To the extent that it is presently relevant, section 55 of the Civil and Administrative Tribunal Act 2013 (NSW) (NCAT Act) states:
(1) The Tribunal may dismiss at any stage any proceedings before it in any of the following circumstances:
…
(d) if the Tribunal considers that there has been a want of prosecution of the proceedings.
This appeal concerns a decision of the Consumer and Commercial Division of the Tribunal which dismissed a homeowner's claim, for compensation for allegedly incomplete and defective building works under a residential building contract, for want of prosecution under s 55(1)(d) of the NCAT Act.
To enable an understanding of the circumstances in which the Tribunal determined to dismiss the proceedings, it is necessary to set out the history of the proceedings in some detail.
The dispute arises out of a residential building contract made in October 2015 (the Contract) for the construction of a duplex on land owned by the appellant homeowner (the Homeowner) in Northmead, a suburb of Sydney. The Builder commenced work under the Contract in October 2015. By the middle of 2016, disputes and differences had arisen and by October 2016, matters had reached the stage when the Builder and the Homeowner both decided to elevate their disputes by filing respective claims in the Tribunal.
On 11 October 2016 the Builder filed an application in the Tribunal claiming payment from the Homeowner in the sum of $127,181.01 (the Builder's Application). Then, on 19 October 2016, the Homeowner filed an application in the Tribunal claiming the sum of $130,000, being $110,000 to complete works under the Contract and $20,000 for the rectification of defects (the Homeowner's Application).
The Tribunal made directions to progress both applications, including directions for the filing of evidence in each. Eventually, both applications were listed for hearing as a one-day matter on 20 December 2017. The Tribunal's directions included a direction that the evidence in one application was to be evidence in the other.
At the hearing on 20 December 2017, the Builder unsuccessfully applied for:
1. leave to rely upon an expert report which had been served only one week before the hearing, and outside the time fixed by the Tribunal's directions as to the service of the evidence; and
2. an adjournment of the proceedings.
The Builder's adjournment application having been refused, the hearing proceeded on the allocated hearing day. The matter did not finish and inevitably was stood over to another day, part-heard. This circumstance prompted the Builder to renew the application for leave to rely on the evidence which it had served too late. The Tribunal granted the application for leave to rely on the evidence the second time round. The Tribunal also made directions that required the parties to ensure the experts were available for cross examination when the matter resumed.
The Tribunal fixed both applications, part-heard, for further hearing on 4 April 2018. Due to the unavailability of the Senior Member, the Tribunal fixed the proceedings for further hearing on 9 April 2018. In the lead up to the resumed hearing, on 5 April 2018, the Homeowner applied for an adjournment of the proceedings. Mr Changizi, a director of the Homeowner, made that application on the grounds that the Homeowner needed to obtain alternative legal representation. The application was initially unsuccessful but the Tribunal stood over the Homeowner's application for further consideration by the Senior Member at the hearing on 9 April 2018.
On 9 April 2018, Mr Changizi appeared for the Homeowner. Ms Granger, of counsel, appeared for the Builder. Mr Changizi renewed the Homeowner's earlier adjournment application on the same grounds; the time required for the Homeowner to obtain legal representation.
The transcript of the hearing included in the appeal papers establishes that:
1. Ms Granger informed the Tribunal that the Builder was ready to proceed;
2. Mr Changizi informed the Tribunal that:
1. the previous legal representative was no longer acting for the Homeowner, and had ceased to act for the Homeowner in mid February 2018, on the basis that they " had mutually agreed to part ways and not work together any more";
2. matters between the previous lawyers and the Homeowner had come to a head, using Mr Changzi's words "because of a dispute on another transaction that the counsel was helping me [with]".
The Senior Member did not ask for further explanation of the circumstances surrounding the termination of the lawyer's retainer, and Mr Changizi left the matter there.
The transcript reveals that the Senior Member wanted to know the Homeowner's position if the matter proceeded. Mr Changizi told the Tribunal that he wasn't sure, but felt that the Homeowner would be disadvantaged. As recorded in the transcript, Mr Changizi said:
"I'm not sure, to be honest" and then stated "I have come today prepared to carry on but I do feel that I will be disadvantaged quite severely in not having representation with no solicitor…it is difficult for me to go through the proceedings but if that is your ruling then I'm here to abide by those".
The Appeal Panel pauses at this point to observe that on a fair reading Mr Changizi was not saying that the Homeowner was not prepared to proceed, if forced to. The clear message conveyed by Mr Changizi was that if the Tribunal refused the application for the adjournment the Homeowner would be disadvantaged in presenting its case. Mr Changizi was not saying that if the adjournment were refused the Homeowner would abandon its application or that it would surrender.
After a short adjournment to enable the parties to have further settlement discussions, the hearing continued. At that point, Ms Granger submitted that the Tribunal should direct the matter proceed, and made three relevant observations. The first was that Mr Changizi remained under cross-examination from the previous hearing. The second was that the Builder's expert was available and ready to attend when required. The third was that the Homeowner's experts were not available to be cross-examined, despite the Tribunal's directions which required them to attend.
According to the transcript of the hearing, the Senior Member informed Mr Changizi that the Tribunal was minded to refuse the Homeowner's adjournment application and to proceed with the hearing that day. In the exchange which took place between the Senior Member and Mr Changizi, the Senior Member informed Mr Changizi that the Homeowner's failure to make its experts available for cross-examination could have the consequence that the Homeowner might either be prevented from relying on its expert witnesses, or alternatively the Tribunal might give their reports little weight. Mr Changizi informed the Senior Member that he was unaware that this would be the consequence of not having the Homeowner's experts available and had not been informed about the Tribunal's previous directions granting the Builder leave to rely on its expert and of the Tribunal's directions requiring the parties to have their experts available at the resumed hearing for cross-examination.
Mr Changizi renewed the Homeowner's application for an adjournment of the proceedings to allow the Homeowner to get legal representation. It was at that point, the Senior Member raised the possibility of the Tribunal making an order under s 55 of the NCAT Act. This clearly took Mr Changizi by surprise, as no application for the dismissal of the Homeowner's Application had been notified. Mr Changizi's response was "I am shocked".
The Senior Member the proceeded to enquire of Mr Changizi as to what he had done since 20 December 2017 to get the matter ready for the resumed hearing. Mr Changizi informed the Senior Member that the Homeowner's solicitors had ceased to act for the Homeowner in mid February 2018, and that he had only obtained their files a few weeks later, possibly the first week of March, and that thereafter Mr Changizi had had to "put [the files] back together in a way that I could understand them". Ms Granger, presumably prompted by the Senior Member's indication that the Tribunal was considering whether the Tribunal should dismiss the Homeowner's Application, made an oral application that the Homeowner's Application should be dismissed for want of prosecution. This again had not been the subject of any earlier notification.
