Rourke under the Consortium Agreement and the LORAC Subcontract in circumstances where JKC had not made a call upon the Kawasaki bonds. Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458; Lucas Stewart Pty Ltd v Hemmes Hermitage Pty Ltd [2010] NSWCA 283 and Simic v NSW Land and Housing Corporation [2016] HCA 47; (2016) 91 ALJR 108 considered. In relation to issue (ii), at [95], [102]: (2) The primary judge was not asked to determine this case "as if" on a final basis. The primary judge's conclusion that he should determine the case on the basis of a serious question to be tried was correct. Cape Lambert Resources Ltd v MCC Australia Sanjin Mining Pty Ltd [2013] WASCA 66; Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 987 considered. In relation to issue (iii), at [111], [115], [118], [120], [123], [125]: (3) The primary judge did not err in determining that the balance of convenience favoured the continuation of the interlocutory injunction. In particular, it was not shown that the primary judge gave insufficient weight to the matters relied upon by Kawasaki in opposition to the grant of the injunction. Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 98; (2015) BCL 407; RCR O'Donnell Griffin Pty Ltd v Forge Group Power Pty Ltd (Receivers and Managers Appointed) (in liq) [2016] QCA 214; (2016) 32 BLC 406 considered.
Judgment
Overview
The JKC Subcontract
Consortium Agreement
LORAC Subcontract
The surety bonds
The dispute between Kawasaki and Laing O'Rourke
Decision of the primary judge
Issues on appeal
Leave to appeal
Grounds of appeal 1 - 5
Appellant's submissions
Respondent's submissions
Preliminary observations
Clough and a suggested special rule of construction
Construction of clause 14 of the Consortium Agreement
The LORAC Subcontract
Conclusion on grounds 1 - 5
That the primary judge should have determined the proper construction of the contract "as if on a final basis" ground (ground 6)
Appellant's submissions
Respondent's submissions
Consideration of ground 6
The discretion ground (ground 7)
Conclusion and orders
Amendments 17 November 2017 - Typographical error in [116] amended. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 17 November 2017
Kawasaki Heavy Industries, Ltd
Laing O'Rourke Australia Construction Pty Ltd
[2013] WASCA 66
[1986] HCA 70
[2017] WASCA 132
[2016] QCA 214
[2015] VSCA 98
[2015] VSCA 987
(2006) 227 CLR 57
(2008) 249 ALR 458
(1986) 61 ALJR 57
(2016) 91 ALJR 108
(2015) 246 FCR 479
(2013) 298 ALR 666
(1936) 55 CLR 499
[2006] HCA 46
[1936] HCA 40