Fund management on fund management
18As already noted, the first allowance claimed is sometimes referred to, in shorthand, as "fund management on fund management". So described, the claim is potentially confounding, having the resonance of double counting. Upon analysis, however, it is difficult to fault the logic of the plaintiff's claim for such an allowance.
19To adopt the illustration used in argument by Dr Morrison SC, who appeared with Mr McGillicuddy for the plaintiff, if the cost of managing a damages award of $10 million over the relevant term were, for example, $2 million (20 per cent of the corpus), the total verdict would be $12 million, to be received today and managed over time. A plaintiff under incapacity would have no better ability to manage the additional $2 million than the initial $10 million. It follows that the award of a component for fund management would itself give rise to future management expenses in the order of $400,000 (assuming fees charged on that amount at the same rate of 20 per cent). The additional $400,000 in turn would cost a further $80,000 to manage, which would cost a further $16,000, and so on.
20A further consideration is the fact that the fund management award must itself be discounted to present value at the statutory rate of 5 per cent. It necessarily follows that, on the assumptions on which the verdict is based (the proper approach being to assess damages in the money of today), that sum will have to be invested so as to earn a net return approximating the discount rate.
21In those circumstances, the plaintiff contends that the only way for her to obtain an adequate award of compensatory damages is to make an allowance for the cost of managing the sum awarded by way of fund management costs.
22There is competing authority in decisions of single judges in this Court and in the Supreme Court of Queensland as to whether any such allowance should be made. Before turning to those cases, I should first consider a remark on this issue made by Meagher JA in the decision of the Court of Appeal in Rosniak .
23His Honour said (at 698G):
Mr Kelly also submitted that an adjustment should be made to award a management fee in respect of each management fee paid; however, in my view, this submission ought be rejected as it would involve unwarranted double counting.
24In my view, properly analysed, the plaintiff's claim does not involve any element of obtaining compensation twice for the same item. The payment to the manager of the fund management component of the damages award is not made by way of payment in advance to be held by the manager beneficially on account of his future fees. If it were, the cost to the plaintiff of managing that part of the fund would be avoided (or at least transferred to the manager) but that is not what happens. Section 79 of the Civil Procedure Act imposes a requirement that the proceeds of the verdict be held on trust by the manager and applied as part of the protected estate. The manager will pay himself periodically as fees are earned, just as he will pay carers and other expenses as accrued.
25It was nonetheless maintained by Mr Deakin QC (who appeared with Mr Kelleher and later Ms King for the defendant) that I should follow the decision of Meagher JA in Rosniak to reject the claim. Mr Deakin submitted that, although the other members of the Court made no express reference to this issue, they were "broadly in agreement" with Meagher JA and so may be taken to have endorsed or joined in his Honour's view on that question.
26In the absence of express reference to the issue in the judgments of the other two members of the Court, I do not think that the decision in Rosniak stands as binding authority on this question. The only reason given by Meagher JA for rejecting the claim was that it would involve unwarranted double counting. With great respect to his Honour, I think that description reveals that he may have misapprehended the nature of the claim and, accordingly, that his remarks on that issue should be considered as having been made per incuriam .
27The plaintiff's position finds support in the decision of Hunter J in Bacha v Pettersen (Supreme Court of New South Wales, 20 September 1994, unreported). His Honour's reasoning appears to derive from the same analysis of the issue as mine (set out above). Hunter J said:
The principal questions are: (1) What is the fund? and (2) How should the management fee be determined? These questions give rise to considerations of (a) the likely expenditure by the Protective Commissioner on matters needed by the plaintiff from time to time; (b) the relevance of the tax deductibility (sic) nature of the management fee, when viewed in the context of income derived by the fund upon which management fees are calculated, and (c) whether the management fee should form part of the fund.
As to those matters, I am clear that the practicabilities of the problem dictate that any determination by me of a management fee will result in that sum going into the hands of the Protective Commissioner, and accordingly attract the establishment fee and the management fee on income. It will not go to the fund with any designation of it being a management fee. It will form part of the damages.