In support of the application made orally by Ms Granger, Ms Granger submitted that:
1. Mr Changizi appeared not even to have the relevant documents with him;
2. that, by his own admission, Mr Changizi had not read the file;
3. the Homeowner was not in a position to proceed on the Homeowner's Application;
4. the Homeowner had taken no steps to have its expert available for cross-examination; and
5. the Homeowner, had clearly done nothing since 8 February 2018 to ensure the Homeowner's Application was ready to proceed.
The Senior Member dismissed the Homeowner's Application by exercising the Tribunal's powers to do so under s 55(1)(d) of the NCAT Act. The Senior Member delivered oral reasons for doing so. The part-heard hearing of the Builder's Application then proceeded.
The Homeowner sought written reasons for the Tribunal's decision to dismiss its proceedings for want of prosecution. On 22 May 2018 the Senior Member delivered written reasons which, as the Senior Member made plain, effectively comprised a transcription of the oral reasons given on 9 April 2018, including exchanges between the Senior Member, Mr Changizi and Ms Granger.
As the Homeowner relies upon statements made by the Senior Member concerning the extent to which the Homeowner, through Mr Changizi, had deliberately failed to prepare the proceedings, it is important that the Appeal Panel set out precisely, and in full, what the Senior Member said in that regard:
20. In my opinion and considering carefully everything I've been told by Mr Changizi today and in the application for an adjournment last week, the more I hear from Mr Changizi the more I am convinced that he has in a sense deliberately failed to take, or rather make any effort to prepare and prosecute his case before me - his case, I'm not referring to this defence of the case brought by Jows Construction Proprietary Limited.
21 They [Jows] appear to be prepared. There have been delays in the past, that's true, as I've mentioned already, but as I told Mr Changizi a few moments ago, in my opinion those procedural issues were dealt with satisfactorily on the last occasion and Mr Changizi was given every opportunity to obtain further evidence which would protect him from any of the otherwise unfair results of late service of Jows' expert evidence.
22 Mr Changizi has simply done nothing and I believe that is a proper characterisation of the situation. Ms Granger gave a succinct and professional summary of what the issues are when she made some submissions in reply. I agree with those submissions.
23 I find it remarkable to say the least that Mr Changizi attends today without even asking a professional legal practitioner, an Australian Legal Practitioner, to come with him to provide some assistance, at least in the emergency in which he has put himself today. He has not attempted to get his witnesses available. He tells me he has not even read the material which he recovered from his previous legal representative. There is a very important set of orders made by me on 20 December last year, he's not even aware if a copy of those orders is on file and he tells me that he has not been told about those orders. He has certainly done nothing to comply with those orders.
24. In my view this amounts to a dramatic want of prosecution of the proceedings, I am inclined to think, without being in a position to decide, that Mr Changizi, as I put to him earlier and he denied, has deliberately sabotaged the hearing today. His attendance today, saying "I am completely naked and not ready to proceed, it would not be fair to make me go ahead under those circumstances" that is his main submission but as I have just been stating, the only reason he is in that position is his own lack of prosecution of the proceedings.
[2]
THE GROUNDS OF APPEAL
The Homeowner's amended Notice of Appeal raised a number of grounds to set aside the Tribunal's dismissal order. The Homeowner submits that:
1. the Senior Member failed to have regard to or give proper weight to relevant matters, and took into account irrelevant matters said to be contrary to the evidence;
2. there was a denial of procedural fairness by the Tribunal failing to grant the Homeowner's application to adjourn, failing to permit Mr Changizi to present the Homeowner's case on 9 April 2018 and "failing to take such measures that are reasonably practical to ensure that the appellant had a reasonable opportunity to be heard and to have its evidence and submissions considered contrary to s 38(5)" of the NCAT Act;
3. that the Tribunal's decision to dismiss the Homeowner's Application for want of prosecution was so unreasonable that no reasonable decision maker would have made that determination;
4. that the Senior Member failed to give adequate reasons for the decision to dismiss the Homeowner's Application for want of prosecution; and
5. that in refusing the Homeowner's application for adjournment and on its own motion determining that the Homeowner's Application should be struck out for want of prosecution, the Senior Member demonstrated apprehended bias sufficient to set aside the determination.
The Homeowner also sought leave to appeal on the basis that the decision was not fair and equitable and that the decision of the Tribunal was against the weight of evidence.
The Homeowner's appeal was filed within time. The Homeowner filed its notice of appeal on 13 June 2018 which was within 28 days of the provision of written reasons, and therefore within the time period specified in rule 25(4)(c) of the Civil and Administrative Tribunal Rules 2014 (NSW) for the lodgement of an appeal against a decision of the Tribunal.
Both parties were represented by experienced counsel. As it was common ground between the parties that the decision to dismiss the Homeowner's Application for want of prosecution was an interlocutory decision, the Appeal Panel has approached the appeal on the basis that the appeal is governed by the provisions of s 80(2)(a) which provides that an internal appeal against an interlocutory decision of the Tribunal may only be brought with the leave of the Appeal Panel, whether or not the appeal is founded upon a question of law.
[3]
The Homeowner's Submissions
It is convenient to set out paragraphs 23 to 32 of the Homeowner's submissions on the appeal:
23. The evidence before the Tribunal comprised a Joint Tender Bundle, consisting of the evidence set out in paragraphs 8 to 20 above. In accordance with Order 12 of Senior Member S. Thode of 7 July 2017, evidence in one application was to be evidence in the other.
24. On 20 December 2017, the legal representatives for the Homeowner and the Builder, agreed that the lay evidence would be heard first in both proceedings to be followed by the expert evidence in both proceedings. As the lay evidence was not concluded by 4.00 pm on 20 December 2017, the matter was stood over for the allocation of a new hearing date. At the conclusion of the hearing on 20 December 2017 Counsel for the Builder made a fresh application to permit the Builder to rely upon the report of Mr O'Donnell, its expert. The Tribunal then gave leave to the Builder, by reason of the adjournment, to rely upon the expert report of Mr O'Donnell and directed that all experts be available for cross examination at the next hearing date.
25. The Tribunal set the matter down to be heard on 4 April 2018, but due to the illness of Senior Member G. Meadows, the matter could not proceed on that day and was adjourned to 9 April 2018.
