The applicant was the holder of a substantial parcel of land (16.3 hectares) at 105 Hoys Road, Moonee Beach (the land). The land was rezoned for public purposes. The land thus fell within the provisions of s 21(1)(a) of Pt 2 Div 3 (the hardship provisions) of the Land Acquisition (Just Terms Compensation) Act 1991 (NSW) (the Act).
The applicant gave notice under s 23 of the Act, requiring the Council to acquire the land. Section 25 of the Act provides that land acquired under the hardship provisions is to be acquired by compulsory process. The applicant was offered compensation in the amount of $3,180,000 but objected to this amount as she was entitled to do by virtue of s 66 of the Act. The commissioners who heard the objection ordered that she be compensated in the amount of $2,034,957.39. Her appeal was rejected and she has now sought leave to appeal to this Court.
To understand the nature of the application it is necessary to set out some of the relevant legislation.
As I indicated, Pt 2 Div 3 of the Act deals with acquisition in the case of hardship. Section 23 provides that an owner who suffers hardship may require the relevant authority to acquire land designated for acquisition. So far as is relevant, it provides as follows:
"23 Owner who suffers hardship may require authority of the State to acquire land designated for acquisition
(1) The owner of land to whom this Division applies may require an authority of the State, by notice in writing given to that authority, to acquire that land under this Act if:
(a) the land is designated for acquisition by that authority for a public purpose, and
(b) the owner considers that he or she will suffer hardship if there is any delay in the acquisition of the land under this Act.
(2) The authority of the State must (subject to this Division) acquire the land within 90 days after the owner gives that authority notice under this section (or such longer period as that authority and the owner may agree on in writing)."
Section 24 provides for circumstances where the authority is not required to acquire the land. So far as is relevant, it is in the following terms:
"24 Hardship
(1) An authority of the State is not required to acquire land under this Division unless it is of the opinion that the owner will suffer hardship (within the meaning of this section) if there is any delay in the acquisition of the land under this Act."
Section 25 deals with the method of acquisition under the Division. It provides as follows:
"25 Method of acquisition under this Division
(1) Land required to be acquired under this Division is to be acquired by compulsory process.
(2) However, nothing in this Division prevents the land concerned from being acquired by agreement instead of compulsory process within the period required by this Division.
(3) Division 1 (Pre-acquisition procedures) does not apply to an acquisition of land under this Division."
Section 26 contains at least a potential limitation on the amount of compensation that can be awarded for the acquisition. It is in the following terms:
"26 Compensation for acquisition under this Division
The special value of land, any loss attributable to severance or disturbance and solatium (as referred to in Part 3) need not be taken into account in connection with an acquisition of land under this Division, despite anything to the contrary in that Part."
These provisions essentially provide that an owner whose land has been designated for public purpose can, in effect, accelerate the acquisition process by requiring the relevant authority to acquire the land. Once the process of acquisition has been set in train, the Valuer-General under s 47 of the Act is required to determine the amount of compensation to be offered. Division 4 of Pt 3 of the Act deals with the determination of the amount of compensation. The following provisions are of relevance:
"54 Entitlement to just compensation
(1) The amount of compensation to which a person is entitled under this Part is such amount as, having regard to all relevant matters under this Part, will justly compensate the person for the acquisition of the land.
…
55 Relevant matters to be considered in determining amount of compensation
In determining the amount of compensation to which a person is entitled, regard must be had to the following matters only (as assessed in accordance with this Division):
(a) the market value of the land on the date of its acquisition,
(b) any special value of the land to the person on the date of its acquisition,
(c) any loss attributable to severance,
(d) any loss attributable to disturbance,
(e) solatium,
(f) any increase or decrease in the value of any other land of the person at the date of acquisition which adjoins or is severed from the acquired land by reason of the carrying out of, or the proposal to carry out, the public purpose for which the land was acquired.
56 Market value
(1) In this Act:
market value of land at any time means the amount that would have been paid for the land if it had been sold at that time by a willing but not anxious seller to a willing but not anxious buyer, disregarding (for the purpose of determining the amount that would have been paid):
(a) any increase or decrease in the value of the land caused by the carrying out of, or the proposal to carry out, the public purpose for which the land was acquired, and
(b) any increase in the value of the land caused by the carrying out by the authority of the State, before the land is acquired, of improvements for the public purpose for which the land is to be acquired, and
(c) any increase in the value of the land caused by its use in a manner or for a purpose contrary to law.
(2) When assessing the market value of land for the purpose of paying compensation to a number of former owners of the land, the sum of the market values of each interest in the land must not (except with the approval of the Minister responsible for the authority of the State) exceed the market value of the land at the date of acquisition.
…
59 Loss attributable to disturbance
(1) In this Act:
loss attributable to disturbance of land means any of the following:
(a) legal costs reasonably incurred by the persons entitled to compensation in connection with the compulsory acquisition of the land,
…
60 Solatium
(1) In this Act:
solatium means compensation to a person for non-financial disadvantage resulting from the necessity of the person to relocate his or her principal place of residence as a result of the acquisition."
