Harris v Morabito Holdings
[2018] NSWSC 912
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2018-06-19
Before
McDougall J
Source
Original judgment source is linked above.
Judgment (26 paragraphs)
Solicitors: Kreisson Legal Pty Limited (Plaintiffs) HWL Ebsworth Lawyers (Defendant) File Number(s): 2016/160508
Judgment
- HIS HONOUR: On about 7 February 2012, the defendant (the builder) contracted to perform residential building work for the plaintiffs [1] (the owners). The builder achieved practical completion on about 13 September 2013. The defects liability period under the contract expired 12 months later.
- In the usual way, the parties have fallen into dispute. The owners said that the work done by the builder was defective. The builder said that it was not liable for any further defects rectification. Further, the builder said, it is entitled to be paid for, among other things, variations and delay costs. There were other, relatively minor (in monetary terms), disputes.
- The owners commenced proceedings in the NSW Civil and Administrative Tribunal. The proceedings were transferred to this court. When the evidence was complete, the whole of the proceedings were referred to a referee, Mr Barry Tozer (the referee), for inquiry and report. After a hearing taking 9 days spread over a four month period in 2017, involving no less than 25 lever arch folders of documents and oral evidence that occupied over 750 pages of transcript, the referee reported. He concluded that, taking into account amounts that he thought were owed one way and the other, there was a total of (in round figures) $328,000, including GST, owed by the builder to the owners.