26. On 5 April 2018, Mr Changizi on behalf of the Homeowner, applied to the Tribunal for an adjournment of the hearing on 9 April 2018, such adjournment to be for a period of six weeks to enable the Homeowner to retain alternative legal representation. The Tribunal refused that application, but stood it over for further consideration at the commencement of the hearing on 9 April 2018.
27. On 9 April 2017, Mr Changizi on behalf of the Homeowner, appeared in person but without legal representation. At that time, Mr Changizi renewed his application for an adjournment for a period of 6 weeks to enable the Homeowner to obtain alternate legal representation. In support of that application, Mr Changizi informed the Tribunal of the following matters:
(i) that the legal representative for the Homeowner who appeared on 20 December 2017, had ceased to act for the Homeowner in mid February 2018;
(ii) that Mr Changizi had been unable to recover the files from the legal representative until the last week of February or the first week of March 2018;
(iii) that Mr Changizi had not been able to read the files;
(iv) that Mr Changizi was unaware of the direction made on 20 December 2017, requiring all experts to be present and that accordingly, the experts to be relied upon by the Homeowners were not available that day;
(v) that Mr Changizi had approached a number of firms, but that they were not prepared to act on behalf of the Homeowner until they had had an opportunity to review the files;
(vi) that Mr Changizi had approached at least three different legal firms seeking representation on behalf of the Homeowner, but without success;
(vii) that the retention of new legal representation, being persons experienced in building construction work, was "imminent", the cost agreement having been received by Mr Changizi that morning;
(viii) that Mr Changizi did not have the "legal capabilities" to properly represent the Homeowner's claim, being a claim that involved a number of complex legal issues;
(ix) that if the application for adjournment was refused, that Mr Changizi was, notwithstanding being "disadvantaged", would appear on behalf of the Homeowner for the hearing that day;
28. In the light of and having regard to the matters set out in paragraphs 23 to 27 above, Counsel for the Builder, although initially making an application for the hearing to proceed then made the following submissions in support of its application that the Homeowner's claim be dismissed for want of prosecution;
(i) that Mr Changizi was the "author of his own circumstances";
(ii) that Mr Changizi had not read the file;
(iii) that Mr Changizi was not in a position to proceed with the hearing;
(iv) that Mr Changizi had taken no steps to have the Homeowner's experts available for the hearing that day; and
(v) that Mr Changizi had "clearly done nothing" since 8 February 2018;
29. For the reasons set out in paragraph 27 above, the matters relied upon by Counsel for the Builder and in particular, items (iii) and (v) above, were incorrect.
30. The Tribunal, notwithstanding the matters set out in paragraphs 23 to 27 above, and in the absence of any contrary evidence or the cross examination of Mr Changizi, then held as follows:
(i) that Mr Changizi had "deliberately sabotaged" the hearing on 9 April 2017;
(ii) that because the file had been marked with a "Red Sticker", that the Tribunal superiors would want to know why such an old matter had not been resolved; and
(iii) that notwithstanding and apart from the "legal issues" in relation to the contract and its termination, being complex issues including the requirement for the provision of expert evidence, held that Mr Changizi was not "quite so helpless in looking after himself as not to be aware of what are the real issues in the proceedings", including the "procedural issues";
(iv) that the Tribunal did not accept that it was reasonable for Mr Changizi to appear that day so "completely unprepared"; and
(v) that based upon the submissions of the Counsel for the Builder (see paragraph 28 above), which the Tribunal held to be "succinct and professional summary" of the issues and with which the Tribunal agreed;
proceeded not only to dismiss the Homeowner's application for adjournment but ordered that the Homeowner's claim be struck out for want of prosecution.
31. Based upon the matters set out in paragraphs 28 to 30 above and notwithstanding that Mr Changizi was:
(i) a litigant in person;
(ii) disadvantaged by not having legal representation as had been present to prosecute the Homeowner's claim on 20 December 2017; and
(iii) ready to proceed with the hearing that day;
the Tribunal nevertheless proceeded to order that the Homeowner's claims be dismissed for want of prosecution pursuant to section 55(1)(d) of the Act.
32. The Tribunal made the order set out in paragraph 31 above, notwithstanding that the Tribunal ordered that day for the Builder's claim to proceed and that Mr Changizi was required to remain to complete his cross examination that day in respect to both the Homeowner's claim and the Builder's claim and in addition to represent the Homeowner in defence of the Builder's Claim.
The Homeowner relies on the Appeal Panel's decision in Bousgas v HD Constructions (Aust) Pty Ltd [2017] NSWCATAP 122 and the decision of Simpson J in Hoser v Hartcher [1999] NSWSC 527. In the former case the Appeal Panel considered the various factors which are relevant to the exercise of the Tribunal's discretion to dismiss Tribunal proceedings for want of prosecution. The Homeowner also referred to the principle set out by Basten JA in State of New South Wales v Plaintiff A [2012] NSWCA 248 at [17], which stands as authority for the proposition that the Court would be reluctant to exercise the power of summary dismissal for want of prosecution where the evidence does not establish intentional and contumelious default on the part of the plaintiff, or inordinate or inexcusable delay giving rise to a substantial risk that a fair trial would not be possible. The Homeowner acknowledged that the stringency of that test had been diminished since the introduction of s 56 of the Civil Procedure Act 2005 (NSW) which is in substantially the same terms as s 36(1) of the NCAT Act, that the guiding principle for the NCAT Act and the Rules is to facilitate the just, quick and cheap resolution of the real issues in the proceedings.
In the light of the principles emerging from the case law, and the guiding principle in s 36(1) of the NCAT Act, the Homeowner submitted that:
1. the most relevant consideration which the Tribunal had to consider in deciding whether it should dismiss the Homeowner's Application for want of prosecution was that of prejudice; prejudice that the delay in the determination of proceedings had upon the Builder's capacity to properly defend the Homeowner's Application; and
2. the Builder had the onus of establishing prejudice in the relevant sense.