In her appeal to the primary judge, the applicant challenged three principal aspects of the commissioners' decision. The first was the approach taken by the commissioners to what was described in the commissioners' valuation as "the residual lot", being that land subject to constraints (the residual lot). The commissioners stated that the residual lot had the following constraints for development purposes:
" • flood prone land,
• tertiary koala habitat,
• sedgelands in the north of the site,
• State forest property to the north of the site,
• bushfire Asset Protection Zone setbacks,
• sight distance constraints on part of Old Bucca Road,
• contamination of a small part of the site, and
• acoustic treatment requirements for land near the highway frontage."
[2]
The commissioners concluded that the balance of the land, excluding the residual lot, could be subdivided into 106 lots, each having a value of $18,000. The commissioners determined that the residual lot only had nominal value. Having regard to their conclusion on the total market value of the land, it is evident, as a matter of mathematics, that they attributed a value of $72,000 to the residual lot.
The second issue was described in some parts of the hearing as "the hypothetical development valuation approach" issue and on other occasions as "the steep land" issue. As it emerged ultimately in argument, it appeared to relate to a failure to adjust for differences in development costs caused by the difference in topography of potential comparable sales.
The third issue involved the construction of s 59(a) of the Act, namely, whether the legal costs incurred in establishing hardship were disturbance costs within the meaning of that provision.
Although the commissioners made allowance for disturbance and solatium, the Council contended that the effect of s 26 of the Act was that the applicant was not entitled to any allowance for those matters. This was the subject of a cross-appeal before the primary judge and the subject of an application for leave to cross-appeal in these proceedings.
In considering these issues, it is important to bear in mind that the appeal to the primary judge and any appeal to this Court is limited to an appeal against an order or decision on a question of law. In ISPT Pty Ltd v Valuer-General [2009] NSWCA 31, Allsop P (as his Honour then was) summarised the nature of the process in the following terms:
"[3] The nature of this process was discussed at length in Maurici v Chief Commissioner of State Revenue [2001] NSWCA 78; 51 NSWLR 673 and B & L Linings Pty Ltd v Chief Commissioner of State Revenue [2008] NSWCA 187 at [57]-[79]. It is the 'decision' not the 'appeal' which must be on a question of law: B & L Linings at [70], citing Roads and Traffic Authority of New South Wales v Peak [2007] NSWCA 66 at [139]. Such an appeal is 'on' a question of law, not limited, however, 'to an error of law': Mir Bros Unit Constructions Pty Ltd v Roads and Traffic Authority of New South Wales [2006] NSWCA 314 at [27]; and see Peak at [139]."
In the Court below, the primary judge criticised the approach taken by the applicant in her summons, in particular, what her Honour described as "a scatter-gun approach" to the identification of questions of law: Primary Judgment at [17]. This criticism, in my opinion, was justified. The summons in the Court below asserted that the commissioners committed six errors of law, each being expressed in entirely general terms with numerous sub-grounds referring mainly to factual matters said, by reason of the absence of supporting evidence or a failure to deal with certain matters, to constitute errors of law. No attempt was made, at least with any precision, to identify the question or questions of law involved in the appeal.
The draft notice of appeal filed in connection with the present application asserts a number of discrete errors of law, once again, in the main, amounting to assertions that there was no evidence or reasoning to support the commissioners' conclusions or that there was a failure to grapple with conflicting evidence on particular issues. Although such matters can constitute errors of law (see Kostas v HIA Insurance Services Pty Ltd [2010] HCA 32; 241 CLR 390 (Kostas) at [90]; Pollard v RRR Corporation [2009] NSWCA 110 (Pollard) at [58]-[59], [65]; Redbro Investments Pty Ltd v Ceva Logistics (Australia) Pty Ltd [2015] NSWCA 73; 89 NSWLR 104 (Redbro) at [53]; Segal v Waverley Council [2005] NSWCA 310; 64 NSWLR 177 at [43], [66]-[69]; Murray v Sheldon Commercial Interiors Pty Ltd [2016] NSWCA 77 at [60]-[63]), care must be taken that the evaluation of these grounds does not involve a rehearing on the merits as distinct from consideration of a question of law which vitiates the decision. Such a question can include a question of mixed fact and law: Maurici v Chief Commissioner of State Revenue [2002] HCA 8; 212 CLR 111 at [8]; Kostas at [25].
[3]
The first issue
What I have described as the first issue is the subject of Grounds 1 to 3 of the draft notice of appeal. Those grounds are in the following terms:
"1 The primary judge erred in law in determining that the Commissioners had not constructively failed to exercise jurisdiction in relation to the value of the residue lot.
2 The primary judge erred in law when she found no legal error in the Commissioners' determination despite the fact that there was no evidence that the market value of the residue lot was $72,000.
3 The primary judge erred in law when she herself failed to deal with the applicant's argument on appeal that there was no sufficient logic or apparent reasoning or evidence to support the conclusion of the Commissioners that the market value of the residue lot was $72,000."
