H M Australia Holdings Pty Limited v Edelbrand Pty Limited t/as Domus Homes & Anor
[2011] NSWSC 604
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2011-06-14
Before
Einstein J
Source
Original judgment source is linked above.
Judgment (29 paragraphs)
The proceedings 1These proceedings concern a building dispute arising from the Building and Construction Industry Security of Payment Act 1999 (NSW) ('the Act'). The plaintiff sought a declaration that Mr Davenport's 14 February 2011 Adjudication Determination is void by reason of seven alleged basic, essential or jurisdictional errors. 2During the hearing, the plaintiff successfully persuaded the Court that grounds 3, 4 and 7 of the plaintiff's case were outside the pleadings. Consequently, the only issues that remained for consideration were grounds 1,2,5 and 6.
Background facts 3On 15 October 2008 the plaintiff ( HM Australia ) and the first defendant ( Domus ) entered into an agreement for what may be described as the provision of project management services in connection with the construction of a warehouse at 1A Jindalee Place Riverwood, NSW. 4The contract provided for Domus to be remunerated on the basis of a fixed fee and a bonus payment (where applicable). The terms of this remuneration agreement are discussed in more detail below. 5The overriding dispute between the parties is whether Domus is entitled to a bonus of $214,913.60. The adjudicator found that this bonus is payable. 6Pursuant to the contract, Domus undertook to provide a variety of services including coordinating survey and geotechnical investigation, finalising the architectural brief in consultation with HM Australia, coordinating the provision of a building cost estimate by the builder, assisting with the selection of finishes, coordinating updates of building cost estimates, coordinating consultants to finalise the construction contract documents, managing consultants and the builder to deliver the project in accordance with the building contract (which included attending site meetings and inspections to monitor and administer the works), coordinating the rectification of defects and providing instructions to the builder and consultants. 7On 18 October 2008, Brecon (NSW) Pty Ltd, the builder, submitted a budget price for building the works. Agreement was reached and a construction budget set. Subsequently, HM Australia requested a number of variations, which were carried out by Brecon. 8On 20 October 2009, Brecon submitted a final price for construction and a list of additional costs comprising variations and provisional items of $2,599,155.00 plus GST to construct the warehouse . 9On 22 October 2009 Canterbury City Council granted development consent in respect of a development application submitted by Domus on behalf of HM Australia. By 25 November 2010, the building works were completed. 10The building works were completed for $390,752.00 below the budget when one excludes variations to the value of $806,725.00. Domus claims this entitles them to a bonus of $195,376.00 plus GST and on 26 November 2010 served a payment claim for the amount owing. 11It is common ground that a payment schedule was not served by the plaintiff in response. Accordingly, on 22 December 2010, Domus, by email, notified HM Australia of its intention to apply for adjudication of the payment claim. HM Australia again did not serve a payment schedule pursuant to s17 (2)(b) of the Act. 12On 19 January 2011, Domus made an adjudication application and served it on HM Australia. On 20 January 2011, Mr Tonkin accepted an appointment as adjudicator but on 7 February 2011 Domus withdrew the adjudication application and made a new adjudication application by notice in writing served on the nominating authority. 13On 9 February 2011, the second adjudication application was served on HM Australia and Mr Davenport, accepted appointment as adjudicator and notified the parties. 14On 14 February 2011, Mr Davenport published his adjudication determination. He found the adjudicated amount to be $214,913.60 inclusive of GST.