The Homeowner on appeal further submitted that:
1. the Senior Member did not have any evidence which either indicated or established that the Builder would suffer any prejudice in the relevant sense by the delay that had taken place, and which would take place if the Tribunal granted the six week adjournment;
2. the lack of any real prejudice to the Builder had to be weighed against the clear damage which the Homeowner would suffer if the Homeowner's Application were dismissed; said to be "substantial and irreparable" when "the proceedings were part heard and substantial legal costs had been incurred";
3. even if there had been "misconduct in the form of tardiness on the part of the [Homeowner]" the essential issue which should have governed the Senior Member's consideration was whether or not that delay or tardiness precluded or give rise to a substantial risk that a fair trial of the Homeowner's Application was no longer possible;
4. the adjournment application on 9 April 2018 was the first occasion upon which the Homeowner had made any such application to the Tribunal, and the Tribunal's findings regarding Mr Changizi, and therefore the Homeowner, were contrary to the evidence and did not in any event establish a clear case for the exercise of the discretion;
5. the Tribunal had not found that the Homeowner's Application either lacked bona fides or was not substantial, and that the Tribunal's finding that Mr Changizi had "deliberately sabotaged the hearing" was contrary to the evidence and constituted an element of punishing the Homeowner for the alleged tardiness of Mr Changizi. The Homeowner did acknowledge that the Tribunal Member indicated that he was not able to determine whether Mr Changizi had deliberately sabotaged the hearing, however the Homeowner submitted that the Tribunal had nevertheless placed weight upon such a conclusion by holding that the Tribunal was very comfortably satisfied that there was a dramatic want of prosecution; and
6. Mr Changizi's explanation for the delay by reason of which he sought an adjournment was not subject to contrary evidence or any cross examination of Mr Changizi, and the Senior Member had failed to consider why tardiness on the part of the Homeowner could not be adequately addressed by granting the adjournment on terms of an appropriate order for costs.
According to the Homeowner, the Senior Member had incorrectly relied upon three matters to dismiss the application for want of prosecution:
1. firstly, the suggestion that Mr Changizi had sacked the Homeowner's legal representative;
2. secondly, that the Tribunal file had a "red sticker" signifying that its determination had taken too long; and
3. thirdly, that Mr Changizi had done nothing to prepare the Homeowner's case for the resumed hearing since December 2017.
The Homeowner maintained that the Senior Member was mistaken because:
1. there was no evidence to support a finding that Mr Changizi had sacked the Homeowner's legal representative, Mr Changizi's explanation having been that the Homeowner and its legal representative parted ways based upon a personal dispute in relation to another matter;
2. a red sticker was placed on files in the Consumer and Commercial Division that have not been determined within a specific period of time, as an indication that the matter should be progressed to ensure the Tribunal maintained its desired level of efficiency in the disposal of matters, but otherwise as having no bearing on whether or not the matter was one where there had been a want of prosecution; and
3. the Homeowner had prosecuted its claim with reasonable diligence prior to 20 December 2017;
4. there existed no proper basis upon which the Tribunal could conclude that the Homeowner had disregarded the orders and directions of the Tribunal, or that the dismissal of the claim for want of prosecution was clear or manifestly warranted;
5. the evidence disclosed that Mr Changizi had undertaken a number of steps since mid-February 2018 and that it was incorrect for the Tribunal to find that Mr Changizi did not "have his documents with him" or that he was not ready to proceed if the adjournment was not granted; and
6. the evidence before the Tribunal was that Mr Changizi had "most of the file with him" and that Mr Changizi had made a statement to that effect. Mr Changizi also indicated that he was ready to proceed if the application for adjournment was refused.
As to the Homeowner's challenge to the Tribunal's determination on the basis of a lack of procedural fairness, the Homeowner relied on the same matters, further submitting that:
1. "by refusing the application by the Homeowner to adjourn the proceedings for six weeks and by proceeding to dismiss the Homeowner's claim for want of prosecution, the Tribunal took the least informal and least practical course to enable the real issue in dispute to be resolved and in so doing denied the Homeowner procedural fairness".
2. the reasons of the Tribunal did not adequately set out why it was appropriate to exercise the discretion to strike out for want of prosecution in the circumstances.
As to the Homeowner's challenge to the Tribunal's determination based on alleged apprehended bias by the Senior Member, the Homeowner relied upon the Senior Member's suggestion that Mr Changizi had "deliberately sabotaged the hearing" as indicating to a fair minded and reasonable observer that the Tribunal Member might not bring an impartial and unprejudiced mind to the resolution of the issues in the dispute.
[4]
The Builder's submissions
The Builder opposed the grant of leave to appeal and submitted that the appeal should be dismissed. In broad terms, the Builder submitted that:
1. there was no error in the exercise of the Tribunal's discretion of the type which the High Court stated in House v The King (1936) 55 CLR 499 as being necessary for appellate intervention to successfully challenge a tribunal's exercise of discretion;
2. that "without all of the relevant documents, having not read the Court file and without his expert witnesses in attendance, the objective fact is that K & J Vision was not able to proceed". In this regard, the Builder referred to Mr Changizi's statement to the Senior Member that he would be disadvantaged quite severely in not having representation and Mr Changizi's admission that he did not have the legal capabilities to represent the Homeowner.
3. "a party ought not be allowed to force the Tribunal's hands to grant an adjournment by attending so fully unprepared and unable to prosecute its case";
4. the Tribunal had correctly noted the prejudice to the Builder in not dismissing the Homeowner's Application was "occasioned by its legal team having prepared and being ready to proceed, with witnesses in attendance". On this issue, the Builder acknowledged that that was not prejudice that could not be cured by a costs order but submitted that that was "not to the point in light of s 36 of the Act and modern considerations of case management";
5. quoting the Member's decision, the Tribunal had found that the Homeowner had "deliberately failed to take, or rather make any effort to prepare and prosecute [its] case";
6. the statement that Mr Changizi might be thought to have deliberately sabotaged the proceedings was not an irrelevant consideration and that the conclusions that Mr Changizi had done nothing and was not ready to proceed were "accurate albeit a colloquial summary of the steps taken by [the Homeowner] having regard to the fact that it had chosen to part ways with its legal representation by 8 February 2018";
7. the Tribunal had proper regard to the steps taken by the Homeowner since 8 February 2018 and had found them "significantly wanting";
8. it was open to the Senior Member to find that in all of the circumstances Mr Changizi appeared to have deliberately sabotaged the Homeowner's ability to proceed with the trial on 9 April 2018, and that in those circumstances the Tribunal was faced with three options:
1. the Tribunal could have granted the further adjournment sought. The Builder submitted that there was no proper basis for such an adjournment in the circumstances;
2. the Tribunal could have forced the Homeowner to proceed. The Builder submitted that that was "not a practical option in circumstances where the Homeowner required expert evidence to support its case and Mr Changizi had failed to arrange for the experts to be in attendance". The Builder submitted that "despite his assertions to the contrary, [Mr Changizi] simply was unable to prosecute K & J's application on 9 April 2018";
3. the Tribunal could have dismissed the Homeowner's Application, as the Senior Member did. The Builder submitted that Mr Changizi's conduct had been "contrary to the guiding principle and an abuse of process". In support of that submission the Builder asserted that the effect of Mr Changizi's conduct was to force the Senior Member's hand to permit an adjournment which, it was submitted, in light of the guiding principles clearly amounts to an abuse of process.