The primary judge referred to the commissioners' findings on the constraints on the land, to which I have referred above at [11], and set out the findings of the commissioners on the residual lot. These findings were in the following terms:
"The rural residential lot / Biobanking
[52] The residual lot is generally that part of the Land identified on Map 4 of DCP 2004 as having constraints. Mr Connelly describes that part of the Land as a rural residential lot with a dwelling house entitlement and as the BioBanking lot, given the nature of the land and its mainly 1:100 year flood inundation characteristics. Mr Connelly explains that BioBanking is a market-based scheme that provides a streamlined biodiversity assessment process for development, a rigorous and credible offsetting scheme as well as an opportunity for rural landowners to generate income by managing land for conservation.
[53] Mr Ryan referred to the requirements under Natural Environment Strategy in DCP 2004 where it states:
All areas to be protected are to be dedicated to Council as development occurs.
[54] While not disputing that the residue could be used as a rural residential lot with a dwelling house entitlement, Mr Ryan maintained that, given the identified constraints and the absence of any studies to address those constraints, the question whether it could be used, as suggested by Mr Connelly, is not able to be answered at the time of the hearing.
[55] On the matter of the DCP requirement that constrained lands are to be dedicated to council, Mr Hemmings explained in his submissions that the council could not require the constrained area to be dedicated to the council free of charge as this would be contrary to s 94 of the EPA Act. There would be no condition of consent requiring this in any consent. However, if the prospective purchaser viewed the residue land as an unacceptable burden in the development of the Land, then it could be dedicated to the council at no cost.
[56] Mr Hemmings identifies four possible scenarios for the residual lot:
1. council could acquire the land,
2. the developer could dedicate the land free of cost,
3. the land could be included as part of a large residue lot, and
4. the developer could 'get stuck' with the land.
[57] While the particular scenario likely to be chosen by a prospective purchaser is difficult to determine, we prefer scenario 3 for a number of reasons. First, the evidence of Mr Ryan and Mr Connelly that the potential does exist for the residue lot to be used as a rural residential lot with a dwelling house entitlement. Mr Ryan's support was however conditional on the completion of a number of studies to address the constraints identified in Map 4 of DCP 2004. Second, this approach is consistent with the 'just compensation override' described by Biscoe J in Al Amanah College Inc v Minister for Education [2011] NSWLEC 254 at [10].
[58] In coming to this conclusion, we find that the constraints identified in Map 4 of DCP 2004 could severely restrict this potential or at worst, deny the opportunity for any development. To realise any potential of the residual lot, the preparation of a number of studies would be necessary and there is no certainty that the residual lot is capable of gaining approval for a rural residential lot with a dwelling house entitlement. In accepting that the residue land must have some value, we find that the amount should only be a nominal amount given the uncertainty of any approval..."
The primary judge, having reviewed the principles governing an appeal against an order or decision on a question of law in a manner not the subject of any criticism, considered that the attribution of value of $72,000 to the residual lot did not involve an error of law. Her Honour expressed her conclusion in the following terms:
"[38] The judgment must be read as a whole. As the Council identified in submissions summarised above at par 30-32, the Commissioners set out the evidence and submissions concerning the planning issues related to the rural residential lot at [52]-[58]. They identify the evidence of both planners and explain their approach in accepting that a rural residential lot could be subdivided, a finding in the Appellant's favour. They also explain why they consider the constraints on the land meant that it has nominal value, at [58]. As this issue was largely determined on the planning evidence there was no need to consider in much detail the valuation evidence. The Council's submissions summarise the references to the valuation evidence on this topic, identified at [111]-[112] for Mr Paris. Mr Davis had no comparable sales as he considered the land would be given to the Council at no cost, at [106]. The Commissioners considered the sales evidence unsatisfactory and came to their conclusion at [168] that the residue lot could be included as part of a large constrained lot of nominal value only. There was no failure to grapple with evidence or refer to an essential issue, nor does the reasoning disclose irrationality. Redbro has no application here. Nor do the authorities such as Ballantyne or Goodwin v Commissioner of Police which concern a failure to exercise jurisdiction by a court apply."
Senior counsel for the applicant submitted that there were two errors of law involved in the commissioners' decision. He submitted that the commissioners first, refused to pay any regard to evidence which he described as "all one way", to the effect that the residual lot could be developed as a rural residential lot for housing, and second, refused to pay any regard to evidence that, even if fully constrained, the land was worth more than $72,000.
In her written submissions, the applicant pointed to the fact that the valuer engaged by her, a Mr Paris, adduced what were described as comparable sales of large residential lots, whilst noting the evidence of the valuer engaged by the Council, Mr Davis, that the land had no value. In that context, it should be noted that the commissioners referred to the contention of Mr Paris that the residual land had value and referred to the four comparable sales of residual parcels to which Mr Paris referred: Commissioners' Determination at [99], [105]. They pointed to the fact that Mr Paris referred to adjustments or "location, topography, access, date of sale, zoning, inter alia" without providing details: at [120]. They further noted that Mr Paris asserted without explanation "a rate of $300,000 for application to the rural home site at the subject property": at [125]. The commissioners' ultimate conclusion was in the following terms:
"[168] Concerning the residue lot, while the evidence tendered was insufficient to facilitate effective adjustment of the analysed rates per hectare, our conclusion that the residue land could be included as part of a large constrained lot of nominal value only renders such adjustment unnecessary."
