INPEX Operations Australia Pty Ltd v AkzoNobel NV
[2023] FCA 382
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2023-04-26
Before
Smith J
Catchwords
- PRACTICE AND PROCEDURE - discovery - where categories of documents largely agreed by Redfern schedule in complex litigation - seven categories disputed - respective applications allowed in part
Source
Original judgment source is linked above.
Catchwords
Judgment (20 paragraphs)
- The parties provide short minutes of order to Chambers giving effect to these reasons by 4.00 pm on 11 May 2023.
- Any party wishing to make a submission as to the costs of the discovery applications is to file and serve a submission of no more than three pages in length within 14 days.
- Any submission in response to a submission filed in accordance with order 2 is to be of no more than three pages in length, and is to be filed and served within 14 days thereafter.
- Liberty to apply. Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
BANKS-SMITH J: 1 This proceeding was instituted by INPEX Operations Australia Pty Ltd and Ichthys LNG Pty Ltd. INPEX is the operator of the Ichthys LNG Project, and Ichthys is responsible for its development. INPEX relevantly acts on behalf of Ichthys. 2 The Ichthys LNG Project is a large liquefied natural gas project, involving the extraction of gas and condensate from the Ichthys Field in the Browse Basin of Western Australia, which is then transported 890 km by undersea pipeline to the Ichthys Onshore LNG Facilities at Bladin Point in the Northern Territory for conversion into LNG for export. 3 INPEX entered into a contract with JKC Australia LNG Pty Ltd for JKC to undertake certain engineering, procurement, supply, construction and commissioning for the Ichthys onshore project. 4 Relevantly, one of JKC's tasks under the contract was to develop coating specifications for pipework and equipment as necessary for the scope of its works. After various communications with one or both of AkzoNobel NV and International Paint Limited, JKC directed suppliers to use a particular coating system known as Intertherm 228 (I228) on pipework and equipment modules. Following the use of I228, degradation and decolourisation issues arose with respect to the coated pipework and equipment. 5 JKC commenced proceedings in this Court against AkzoNobel and International Paint (WAD 448 of 2017) (JKC proceeding). The pleaded claim relates to the communications, selection and use of I228. 6 Separately, INPEX issued these proceedings relating to the use of I228 against AkzoNobel, International Paint and Akzo Nobel Pty Limited (Akzo Australia) (INPEX proceeding). Those respondents have brought a cross-claim in the INPEX proceeding against INPEX, Ichthys and JKC. 7 The JKC proceeding and the INPEX proceeding are now being case managed together and the trials, provisionally listed during 2024, will be heard together. 8 In the JKC proceeding the parties implemented a document disclosure regime by way of a Redfern schedule. I was asked to determine disputes on two occasions with respect to a number of categories of documents. Orders were made with reasons published to the parties by way of commentary and comments on the Redfern schedule. The schedule and reasons have been made available to the parties in the INPEX proceedings. 9 Separately, in the INPEX proceedings the parties also entered into a document disclosure regime by way of a Redfern schedule. Despite attempts to narrow the issues, it was necessary to conduct a hearing to hear submissions about the scope of the proposed discovery. 10 After the hearing a further iteration of the schedule was produced (dated 23 September 2022), culminating in an outcome where only seven categories remain in dispute. 11 Those categories are the subject of these reasons. 12 I have adopted the headings and definitions used by the parties. The disputed discovery requests are set out in full as formulated in the revised schedule.