28His Honour proceeded to calculate the allowance on the basis that the relevant fund included the management fee itself. A contrary view was reached by Burchett AJ in Buckman v M & K Napier Constructions Pty Limited [2005] NSWSC 546 at [13]. Although the relevant passage is lengthy, it is appropriate to set it out in full:
13 I turn to the second question, that raised by the plaintiff's contention to the effect I should add the amount required to meet the cost of fund management to the fund, and recalculate what is required, because any amount allowed will swell the fund and therefore be reflected in the charges ultimately made. Theoretically, this process could go on forever, although the plaintiff's counsel do not push the point so far. It is, indeed, a point reminiscent of the ancient mathematical fallacy of the hare and the tortoise: if, it was said, the hare can run ten times as fast as the tortoise, which has a ten yards start, while the hare runs the ten yards, the tortoise will go one, and while the hare runs that, the tortoise will go one tenth and so on, so the hare will never quite catch the tortoise! But, in my opinion, there is a simpler answer to the plaintiff's contention, which is not fallacious. The calculation of damages is not mathematically exact. It involves estimations. To strive for the precision the argument seeks in respect of the cost of the management of a fund components of which are themselves broad assessments of reasonable sums that are beyond calculation, such as damages for pain and suffering and the loss of the amenities of life, would just be incongruous. Furthermore, while a calculation utilising the figure of $2,700,000 in some way seems inescapable, it must be recognized, as McHugh J pointed out during the argument in Willett v Futcher, that even that basic step will lack precision, since a change in market conditions (a steep rise or fall in the share market, for instance) could, within a little time, change greatly the figure to which the Protective Commissioner's percentages will be applied, or, it may be added, a change in the regulation itself may intervene during the life expectancy of the plaintiff. It is, and must be, all a question of reasonable estimate which will determine the amount to be allowed. In my opinion, a sum calculated in the manner I have already indicated is the reasonable amount to allow in the present case.
29Burchett AJ was evidently troubled by a perceived incongruity between the inexact calculation of damages generally and the exactitude of a calculation that, theoretically, must be repeated to infinity.
30I do not think that should be an impediment to the plaintiff's claim. The starting point is to observe that the cost of future fund management is a recognised head of future loss, the entitlement to which is beyond question, having been affirmed by the High Court: Nominal Defendant v Gardikiotis [1996] HCA 53; (1996) 186 CLR 49; Willett v Futcher [2005] HCA 47; (2005) 221 CLR 627 (the latter was decided after the decision in Buckman ). It is difficult to understand why the nature of its calculation (being repetitive and ever-diminishing) should preclude the grant of an award adequate to compensate the plaintiff for a recognised loss.
31Burchett AJ does not appear to have been taken to the decision of Hunter J in Bacha (which, it must be acknowledged, is unreported); or to have received assistance of the kind I have received from the expert evidence in the present case. The actuary, Mr Plover, produced a ready calculation of the appropriate amount (repeating the calculation until the additional amount was negligible). The terms of the judgment of Burchett AJ suggest that his Honour was not provided with such assistance, and may even be read as revealing that the plaintiff had invited his Honour to undertake the relevant calculation.
32The decision in Buckman has been followed in this Court in Haywood v Collaroy Services Beach Club Limited [2006] NSWSC 566 at [8] per Hidden J. In that case, there were competing opinions of experts, as in the present case. His Honour rejected the claim, adopting the reasoning of Burchett AJ in Buckman as a matter of comity and expressing his agreement with it. His Honour did not undertake any discrete analysis of the issues that have been agitated in the hearing before me, and does not appear to have had the decision of Hunter J in Bacha drawn to his attention. It may also be noted that the amounts involved in that case were substantially smaller than in the present case.
33Buckman and Haywood were subsequently followed by the Supreme Court of Queensland in Lewis v Bundrock [2009] 1 Qd R 524 ; [2008] QSC 189 at [16] per Martin J. Again, the unreported decision of Hunter J in Bacha does not appear to have been brought to the attention of the Court.
34Martin J analysed the reasoning of Burchett AJ in Buckman and expressed his agreement with it, noting that an award of damages is only ever an estimate of the fair and reasonable compensation required. His Honour specifically referred, as Burchett AJ had, to the fact that the calculation required to give effect to the plaintiff's claim "could be extended indefinitely, with ever-decreasing increments" (at [15]).
35At most, that is a reason for insisting on a measure of approximation at the tail end of the plaintiff's calculation (there would be no sense in taking it beyond the smallest denomination of the currency in any event). I do not think it is a reason for keeping the plaintiff out of the award that is necessary to meet an identifiable future cost.
36I do not think I am constrained by any obligation of comity on this question, since I am faced with a choice between two lines of authority in decisions of single judges (albeit that one of the lines is a single point). For the reasons explained above, I prefer the reasoning of Hunter J in Bacha .
37A separate submission put on behalf of the defendant related to the state of the evidence as to whether the services of any of the proposed managers could be obtained more cheaply having regard to the size of the fund under management. It is true that there was no evidence specifically directed to whether the proposed manager would accept fees at a lower rate to manage a fund of the size agreed in the settlement between the parties (including the fund management costs component). In light of the fact that there is to be a further round of hearing in any event, the plaintiff should have leave to adduce evidence directed to that issue.