The applicant complained, without elaboration, that this approach failed to address her case, namely, that lots of the nature of the residual lot were sold on a per lot basis rather than a per hectare basis. It is not clear how this was said to be an error of law, much less vitiate to the decision, particularly in circumstances where the balance of the land was valued on a per lot basis and the commissioners concluded that the residual lot had only nominal value, the evidence being that, at most, it could only support a single dwelling: see below at [26].
Senior counsel for the applicant accepted that the commissioners rejected the evidence of Mr Paris on the residual lot, but stated that even if the commissioners were entitled to reject his analysis and conclude that the land was fully constrained, they did not take into account two other sales of properties which were said, without any supporting expert valuation evidence, to be comparable.
The applicant also submitted that, before the commissioners, she had submitted that "the evidence in favour of the approval of a residue lot capable of being developed with a dwelling house was all one way". Senior counsel for the applicant acknowledged that the commissioners referred to the evidence of Mr Connelly and Mr Ryan where they said it may be possible that the constrained land could support a dwelling house: Commissioners' Determination at [52]-[58]; see above at [20]. Mr Connelly and Mr Ryan were town planners, the former being engaged by the applicant, the latter by the Council. Senior counsel for the applicant referred, in particular, to the cross-examination of Mr Ryan where he stated that the residual lot had the potential to be so developed and submitted that the commissioners ignored this evidence.
Finally, the applicant submitted that there was no evidence to support a finding that the residual lot had a value of $72,000 and the commissioners erred in arriving at that figure.
[4]
Consideration
It is well-established that a decision reached in the absence of evidence to support it constitutes an error of law: Kostas at [91]-[92]. Further, a tribunal will err in law if it fails to deal with or give consideration to the cases presented by the parties or prefers one piece of conflicting evidence over another without giving reasons for doing so: see Redbro at [53]; Pollard at [66]. Whether a decision is vitiated by these matters does involve a question of law.
However, in the present case, the commissioners considered the evidence and explained the reasons for their conclusions. They accepted the evidence of Mr Davis that the residual lot had no value and rejected the competing evidence of Mr Paris for the reasons I have summarised above at [23]. It could not be said that the commissioners failed to deal with the competing valuation evidence.
Further, the commissioners, in the paragraphs of their decision which I have set out above at [20], also considered and accepted the town planning evidence that there was potential to develop the residual lot as a rural/residential lot. However, for the reasons given at [58] of their determination, they considered that notwithstanding that potential, the lot had only nominal value. In reaching this conclusion, they considered the evidence and explained their reasons. There was no error of law involved in the approach they took.
The other error of law was said to be the attribution by the commissioners of a value of $72,000 to the residual lot. It was submitted that there was no evidence to support this valuation.
In that context, it is important to remember that the task of the commissioners was to value the land, of which the residual lot only formed part. They concluded that the total value of the land was $1,980,000. As I indicated above at [12], having regard to the valuation of the 106 lots, they attributed a value of $72,000 to the residual lot.
As with the subject of the first aspect of this ground of appeal, the commissioners considered the evidence and concluded the residual lot had nominal value. This left them with the task of either concluding that it did not increase the value of the overall parcel or giving some limited value to it. In what was essentially a matter of judgment consequent on their conclusion that the land had nominal value, the commissioners ascribed $72,000 to the residual lot in determining the total value of the land. There was no error of law in arriving at this conclusion, which was, on one view, generous to the applicant.
The primary judge dealt with this issue in her judgment in a similar manner: Primary Judgment at [38]. Whilst it may be that the draft grounds of appeal on this issue raised a question of law, there was no error in the conclusion reached by her Honour. There is no merit in these grounds of appeal.
[5]
The second issue
This issue is the subject of Grounds 4, 5 and 6 of the grounds of appeal. Those grounds are in the following terms:
"4 The primary judge fell into error of law when she failed to deal with the appeal ground that the cost of developing steep land was a necessary adjustment to be made when valuing the land at Ainslie Drive, Korora.
5 The primary judge erred in not determining that the Commissioners had failed to grapple with evidence or constructively failed to exercise jurisdiction in relation to the engineering evidence as to the costs of developing steep land in relation to the comparable sales.
6 The primary judge fell into error when finding that leave was required to argue the matters in Grounds 4 and 5 above."
In the Court below, the applicant sought to rely on the following grounds of appeal relating to this issue:
"4 The Commissioners acknowledged that they did not consider the evidence concerning the hypothetical development valuation approach [98] because they said the approach was not addressed in any detail at the hearing. However:
a. Evidence was called by the appellant addressing that approach in particular of the costs of developing steep land and the fact that Mr Davis['] sales analysis was potentially wholly undermined by that evidence;
b. The Commissioners were obliged in law to canvass that evidence and give a reasoned judgement [sic] taking that evidence into rational account; and
c. The Commissioners failed thereby to take into account relevant evidence and give an adequately reasoned judgement [sic]."
In the written submissions in the Court below, the following submissions were made in support of this ground:
"72. In relation to this appeal ground, many of the principles referred to in relation to the first appeal ground are relevant again to this ground.
73. Cases such as Ballantyne, Bredbo, Beale, Kostic and Fitzgibbon all referred to above deal with the issue that the trier of fact's responsibility is to resolve contested issues and set out his reasoning in respect of those issues.
