Costs "incurred" and causation
45The respondent submitted to the referee that the design and construction costs paid to Bauen Constructions were not allowable under s 59(f) (or at all) because they were "incurred" prior to the date of announcement of the intended acquisition in July 2009 and accordingly could not be said to be caused by the acquisition: report [87(b)]. The referee rejected the submission holding that they were clearly financial costs "for which the applicant was deprived of any benefit, a consequence specifically contemplated by s 59(f) which draws no distinction between costs incurred before or after the date of acquisition but only that they related to actual use of the land and are a cost suffered as a direct and natural consequence of the acquisition": report [89].
46The respondent's written submission is that, first, it is a legal error to hold that a cost is "incurred" within the meaning of s 59(f) not at the point when the party spends the money or becomes liable to spend it, but at a later point when that party is "deprived of any benefit"; and, secondly, costs cannot be caused by the acquisition if they were incurred prior to announcement of the public purpose. When faced with the fact that the applicant had paid these costs after the date of the respondent's announcement of the proposed acquisition on 20 July 2009, the respondent orally modified its written submission by submitting that a cost is "incurred" at the earlier of the times when the legal obligation to pay arises or the time when the money is paid.
47As I understand it, the respondent in oral submissions seeks to extend its costs "incurred" and causation submissions to all the applicant's wasted costs, on the basis that the contractual obligation to pay them arose prior to announcement of the resumption proposal on 15 July 2009. They were all paid, or are to be paid, after that date.
48It is the terms of the Just Terms Act that are determinative: Walker Corporation Pty Ltd v Sydney Harbour Foreshore Authority [2008] HCA 5, 233 CLR 259 at [47]. However, it was said in the Court of Appeal in Blacktown, and the Court of Appeal proceeded on the basis, that while care must be taken in utilising the reasoning from decisions construing similar words in different legislative regimes, such decisions may be helpful in the task of construction of the disturbance provisions of the Just Terms Act: at [3].
49Abortive or wasted expenditure which does not improve the value of land, and hence is not picked up in market value, has been recognised in cases decided under earlier resumption compensation legislation in New South Wales as well as under the Just Terms Act, and under resumption compensation legislation in England and Canada. Such claims were recognised by the Court of Appeal in Yates Property Corporation Pty Ltd (In Liq) v Darling Harbour Authority (1991) 24 NSWLR 156 at 161G - 162B, 163E - G, 185F (decided under the Public Works Act 1912) and allowed by Cripps CJ on the rehearing, as noted in Boland v Yates Property Corp Pty Ltd [1999] HCA 64, 167 ALR 575 at [34], [35]. Those findings were not criticised in Boland : at [23], [34], [86], [87]. In Peter Croke Holdings Pty Ltd v Roads and Traffic Authority of NSW (1998) 101 LGERA 30 at 64 - 66 Bignold J rejected an argument that deductions from disturbance compensation should be made for enhancement or residual value. Legal costs of abortive negotiations to sell the subject land to the resuming authority in the shadow of a resumption were allowed in Caruana v Port Macquarie - Hastings Council [2007] NSWLEC 109 at [88] - [91] (Biscoe J) having regard to the fact that the Act envisaged sale to the resuming authority as an alternative to compulsion.
50Other compensation cases which have recognised the value of abortive expenditure which does not improve the land and hence is not picked up as market value, include the following: Scottish Halls Ltd v The Minister (1915) 15 SR (NSW) 81 at 82, 90 - 91 (decided under the Public Works Act 1912); George Wimpey & Co Ltd v Middlesex county Council [1938] All ER 781 at 783D - E (expenditure thrown away, being the costs of road construction in developing a housing estate); Service Design Pty Ltd v Commissioner of Highways (1986) 59 LGRA 176 at 193.3 (abortive auctions); McEwen v R (1978) 15 LCR 1 at 5 - 7 (development costs of partial clearing, survey, fees for initial abortive redevelopment) (Federal Court); Liebovitch v City of Vanier (1975) 8 LCR 109 at 111 (building permit obtained for projected development) (Land Compensation Board, Ontario); Durette v New Brunswick ( Minister of Transportation) (1980) 21 LCR 124 at 132 (architect's fees rendered nugatory) (Property Compensation Board New Brunswick); Ridgeport Developments v Metropolitan Toronto Region Conservation Authority (1976) 11 LCR 143 at 154, 156 - 7 (architect's plans and other costs of future development rendered abortive) (Land Compensation Board, Ontario); Starkman v City of Brampton (1974) 7 LCR 329 at 346 - 8 (legal principle, abortive development expenditure) (Land Compensation Board, Ontario).
51In Canada (Federal District Commission) v Dagenais [1935] Ex CR 25, the President of the Exchequer Court of Canada allowed abortive expenditure, either as special value or disturbance, because the owner had lost the benefit of his expenditure on preparing building plans and other costs preliminary to starting building work: at [4]. It was the taking of the land which had caused the incurrence of the loss or damage: at [10] - [15]. The President followed the NSW case of Scottish Halls (above) finding that there was nothing in the Public Works Act of NSW under which that case was decided to distinguish it from the Canadian statute there under consideration.
52In the present case, all the wasted costs were paid after the announcement of the resumption. Some have not yet been but will be paid (eg architect's fees). What was paid to the applicant's contractors was, in effect, frustration damages for work of no value to the applicant: in truth, a cost to the applicant. It would be different if the work resulted in an improvement to a capital asset (the land) in which case its value would have sounded in market value. However, there was no physical manifestation of the work which was of any value: it was simply lost, as a direct consequence of the resumption.
53Section 59(f) is a wide, catch - all provision, and the words "any financial costs" should not be read down: McDonald v Roads and Traffic Authority of NSW [2009] NSWLEC 105, 169 LGERA 352 at [110]. They include a financial loss: Sydney Water v Caruso [2009] NSWCA 391, 170 LGERA 298 at [186]. Compensation for disturbance compensates for loss: ss 55(d), 59; Bligh v Minister Administering the Environmental Planning and Assessment Act 1979 [2011] NSWLEC 220 at [67] - [78] (Biscoe J). The loss to a dispossessed owner includes financial costs thrown away because of the resumption. The ordinary meaning of "cost" includes not only the price paid to acquire property or services but also "a sacrifice, loss or penalty": Macquarie Dictionary.
54If a compulsory acquisition converts amounts payable or paid under earlier contractual obligations into wasted or aborted expenditure for no value, at that moment costs are incurred as a direct and natural consequence of the acquisition. Whilst the contractual obligation to pay was incurred before the acquisition, the "costs", within the meaning of s 59(f), were incurred once the applicant was deprived of the benefit of the obligations by the acquisition. In this sense they are costs which are compensable pursuant to s 59(f).
55In my opinion, the referee was correct in allowing the contentious costs claimed by the applicant under s 59(f).