In respect of the assertion that by failing to grant an adjournment the Tribunal denied the Homeowner procedural fairness, the Builder submitted that s 38 of the NCAT Act did not require the Tribunal to do more than undertake reasonably practicable measures to ensure parties have a reasonable opportunity to be heard. The Builder further submitted "there can be no failure of the Tribunal to afford procedural fairness, as alleged, in circumstances where an adjournment of the proceedings was not warranted". On this point, the Builder relied upon the decision of an Appeal Panel in O'Neil v T & I Engines Pty Ltd [2015] NSWCATAP 77 at 22(3) which stated:
"Where the adjournment is caused, at least in part, by the delay of the party seeking the adjournment, or non-compliance by that party with an extant order of the Tribunal, adequate explanation is called for, and its absence weighs heavily, and sometimes decisively against the grant of an adjournment".
In response to the Homeowner's challenge to the Tribunal's determination on the grounds that the Tribunal's decision was unreasonable, the Builder submitted that the Tribunal's decision to dismiss the proceedings was not unreasonable in the relevant sense.
In respect of the Homeowner's challenge to the Tribunal's determination on the grounds that the Tribunal had failed to give adequate reasons, the Builder submitted that the reasons were adequate; the Tribunal had set out the submissions on which its conclusions were based, the applicable law and its reasoning process, that is the factors weighing against and in favour of the course adopted, and its conclusion that the proceeding should be dismissed.
In relation to the Homeowner's claim of apprehended bias, the Builder submitted that there was nothing raised by the Homeowner which would lead a fair-minded observer to conclude that the Tribunal had decided the matter other than on its legal and factual merits.
[5]
Consideration
As the Appeal Panel has already stated, it was common ground that, as the decision under appeal was an interlocutory decision, the Homeowner required the leave of the Appeal Panel to bring an appeal to the Tribunal's determination to dismiss the Homeowner's Application. The principles applicable to the grant of leave to appeal in respect of an interlocutory decision were considered by the Appeal Panel in Champion Homes v Guirgis [2018] NSWCATAP 54 at [31]-[35]. The Appeal Panel stated at [34]-[35]:
34.… there is no specification in the NCAT Act as to the circumstances in which leave should be granted in respect of interlocutory decisions. Rather, there is a discretion to be exercised and general principles apply to the grant of leave to appeal such decisions.
35. As stated in various decisions of the Tribunal and its predecessor, the Administrative Decisions Tribunal, the principles to be applied are to be derived from the principles applicable to leave applications in courts: see for instance, Johnston v Department of Education and Training (GD) [2007] NSWADTAP 6 and BHM v BHN & Ors [2014] NSWCATAP 26. These principles include the following:
1. It is unnecessary and unwise to lay down rigid rules of practice or exhaustive criteria governing the grant of leave to appeal: Adam P Brown Male Fashions Pty Ltd v Philip Morris Inc (1981) 148 CLR 170 at 175; [1981] HCA 39;
2. However, the requirement for leave is a filter restricting access to the appeal process: Coulter v R (1988) 164 CLR 350; [1988] HCA 3 at 359 per Deane and Gaudron JJ;
3. Leave should only be granted where there are substantial reasons to allow an appellate review: Johnson Tiles Pty Ltd v Esso Australia Ltd [2000] 104 FCR 564;
4. Circumstances justifying leave may be an error of principle resulting in substantial injustice: Minogue v Williams [2000] FCA 125. However, these concepts may not be cumulative;
5. There is a difference between the exercise of a discretion concerning a matter of practice and procedure and an exercise of a discretion that determines substantive rights: Adam P Brown per Aickin, Wilson and Brennan JJ at 177 citing with approval Jordan CJ in In re Will of FB Gilbert (dec) (1946) 46 SR (NSW) 318 at 323;
6. Where an interlocutory decision effectively determines the substantive rights of the parties, that may be a significant factor in favour of granting leave to appeal: Eltran Pty Ltd v Westpac Banking Corporation (1991) 32 FCR 195 per Spender J at [14]-[15], referring to Ex parte Bucknell (1936) 56 CLR 221 at 225-6;
7. In connection with a matter of practice and procedure, restraint should be applied in reviewing such decisions, especially if an application for leave is made during the course of a hearing: BHP Billiton Ltd v Dunning [2013] NSWCA 421 at [21], referring to Adam P Brown and in In re Will of FB Gilbert (dec);
8. Leave should not be granted unless a substantial injustice would result and the decision is attended with sufficient doubt to warrant it being reconsidered by the appeal body. What is sufficient is dependent on the particular case: Décor Corporation Pty Ltd v Dart Industries Inc (1991) 33 FCR 397 at 398-9;
9. Lastly, subject to the above, the matters set out in Collins at [84 (1)-(2)] are also relevant to the exercise of a discretion to grant leave.
The matters set out in Collins v Urban [2014] NSWCATAP 17 at [84 (1) to (2)] were:
(1) In order to be granted leave to appeal, the applicant must demonstrate something more than that the primary decision maker was arguably wrong in the conclusion arrived at or that there was a bona fide challenge to an issue of fact: BHP Billiton Ltd v Dunning [2013] NSWCA 421 at [19] and the authorities cited there, Nakad v Commissioner of Police, NSW Police Force [2014] NSWCATAP 10 at [45];
(2) Ordinarily it is appropriate to grant leave to appeal only in matters that involve:
1. issues of principle;
2. questions of public importance or matters of administration or policy which might have general application; or
3. an injustice which is reasonably clear, in the sense of going beyond merely what is arguable, or an error that is plain and readily apparent which is central to the Tribunal's decision and not merely peripheral, so that it would be unjust to allow the finding to stand;
4. a factual error that was unreasonably arrived at and clearly mistaken; or
5. the Tribunal having gone about the fact finding process in such an unorthodox manner or in such a way that it was likely to produce an unfair result so that it would be in the interests of justice for it to be reviewed,
The considerations relevant to the exercise of the power provided by s 55(1)(d) of the NCAT Act to dismiss an application for want of prosecution were addressed by the Appeal Panel in Bousgas v HD Constructions at [27]-[34] as follows:
[27] The power to dismiss a proceeding for want of prosecution is found in s 55(1)(d) of the NCAT Act. This power is discretionary in its nature.