74. In this case, there were two methods of valuation addressed by both of the valuers. The first was a direct sales comparison approach of en globo subdivision land. The second was a hypothetical development method of valuation. This latter method, sometimes called the residual value analysis, show the value of land determined by the cost to develop it against the profit to be made after its development (see W and H Carter v Roads and Traffic Authority of NSW [2006] NSWLEC 89 at [92]ff).
75. In this case, the Commissioners acknowledge that they did not consider the evidence concerning the hypothetical development valuation approach (at [98]) because they said the approach was not addressed in any detail at the hearing. However:
(a) Evidence was called by the appellant addressing that approach in particular of the costs of developing steep land and the fact that Mr Davis['] sales analysis was potentially wholly undermined by that evidence;
(c) The Commissioners were obliged, based on those principles set out extensively above, to canvass that evidence and give a reasoned judgement [sic] taking that evidence into rational account. They did not, and accordingly failed to take into account relevant evidence, grapple with the contested evidence and give an adequately reasoned judgement [sic].
76. That is, in the appellant's submission, another vitiating error."
The primary judge refused leave to argue this ground. In her judgment, she noted that the hypothetical development valuation approach was not relied on before the commissioners and the applicant could not complain that the commissioners did not deal with it: Primary Judgment at [51].
In argument on this issue in the Court below, senior counsel for the applicant said that "the heading might be the Hypothetical Development Method but the argument which we're addressing was a subset of the hypothetical development method". The primary judge stated that, having regard to the written submissions, that was not the basis on which the argument was put forward and invited senior counsel for the applicant to seek to amend the summons. The applicant, after consideration, decided not to seek leave to amend.
To illustrate the nature of what was sought to be argued, the applicant, in her written submissions, argued that the commissioners found that certain land at Ainslee Drive, Korora, was an "indirectly relevant" comparable property and made an adjustment for topography, but failed to analyse engineering evidence concerning the cost of developing that land or make any adjustment that took account of the engineering evidence concerning that cost. It should be noted that senior counsel for the applicant conceded that neither of the expert valuers using the hypothetical development method as a check on their valuation found it necessary to undertake this task.
[6]
Consideration
Each party accepted that the grounds of appeal the subject of this issue raised the same issues as Ground 4 in the grounds of appeal below. The primary judge was said to have erred in refusing leave to argue this ground. The primary judge took the view, having read the grounds of appeal and the submissions in support, that the challenge was that the commissioners had erred in failing to consider the hypothetical development method of valuation. In my respectful opinion, to the extent that Ground 4 of those grounds could have been read to be wider than an assertion of a failure to consider that method of valuation, the submissions in support were clearly limited to that issue.
When, in argument, it emerged that what was sought to be argued was wider than that which was suggested by the grounds of appeal and the written submissions, the primary judge sensibly invited the applicant to amend her summons. This may have clearly articulated the issue sought to be argued so that further consideration could be given as to whether it was appropriate to permit it to be raised. The appellant having declined the invitation to amend, it was appropriate for her Honour to refuse leave. No error of discretion was demonstrated and leave to appeal on these grounds should be refused.
[7]
The third issue and the cross-appeal
The ground of appeal dealing with this issue is in the following terms:
"7 The primary judge erred in law in the construction of s 59(a) of the Land Acquisition (Just Terms Compensation) Act 1991 such that legal costs incurred in connection with establishing that the Applicant was suffering hardship to the Council's satisfaction were not disturbance costs incurred by the Applicant 'in connection with the compulsory acquisition of the land'."
In support of an application for leave to cross-appeal, the Council contended that, having regard to the provisions of s 26 of the Act, it was an error of law to make any allowance for disturbance costs or solatium, including, but not limited to, the legal costs the subject of the ground of appeal.
The primary judge, in rejecting both the applicant's appeal on legal costs and the cross-appeal, stated that a textual analysis of the words of s 26 showed that they are not ambiguous and that the words "need not" confer a discretionary power on the State or the Court on appeal to make allowance for disturbance costs or solatium: Primary Judgment at [121]. However, she concluded that s 59 of the Act did not extend to legal costs incurred in the making of a hardship application: at [126].
In relation to the cross-appeal, senior counsel for the Council pointed to the fact that s 25 required the land acquired under the hardship grounds to be acquired by compulsory process and that under s 47, it was the Valuer-General who determined the compensation payable. He submitted that the Council, which exercises the discretion to acquire on the hardship grounds, has, in those circumstances, no opportunity to decide whether it will give any allowance for the matters referred to in s 55. Senior counsel for the Council submitted that it would be unusual to vest in the Valuer-General a discretion as to whether or not particular amounts are payable or not as distinct from determining the appropriate amount of compensation in accordance with Pt 2 Div 3 of the Act.
In relation to the legal costs the subject of the appeal, the Council submitted that the costs predated the acquisition process and, in those circumstances, were not connected with an acquisition. The Council submitted that there is no entitlement to compensation until a decision to acquire is made and, as such, legal costs in respect of hardship applications cannot fall within s 59(a) of the Act.
