Delay in bringing application
79 Since at least October 2022 the parties were conferring and communicating with my chambers as to indicative trial dates for the Representation Proceedings. In December 2022 the parties inquired as to my availability for trial in 2024, and by February 2023 the months of June to August 2024 had been identified with the parties and reserved for trial. ANIP's solicitors participated in those communications and did not indicate that they had any issue with the trial dates being set. The other parties (and the Court) have therefore allocated resources and undertaken work having regard to those dates. I assume that until the question of a transfer arose, witness statements were prepared on behalf of JKC and INPEX having regard only to the matters the subject of the Representation Proceedings. I infer that some trial preparation would have been different and may have been deferred, had a transfer application been anticipated earlier.
80 The existence of the Insurance Proceedings in the Supreme Court was a matter of public record. The evidence relied upon by ANIP in this application includes evidence that the Supreme Court provided copies of the writs in the Insurance Proceedings to ANIP's solicitors in December 2020. The indorsements in the respective writs reveal that the ramifications of the use of I228 were in issue. They provide:
The plaintiff:
…
(b) claims, from each of the defendants, in the proportions set out in [an attached table]:
1. an indemnity in accordance with the Basis of Settlement (as defined in the Policy, including costs as referred to in Insuring Clauses 1.4 and 1.7), against Damage (as defined in the Policy) to Insured Property (as defined in the Policy) occurring during the Construction Period (as defined in the Policy) and/or in respect of the Defects Liability Period (as defined in the Policy) from any cause whatsoever not excluded under the Policy including defects of material, workmanship, design, plan or specification in relation to the:
i. Intertherm 228 coating system;
…
used on the Project (as defined in the Policy); and
2. reimbursement of its Additional Costs and Expenses … incurred by the plaintiff from any cause whatsoever not excluded under the Policy including defects of material, workmanship, design, plan or specification in relation to the:
i. Intertherm 228 coating system;
…
used on the Project (as defined in the Policy); and
…
81 The existence of the Insurance Proceedings was referred to by this Court by at least October 2021: JKC Australia LNG Pty Ltd v AkzoNobel NV (No 3) at [23] and referred to in the orders.
82 Mr Timothy Donisi, special counsel at Clayton Utz, provided an affidavit on behalf of ANIP and said that in about February 2022 he sought copies of additional pleadings in the Insurance Proceedings from the Supreme Court, which were provided in July 2022. He deposed that:
As I now understand from reviewing the statement of claim filed in these actions (referred to in paragraph 19 below), CIV 1620 and CIV 1631 involve claims by INPEX Operations Australia Pty Ltd (INPEX), the First Applicant in INPEX v ANIP, against its insurers under a Construction All Risks insurance policy pertaining to construction of the Ichthys Onshore Project.
83 Mr Donisi also refers to the need to retain new senior counsel in November 2022, and communications between Clayton Utz and Corrs in March 2023 about the prospect of the matters being determined by the same judge.
84 Whilst I accept that the detailed nature of the Insurance Proceedings may not have been known to ANIP until it received the pleadings in July 2022, in my view it was readily apparent from December 2020, when copies of the writs were received, that there was a prospect of overlap in the proceedings, it being identified in those writs that the Insurance Proceedings related to I228 and the Project. In any event, the majority of the pleadings were received in July 2022.
85 There was then a period of time that passed between receipt of those pleadings and the communications with this Court about listing the Representation Proceedings for trial. If there was an identified concern about inconsistencies and overlap, it is surprising that it was not raised at that time.
86 I take into account the exigencies of the availability of senior counsel. However, there was a lengthy delay between when the risks that ANIP now seeks to rely upon could have been relevantly identified and acted upon, and when the transfer application was filed. During that period ANIP participated in the listing of the Representation Proceedings for trial. Significant work has been undertaken by the parties in the intervening period directed at facilitating the trial, as discussed at [39]-[40] above.
87 It is no answer to say that all the work that has been undertaken to date would be necessary even if the Representation Proceedings are transferred. I accept that some work would have been required regardless. But if the matters become intertwined by being heard together or managed together, there is a real risk that the parties in the Representation Proceedings will become participants in a more complex action with additional and different features, and will be required to repeat, revise or reconsider work already undertaken. They have, since December 2020 and since July 2022, prepared for the case they need to meet in this Court.
88 If INPEX and JKC had known that they were to run a concurrent hearing of the Insurance Proceedings and the Representation Proceedings, then I accept INPEX's submission that they would have gone about preparing their evidence in a different manner. That extends to discovery and other evidence gathering tasks such as the preparation of witness statements.
89 INPEX was ultimately obliged to replace its senior counsel in the Representation Proceedings as its former senior counsel was unable to accommodate the identified dates in June 2024. That is no small thing in a matter of this size and complexity, particularly where the former senior counsel had been retained (it appears) from the commencement of the INPEX action in this Court, had signed the pleadings and had appeared in interlocutory hearings. The step of replacing senior counsel may have been unnecessary had the transfer application been foreshadowed and brought earlier. This is not a matter that would be persuasive on its own, but it nevertheless weighs in the balance.
90 All of these matters persuade me that delay is a significant factor that weights against transfer, as the parties have incurred costs having prepared their cases in this Court on a particular basis, and with a particular timeframe in mind.
91 I have taken into account ANIP's submission that INPEX delayed in bringing court proceedings in the first place, having regard to the time when events occurred, and so a delay in a determination of all proceedings should not be considered real prejudice.
92 It is public knowledge that INPEX and JKC have engaged in an international arbitration process and have entered into a settlement deed (JKC Australia LNG Pty Ltd v AkzoNobel NV (No 3) at [22]; JKC Australia LNG Pty Ltd v AkzoNobel NV (No 4) at [9]-[13]). Remediation works have been undertaken. The delay in commencing court proceedings is not to be viewed in isolation. Nor do I see past delay as justifying further delay. There is no simple answer to how delay is to be weighed in this case. There may well be unforeseen delays that now occur in the Representation Proceedings. There is no doubt that issues such as the time required to write a judgment in a matter of this size and the prospect of appeal(s) deny the possibility of giving an accurate indication of when the proceedings in this Court might be finalised. This does not justify interrupting the current momentum directed at conducting the trial in 2024.
93 Finally on this point, I note ANIP's submission that if delay is treated as pivotal, it is used as if to punish a party. That is not my intention. This is not about punishment. It is about addressing the circumstances in which the parties and the Court find themselves at the moment - and that includes taking into account the fact that the transfer application could have been brought or anticipated earlier, and in the meantime, the parties have proceeded to prepare for a trial commencing in June 2024 and have deployed costs and resources accordingly.