[28] The principles applicable in deciding whether proceedings should be dismissed for want of prosecution were summarised by the Supreme Court of New South Wales in Hoser v Hartcher [1999] NSWSC 527. In that case, Simpson J said at [19] and following:
19. It seems to me that the following principles are relevant to the exercise of the discretion to strike out for want of prosecution. The list is not intended to be exhaustive:
(1) the ultimate question is whether, on balancing the prejudice to the respective parties by making or not making an order, justice demands that the action be dismissed: Stollznow v Calvert(1980) 2 NSWLR 749 at 751 F (Court of Appeal); Razvan v Berechet , unreported Court of Appeal, 23 February 1990; Vilo v John Fairfax and Sons Ltd , unreported, 19 November 1995, per Sperling J;
(2) the discretion should be exercised only in a clear case where it is manifestly warranted; Razvan, per Kirby P; as is generally the case with discretionary decisions, each case depends upon its own facts. Rigid formulae should not be applied to the exercise of the discretion: Stollznow v Calvert at 751 D;
(3) any explanation offered by the plaintiff for the delay in proceeding must be considered: Burke v TCN Channel Nine Pty Ltd , unreported, 16 December 1994, per Levine J;
(4) personal blamelessness on the part of a plaintiff(as distinct from any tardiness or other fault on the part of his/her/its legal representative) is relevant: Stollznow, p 73.
(5) a defendant who takes no steps to secure progress in the proceedings, or to activate an apparently inactive plaintiff or who stands by in the hope that the passage of time will ensure the quiet death of the proceedings or that the longer delay will strengthen the case for striking out, runs the risk that that very behaviour will operate to his/her/its disadvantage. A defendant has two choices: to attempt to prod the plaintiff into action, or to stand by, doing nothing, trusting that time will bring about the slow death of the action. Either choice represents something of a gamble, dependent upon future events that the defendant is unable with any degree of confidence to predict. If the defendant opts for the former course, of prodding the plaintiff into action, it may succeed in doing so, precluding an application to strike out. On the other hand, if the plaintiff remains inert, the defendant's case for striking out strengthens with passing time. If the defendant chooses the latter option and takes no action, the plaintiff may take no further steps, or may take no further steps until such irremediable prejudice is caused to the defendant that the application to strike out will succeed; if, however, some other event galvanises the plaintiff into action the defendant, having done nothing to progress the matter, can hardly be heard to complain of the plaintiff's earlier inactivity: Calvert v Stollznow, 1 April 1980, Ritchie's Supreme Court Procedure, (NSW) Vol 2, para 13, 022, per Cross J (at first instance); and in the Court of Appeal per Moffitt J, p 753; Vilo, p 10; McBride v Australian Broadcasting Corporation , unreported 6 November 1998, per Levine J; Bass v TCN Channel Nine Ltd , unreported 25 July 1997, per Levine J; Hart v Herron , unreported, 3 June 1993, Court of Appeal per Priestley JA;
(6) delay between the date the cause of action arose and the commencement of the proceedings may be a relevant factor: Calvert v Stollznow, per Cross J; Burke v TCN. But in my view, this circumstance must be treated with some caution. The weight that can be accorded to that delay is limited. Where an action is commenced within the period provided for by an applicable statute of limitations, it would not ordinarily be appropriate to take that period into account. However, if a plaintiff has delayed significantly in the commencement of the proceedings, and that delay is followed by further lethargy in the advancement of the proceedings, the effect of the initial (but permissible) delay is compounded. The real question is not the length of the delay, but the impact that delay has upon the defendant's capacity properly to defend the plaintiff's claim. That will be a question of fact in each case. While there may be some prejudice presumed by reason of the passage of time, much will depend upon the nature of the proceedings, and the identification of the issues involved in the litigation. Where, for example, at the close of pleadings it can be seen that there are disputed questions of fact dependent upon the oral evidence of witnesses, or their recollections, the prejudice will plainly be greater than in cases that depend essentially upon the application of legal principle to largely undisputed facts, or upon disputed questions of fact that will be resolved by reference to documentary or other objective evidence not likely to be affected by the effluxion of time;
(7) the onus lies on the defendant to establish any prejudice upon which reliance is placed. The disappearance or death of witnesses, the fading of their recollections, or the destruction of records, are some obvious examples of the kind of prejudice that might arise;
(8) prejudice to a defendant caused by delay has to be balanced against prejudice to a plaintiff deprived of an otherwise valid claim; delay in the commencement of proceedings by a plaintiff is sometimes taken as evidence contra-indicating prejudice to the plaintiff in the sense that he/she/it has evinced no interest in his/her/its own case: Burke, supra. Such an inference may be contra indicated by explanatory evidence; in this regard the plaintiff's personal responsibility for the delay is an important factor as is any explanation provided for the delay;
(9) what the defendant has (or has not) done by way of preparation for trial may be a factor. This is a distinct question from that concerning any steps taken (or not taken) by the defendant in prompting the plaintiff to action. A defendant who has not interviewed witnesses, taken statements or collected documents, after being served with the claim, has a less meritorious complaint about the effect of prejudice caused or presumed by reason of delay: McBride v ABC , unreported, 6 November 1998, per Levine J;
(10) the plaintiff's prospects of success is a relevant factor. If it appears that the prospects are minimal, the discretion is more likely to be exercised in favour of the defendant. Conversely, where the plaintiff's case is strong (absent the kind of prejudice to the defendant to which I have referred) it is less likely that justice will be done by striking the action out: Razvan, per Kirby P;
(11) the exercise of the discretion to strike out should not incorporate any element of punishing a tardy plaintiff, or of excluding one who may appear to have some unworthy characteristics: Razvan, per Kirby P. The ultimate aim of a court is the attainment of justice: Queensland v J L Holdings Pty Ltd(1997) 189 CLR 146. To adapt the words of the High Court in that case, discretions such as that presently invoked ought not to be used to supplant the overall aim of the attainment of justice.
[29] This decision was made before the introduction of the Civil Procedure Act, 2005 (CP Act) and s 56 of that Act which require a court to "facilitate the just, quick and cheap resolution of the real issues in the proceedings".
[30] In Batistatos v Roads and Traffic Authority (NSW) [2006] HCA 27 ; (2006) 227 ALR 425 ; (2006) 80 ALJR 1100, the majority of the High Court of Australia said at [65]-[69]:
65. The "right" of the plaintiff with a common law claim to institute an action is not at large. It is subject to the operation of the whole of the applicable procedural and substantive law administered by the court, whose processes are enlivened in the particular circumstances. This includes the principles respecting abuse of process.