The applicant submitted that the legislation should be interpreted in such a way as to protect the interests of persons whose property interests are affected by compulsory process in favour of the interests of the acquiring authority: Cumerlong Holdings Pty Ltd v Dalcross Properties Pty Ltd [2011] HCA 27; 243 CLR 492 (Cumerlong Holdings) at [33]-[34]. Second, she submitted the words "need not" indicated a choice by the legislature of discretionary words in contrast to the words "must" or "may", which appear in many other sections of the Act. Third, she submitted that the construction found by the primary judge was supported by the Second Reading Speech introducing s 26 into the Act.
So far as the question of legal costs was concerned, the applicant again emphasised the need for a liberal construction of provisions concerning compensation for compulsory acquisition, pointing out that the words "in connection with" are words of wide import. She submitted that proving hardship to the satisfaction of the State is something which leads to compulsory acquisition and so the costs of doing so were incurred in connection with it.
[8]
Consideration
It is convenient to deal with the cross-appeal first.
I have set out s 26 of the Act above at [9]. In the Second Reading Speech introducing the Act, the relevant Minister made the following remarks:
"An authority must form an opinion that the owner will suffer hardship because he is unable to sell the land at its market value, and that he needs to sell it now rather than later for either pressing personal, domestic or social reasons, or to avoid the loss of his income. Pressing personal, domestic or social reasons include situations where: the owner or his spouse has been relocated to a job in another State; the family has to relocate for health reasons; the family has outgrown its accommodation; the owner needs to move closer to sick relatives; the owner's house is too big for him now and maintenance of it is beyond his capacity. Of course, every case would need to be considered on its merits and the full range of personal, social and domestic reasons which might give rise to hardship cannot be anticipated. Alternatively, an owner may need to sell the land to avoid loss of his income where, for example, his business is in danger of insolvency and is secured against his familiar home. Once hardship is found, in assessing compensation under this division, authorities need not take into account factors other than the market value of the land. This is to be found in clause 26.
There has been some criticism of this provision. Policy rationale is that people should not force government to acquire their land unless they have a legitimate reason for needing to sell the land now rather than later. If they really need to sell, they are in the position of any other person wishing to sell property - a voluntary vendor, who would expect to pay all the usual costs associated with the sale of real property, such as relocation costs and so on. However, section 26 gives an authority some discretion in assessing these additional heads of compensation. If an owner has to move for personal, domestic or social reasons - for example, a job relocation - it may not be appropriate for an authority to offer him special value, severance, disturbance or solatium because his move is for reasons other than the blight on his land. It is conceivable, however, that there may be situations which would warrant an authority exercising its discretion to pay one or more of these additional heads of compensation. Because all the problems and circumstances of landholders cannot be anticipated, the bill has this inbuilt flexibility to ensure fairness."
As was stated in Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue [2009] HCA 41; 239 CLR 27, the task of statutory construction must begin with a consideration of the text itself, although the meaning of the text may require consideration of the context, which includes the general purposes and policy of the provision in question: at [47]; see also Commissioner of Taxation v Consolidated Media Holdings Ltd [2012] HCA 55; 250 CLR 503 at [39]. Context and purpose are important as the task of the Court is to give the words the meaning the legislature is taken to have intended them to bear. Such purposes can be inferred from the statute itself and, where appropriate, by reference to extrinsic material. However, in making use of such extrinsic material, it must be remembered that such material can only be used as an aid to statutory construction, not for the purpose of identifying the subjective purpose or intention of the legislature: Certain Lloyd's Underwriters v Cross [2012] HCA 56; 248 CLR 378 at [23]-[26]; Project Blue Sky v Australian Broadcasting Authority [1988] HCA 28: 194 CLR 355 at [69]-[71], [78].
In the present case, the issue is whether the words "need not" in s 26 of the Act require the valuing authority, in determining compensation in respect of an acquisition initiated through the hardship provisions, to make no allowance for the special value of the land or any loss attributable to severance or disturbance and solatium, or merely confer a discretion on the valuing authority to disregard those matters.
In my opinion, s 26 confers a discretion on the Valuer-General in determining compensation under s 47 to take the matters referred to in s 26 into account, notwithstanding that the acquisition process was activated by the hardship provisions in Pt 2 Div 3. This is for a number of reasons. First, as a matter of language, the words "need not" are appropriate to confer a discretion. Second, one of the objects of the Act is to ensure compensation on just terms for owners of land that is acquired by an authority of the State: see s 3(1)(b) of the Act. It is difficult to see how a construction of s 26 which would exclude, for example, compensation for special value to a person who is entitled to have his or her land acquired on the ground of hardship is consistent with that object. This approach, which, in my view, is discernible from the text of the Act, is consistent with what was said by the Minister in introducing the legislation.
The construction also gives effect to what was stated by Heydon J in Cumerlong Holdings at [33]-[34] that provisions of this nature should be construed generously and liberally because they are protecting the interests of those whose property rights have been damaged, in this case by the land being designated for public purposes.
The Council submitted that if s 26 conferred a discretion, the acquiring authority would have no opportunity to decide whether it would make any allowance for special value and the other matters referred to in s 55. This does not seem to me to affect the position. First, the Council does not have the opportunity when it moves to invoke the compulsory acquisition provisions itself. Second, s 25(2) of the Act makes it clear that land required to be acquired under the hardship provisions can be acquired by agreement, the acquirer thereby having the ability to negotiate what it regards as an appropriate price.