66. Birkett v James concerned a second action commenced in anticipation that a strike-out motion, for want of prosecution, would dispose of the first action. Lord Diplock said that in such a situation [93]:
[E]xceptional cases apart, where all that the plaintiff has done has been to let the previous action go to sleep, the court in my opinion would have no power to prevent him starting a fresh action within the limitation period and proceeding with it with all proper diligence notwithstanding that his previous action had been dismissed for want of prosecution.
67. What those "exceptional cases" might include was not explored beyond the possible example given by Lord Diplock of Spring Grove Services Ltd v Deane [94], but it is apparent from other passages [95] that "contumelious disregard" by a plaintiff in observance of the more important steps in the preparation of the action for trial could enliven the exercise of the inherent power of the court. Such default was not relied on in Birkett v James [96] itself. However, it is upon this footing that the present plaintiff points to a requirement of "oppressive conduct", to its conceded absence in this case, and to consequent error in principle by the Court of Appeal.
68. The decisions in England since Birkett v James were analysed recently and in detail by the New Zealand Court of Appeal in Bank of New Zealand v Savril Contractors Ltd [97]. It is unnecessary to repeat what is there said, beyond making one point. This is that, as exemplified by the decision of the English Court of Appeal in Securum Finance Ltd v Ashton [98], the new Civil Procedure Rules have been taken in England as giving a wider scope for the use of principles of abuse of process in dealing with dilatory plaintiffs. It has been suggested that the significance of Birkett v James has been "overtaken" by the strictures of the new procedural code [99].
69. The descriptions, rather than definitions, given in this Court and set out earlier in these reasons post-date Birkett v James and do not provide any ground for a requirement of oppressive conduct by the plaintiff. Rather, as in the circumstances of the present case, attention must be directed to the burdensome effect upon the defendants of the situation that has arisen by lapse of time. The Court of Appeal held that this was so serious that a fair trial was not possible. The result was that to permit the plaintiff's case to proceed would clearly inflict unnecessary injustice upon the defendants.
[31] Subsequently, in New South Wales v Plaintiff A [2012] NSWCA 248, Basten JA said at [17]-[18]:
17. Although there is authority for the proposition that a court should be reluctant to exercise the power of summary dismissal without a hearing on the merits absent intentional and contumelious default on the part of the plaintiff, or inordinate or inexcusable delay, giving rise to a substantial risk that a fair trial would not be possible - see Birkett v James[1978] AC 297 at 318 - the stringency of that principle has been diminished by the enactment of ss 56-60 of the Civil Procedure Act. Further, a proceeding will involve an abuse of process in circumstances where the objective effect of the lapse of time since the cause of action arose is to render a fair trial impossible, despite the absence of any moral delinquency, oppressive conduct or misconduct on the part of the plaintiff: Batistatos v Roads and Traffic Authority (NSW) [2006] HCA 27 ; 226 CLR 256 at [69]-[70].
18. Despite the fact that misconduct on the part of a plaintiff is not a precondition to a finding of abuse of process, the reasons for any delay are relevant considerations. Thus, it would be a rare case in which a defendant could complain of unfairness where the delay was in large part due to the defendant's own behaviour. By parity of reasoning, a court is likely more readily to find an abuse of process where there is culpable misconduct on the part of a plaintiff.
[32] As is clear from these comments, the requirements of s 56 of the CP Act is itself a matter to be taken account of in determining whether proceedings should be dismissed for want of prosecution.
[33] Similarly, s 36(1), (3) and (4) and s 38(5)(c) of the NCAT Act impose obligations on the Tribunal and the parties which must be taken account of in considering whether to make an order to dismiss proceedings for want of prosecution under s 55(1)(d) of the NCAT Act.
[34] It is in the context of these principles that the decision of the Tribunal must be evaluated.
The Builder correctly submitted, as that the Tribunal's decision to dismiss the Homeowner's Application was a discretionary decision of the Tribunal, the Homeowner had to establish a House v The King error. In that case (House v The King (1936) 55 CLR 499 at 504-505) the Court said:
The manner in which an appeal against an exercise of discretion should be determined is governed by established principles. It is not enough that the judges composing the appellate court consider that, if they had been in the position of the primary judge, they would have taken a different course. It must appear that some error has been made in exercising the discretion. If the judge acts upon a wrong principle, if he allows extraneous or irrelevant matters to guide or affect him, if he mistakes the facts, if he does not take into account some material consideration, then his determination should be reviewed and the appellate court may exercise its own discretion in substitution for his if it has the materials for doing so. It may not appear how the primary judge has reached the result embodied in his order, but, if upon the facts it is unreasonable or plainly unjust, the appellate court may infer that in some way there has been a failure properly to exercise the discretion which the law reposes in the court of first instance. In such a case, although the nature of the error may not be discoverable, the exercise of the discretion is reviewed on the ground that a substantial wrong has in fact occurred.
The Appeal Panel has concluded that leave to appeal should be granted and that the decision to dismiss the proceedings should be set aside. The reasons for that decision are explained in what follows.
The Appeal Panel accepts that in light of the provisions of s 36 of NCAT Act, following the Appeal Panel's earlier statements on the same issues in Bousgas, it is not necessary before the discretion to dismiss for want of prosecution may be exercised that an applicant's conduct has been deliberate and contumelious. However it is in the Appeal Panel's view necessary before the power is exercised that the Tribunal must find that the conduct of the applicant was such as to constitute an abuse of process, or was such as to have caused such prejudice to a respondent that it would not be fair to permit the matter to go to trial.
As Basten JA suggested in NSW v Plaintiff A, the Tribunal may more readily dismiss an application for want of prosecution where the applicant's conduct leading to delay has been deliberate and culpable.
The Senior Member exercised his discretion in two ways, each unfavourably to the Homeowner. The first was in refusing the Homeowner's application for an adjournment to allow the Homeowner to obtain legal representation. The second was to dismiss the Homeowner's Application for want of prosecution.
The proceedings were part heard, the Builder was ready to proceed with the hearing and had expert witnesses available. The Homeowner, in the person of Mr Changizi, failed adequately to explain the reasons why it had been unable to get ready for the hearing or obtain legal representation to enable the Homeowner's case to be properly prepared. In the absence of detailed explanation of the circumstances in which the Homeowner had terminated the retainer of its former solicitors and full details of the steps taken to obtain alternative representation, the Tribunal was entitled to be sceptical of Mr Changizi's adjournment application and his failure to be prepared or obtain legal representation. In addition, the Appeal Panel considers the Senior Member was entitled to take into account the fact that the Homeowner's Application had been in the Tribunal for a long period, as indicated by the red sticker. The Senior Member weighed the relevant factors in refusing the Homeowner's adjournment application. The Appeal Panel finds no error in the Senior Member's determination at that point.
The Appeal Panel is of the view that the Senior Member's discretion in dismissing the Homeowner's Application miscarried.
To warrant the Homeowner's claim being struck out for want of prosecution it was necessary for the Tribunal to be persuaded that the Homeowner had engaged in an abuse of process or that the Builder would be unduly prejudiced if the hearing proceeded. As Simpson J held in Hoser v Hartcher (at [19(11)]) the exercise of the discretion to strike out for want of prosecution should not incorporate any element of punishing a tardy plaintiff or of excluding one who may appear to have some unworthy characteristics.
The Appeal Panel accepts the Homeowner's submission that there was no basis to conclude that the Builder would have been prejudiced if the hearing had proceeded. Indeed, given that the Homeowner's experts were not available for cross examination, and the Senior Member's correct observation that this was likely to have diminished the weight the Tribunal could afford to the Homeowner's expert evidence, or to have prevented the Homeowner from relying on it, the Tribunal could have permitted the Homeowner's Application to proceed on the day rather than summarily dismiss it without more.
In the final analysis, the Appeal Panel has concluded that the evidence before the Senior Member was not sufficient to establish that the Homeowner had engaged in the type of conduct to which Simpson J referred in Hoser v Hartcher (at [19(11)]), namely an abuse of process. The only "evidence" before the Tribunal was the statements made by Mr Changizi from the Bar table and, perhaps, what the Senior Member observed in relation to the volume of documentation which Mr Changizi had with him. In this latter respect we note that the Senior Member made no findings and did not explicitly record exactly what he observed Mr Changizi had brought with him.
The statements by Mr Changizi from the Bar table did not, in the Appeal Panel's view, amount to an admission that the Homeowner had dismissed its solicitors for inappropriate reasons, that the Homeowner was to be faulted for parting ways with its solicitors, or that Mr Changizi had "deliberately sabotaged" the hearing. Mr Changizi's explanations for the termination of the retainer of the Homeowner's solicitors were not detailed or explicit, but Mr Changizi did explain that the separation was related to other proceedings. There was no basis in that statement to found any inference that the termination had been inappropriate or brought about in order to delay the proceedings in the Tribunal.
Mr Changizi's statements from the Bar table likewise did not indicate an intent on Mr Changizi's part to sabotage the hearing, or deliberately bring about the result that the Tribunal had no option but to adjourn. Mr Changizi had clearly not been as diligent in the prosecution of the Homeowner's Application as he should have been, but he was not a legal practitioner and should not have been held to the standards expected of legal practitioners. Ultimately, the Tribunal had to consider the overall interests of justice in that context, particularly having regard to the great prejudice suffered by the Homeowner on one side when weighed against any prejudice to the Builder, and particularly where the sanction of costs was available to the Tribunal.
In the Appeal Panel's view, contrary to the conclusion set out in paragraph [24] of the Senior Member's reasons (set out above), Mr Changizi did not say "I am naked, and not ready to proceed" or words to that effect. The transcript of the hearing on 9 April 2018, which the Appeal Panel have reviewed carefully, clearly discloses that Mr Changizi stated that he was ready to proceed if required to do so.
We have concluded that the Senior Member erred in dismissing the proceedings without clearly putting the Homeowner (through its representative, Mr Changizi) to its election whether to proceed with the matter without legal representation or to have the proceedings dismissed for want of prosecution. In circumstances where the Homeowner may have been able to recommence its action, it may be that the Homeowner would have been better advised to elect to have the proceeding dismissed. Nevertheless Mr Changizi was not given that option. He explicitly stated that he was willing to proceed if required to. The consequences of the adoption of that course, that is proceeding with the hearing, may very well have been that the Homeowner's case was fatally damaged by the unavailability of its expert witnesses, but that likely consequence did not warrant the dismissal of the proceedings if Mr Changizi was prepared to proceed.
The Appeal Panel do not accept the Builder's submission, that proceeding with the hearing of the Homeowner's case was not a practical option.
Accordingly the Appeal Panel consider that the order dismissing the proceedings should be set aside and the application remitted to the Tribunal for determination.
As we conclude that the Senior Member failed to apply the correct test in determining to dismiss the proceedings for want of prosecution, it is not necessary to address the other grounds of appeal. It is sufficient for the Appeal Panel to note that it is not persuaded that the Senior Member failed to accord procedural fairness or that there was any basis upon which it could find there was apprehended bias.
The Appeal Panel tends to the view that the Senior Member's reasons did not adequately set out the findings on material questions of fact or refer to the evidence on which the findings were based. However the Appeal Panel does not reach a final conclusion on this issue.
The Appeal Panel recognises that the effective result of the order it proposes to make is that the Homeowner will have the opportunity to rely upon its expert evidence and will effectively have obtained the benefit of the adjournment it was properly refused. However, that result was, at least in part, a consequence of the Builder's decision to make an oral application for the dismissal of the Homeowner's Application and to press for dismissal. The Builder was represented by experienced Counsel who, no doubt, considered it was in the client's interest to take that course. Had the Builder declined to support or actually opposed the Tribunal's proposal to dismiss the proceedings and rather press for the hearing to proceed on the day, we have no doubt that the Tribunal would have followed that course.
The Builder indicated that it sought to be heard on the question of costs in the event that the appeal were upheld. Accordingly the Appeal Panel will make orders providing for the parties to provide written submissions in respect of costs.
Our orders will be:
1. Grant leave to appeal.
2. Allow the appeal.
3. Set aside the orders made by Senior Member G Meadows on 9 April 2019 dismissing the application.
4. Remit the application to the Consumer and Commercial Division of the Tribunal for hearing on such evidence as the Tribunal may permit.
5. Any application in respect of the costs of the appeal to be made by written submissions filed and served within 14 days of the date of publication of this decision. Such submissions should address the question whether the application for costs can be dealt with on the papers and without a hearing pursuant to s 50(2) of the Civil and Administrative Tribunal Act.
6. If either party files submissions in accordance with order 5 above the other party may file and serve submissions in response within a further 14 days. Such submissions should address the question whether the application for costs can be dealt with on the papers and without a hearing pursuant to s 50(2) of the Civil and Administrative Tribunal Act.
[6]
I hereby certify that this is a true and accurate record of the reasons for decision of the New South Wales Civil and Administrative Tribunal.
Registrar
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Registrar
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 04 June 2019