The Council also submitted that it would be unusual for a discretion to determine the matters referred to in s 26 to be conferred on the Valuer-General. I do not see why this is so, particularly when the Valuer-General is empowered to determine the quantum of non-financial disadvantage for solatium.
For these reasons, the commissioners had a discretion to make an allowance for disturbance and solatium. The cross-appeal did not suggest that there was any error in the exercise of that discretion if it existed. In those circumstances, as the matter the subject of the cross-appeal raises a question of general importance, leave to cross-appeal should be granted but the cross-appeal dismissed.
So far as the seventh ground of appeal is concerned, I do not think the power to compensate for legal costs extends to costs incurred in establishing hardship. The power to award legal costs, contained in s 59(1)(a), relates to costs incurred by a person entitled to compensation in connection with the compulsory acquisition of the land. A person is only entitled to compensation once the authority becomes bound to acquire the land, that is, in the case of a hardship application, once the pre-conditions in s 24(2) are established to the satisfaction of the relevant authority referred to in s 24(1). Legal costs incurred in establishing hardship are incurred prior to an entitlement to compensation arising and thus do not fall within s 59(1)(a).
Further, although, as the applicant pointed out, the words "in connection with" are of wide import (see for example, Claremont Petroleum NL v Cummings (1992) 9 ACSR 1 at 41-42), it does not seem to me that in the present context, costs incurred in establishing an entitlement to have the land compulsorily acquired fall within the definition. Section 59(1)(a), in my opinion, is directed to compensating persons for legal costs incurred in respect of an acquisition, whether resulting from the application of the hardship provisions or the action of the acquiring authority. It does not confer an entitlement to compensation for costs which arise prior to that time.
[9]
Conclusion
I do not consider the matters raised by Grounds 1 to 6 of the draft grounds of appeal warrant leave being granted. Further, I see no reason why, on an application of this nature, being a second appeal from a decision of the commissioners, costs should not follow the event. It follows that I would make the following orders:
1. Grant the applicant leave to appeal on Ground 7 of the draft notice of appeal filed in the proceedings, otherwise refuse leave to appeal.
2. Dismiss the appeal.
3. Order the applicant pay the respondent's costs of the application for leave to appeal and the appeal.
4. Grant the respondent leave to cross-appeal in the terms of the draft notice of cross-appeal filed in the proceedings.
5. Dismiss the cross-appeal.
6. Order the respondent pay the applicant's costs of the application for leave to cross-appeal and the cross-appeal.
SIMPSON JA: I agree with Bathurst CJ.
PAYNE JA: I agree with Bathurst CJ.
[10]
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated: 08 September 2016
[This headnote is not to be read as part of the judgment]
Ms Iris Hoy (the applicant) was the owner of a plot of land in the Coffs Harbour region. The land was rezoned for public purposes by the Coffs Harbour City Council (the Council). Part 2 Div 3 of the Land Acquisition (Just Terms Compensation) Act 1991 (NSW) (the Act) allowed for an owner, whose land had been designated for a public purpose and who will suffer hardship as a result of the delay, to accelerate the acquisition process by requiring the relevant authority to acquire the land by compulsory process.
Under Pt 3 of the Act, s 47 required the Valuer-General to determine the amount of compensation to be offered. Section 55 set out an exhaustive list of relevant considerations in determining compensation, which included the special value of the land, loss attributable to severance or disturbance and solatium. Section 59(1)(a) defined "loss attributable to disturbance" as including "legal costs reasonably incurred by the persons entitled to compensation in connection with the compulsory acquisition of the land". Section 26, under Pt 2 of the Act, stipulated that "the special value of land, any loss attributable to severance or disturbance and solatium (as referred to in Part 3) need not be taken into account in connection with an acquisition of land under this Division, despite anything to the contrary in that Part".
The applicant gave notice under Pt 2 Div 3 of the Act requiring the Council to acquire the land. She was offered compensation in the amount of $3,180,000 but objected to this amount under s 66 of the Act. Two commissioners of the Land and Environment Court heard the objection and ordered that she be compensated in the amount of $2,034,957.39.
The commissioners determined that, apart from certain land the subject of constraints (the residual lot), the land could be subdivided into 106 lots each valued at $18,000. After referring to the evidence of valuers retained by the applicant and the Council that it was possible the residual lot could be used as a rural residential lot, the commissioners determined that this possibility existed but that the constraints identified severely restricted the potential. They assigned a nominal value to the lot of $72,000 and made an allowance for disturbance and solatium.
The applicant appealed under s 56A of the Land and Environment Court Act 1979 (NSW) (LEC Act) to a judge of the Land and Environment Court (the primary judge), which was limited to an appeal from an order or decision on a question of law. The primary judge dismissed the appeal. The applicant then appealed under s 57 of the LEC Act to the Court of Appeal, which was similarly limited to an appeal from an order or decision on a question of law and required leave. The Council cross-appealed on the allowance made for disturbance and solatium.
The issues on appeal were:
Whether the primary judge erred in not finding that the commissioners failed to deal with the evidence concerning the development of the residual lot into a rural residential lot and that there was no evidence to support their valuation of the residual lot (Grounds 1-3).
Whether the primary judge erred in refusing leave to argue that the Commissioners failed to deal with engineering evidence as to the costs of developing steep land in comparable sales (Grounds 4-6).
Whether the primary judge erred in determining that legal costs incurred in establishing hardship were not disturbance costs incurred "in connection with the compulsory acquisition of the land" under s 59(1)(a) of the Act (Ground 7)
Whether, having regard to s 26 of the Act, it was an error of law to make an allowance for disturbance costs or solatium in compensating for an acquisition activated under Pt 2 Div 3 of the Act (Cross-Appeal).
The Court held (Bathurst CJ, Simpson and Payne JJA agreeing) refusing leave to appeal on Grounds 1-6 and dismissing the appeal and cross-appeal:
Valuation of residual lot
(i) An error of law may arise where a decision is reached in the absence of evidence to support it, where a decision-maker fails to deal with or give consideration to cases presented by the parties to the dispute or where the decision-maker prefers one piece of conflicting evidence over another without giving reasons for doing so. Whether a decision is vitiated by these matters involves a question of law, however, care must be taken to ensure that the evaluation of such grounds does not involve a rehearing on the merits. A question of law may include a question of mixed fact and law: [18], [28] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
Kostas v HIA Insurance Services Pty Ltd [2010] HCA 32; 241 CLR 390; Redbro Investments Pty Ltd v Ceva Logistics (Australia) Pty Ltd [2015] NSWCA 73; 89 NSWLR 104; Pollard v RRR Corporation [2009] NSWCA 110; Segal v Waverley Council [2005] NSWCA 310; 64 NSWLR 177; Murray v Sheldon Commercial Interiors Pty Ltd [2016] NSWCA 77; Maurici v Chief Commissioner of State Revenue [2002] HCA 8; 212 CLR 111 applied
(ii) Where a commissioner considers the evidence, explains the reasons for his or her conclusions and gives reasons for rejecting competing evidence, it cannot be said that the commissioner failed to deal with competing evidence: [29]-[30] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
(iii) Where a commissioner has concluded that land has nominal value, the task of ascribing a figure to that value is essentially a matter of judgment consequent upon the determination that the land has nominal value: [33] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
Refusal of leave
(iv) There is no error of discretion in refusing leave where a party seeks to argue a ground wider than that suggested by the grounds of appeal and written submissions and then further refuses, upon invitation, to amend his or her summons: [41]-[42] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
Disturbance costs
(v) The task of statutory construction must begin with a consideration of the text itself, although the meaning of the text may require consideration of the context, which includes the general purposes and policy of the provision in question. Such purposes can be inferred from the statute itself and, where appropriate, extrinsic material. However, extrinsic material can only be used as an aid to construction not for the purpose of identifying the subjective intention of the legislature: [52] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue [2009] HCA 41; 239 CLR 27; Commissioner of Taxation v Consolidated Media Holdings Ltd [2012] HCA 55; 250 CLR 503; Certain Lloyd's Underwriters v Cross [2012] HCA 56; 248 CLR 378; Project Blue Sky v Australian Broadcasting Authority [1988] HCA 28: 194 CLR 355 applied
(vi) Section 26 of the Act confers a discretion on the Valuer-General in determining compensation under s 47 to take the special value of land, any loss attributable to severance or disturbance and solatium into account, notwithstanding that the acquisition process is activated by the hardship provisions in Pt 2 Div 3 of the Act: [54]-[58] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
Cumerlong Holdings Pty Ltd v Dalcross Properties Pty Ltd [2011] HCA 27; 243 CLR 492 applied
(vii) The power to compensate for legal costs under s 59(1)(a) of the Act does not extend to costs incurred in establishing hardship. A person is only entitled to compensation once the authority becomes bound to acquire the land. Legal costs incurred in establishing hardship are incurred prior to an entitlement to compensation and thus do not fall within s 59(1)(a): [59]-[60] (Bathurst CJ); [62] (Simpson JA); [63] (Payne JA).
Judgment
BATHURST CJ: This is an application for leave to appeal brought pursuant to s 57(1) of the Land and Environment Court Act 1979 (NSW) (LEC Act), from a decision of a judge of the Land and Environment Court, dismissing an appeal from a decision of two commissioners of that Court: Hoy v Coffs Harbour City Council [2015] NSWLEC 128 (Primary Judgment). The commissioners determined that the applicant was entitled to compensation of $2,034,957.39 in respect of the compulsory acquisition by the respondent (the Council) of certain land owned by the applicant in the Coffs Harbour area: Hoy v Coffs Harbour City Council [2014] NSWLEC 1217 (Commissioners' Determination).
The appeal from the decision of the commissioners to the primary judge was brought pursuant to s 56A of the LEC Act. Such an appeal was limited to an appeal from an order or decision on a question of law. Section 57(4)(c) of the LEC Act provides that any appeal from a decision made under s 56A can only be brought by leave. Such an appeal is, again, limited to an appeal from an order or decision on a question of law.