Grandview Ausbuilder Pty Ltd v Budget Demolitions & Excavations Pty Ltd
[2020] NSWSC 343
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2020-03-25
Before
Parker J
Source
Original judgment source is linked above.
Judgment (10 paragraphs)
Judgment - EX TEMPORE Revised and reissued 6 April 2020
- This is an application by the defendant in these proceedings for an order that the plaintiff provide security for its costs of the proceedings. The plaintiff company ("Grandview") formerly carried on business as a builder. The defendant company ("Budget"), as its name suggests, is a building contractor which specialises in demolition and excavation work.
- While Grandview was carrying on its building business, it appears to have been controlled by a Mr Jason Zhang. In August 2019 Mr Zhang recognised that Grandview was insolvent, and an administrator was appointed. Grandview is now operating under a Deed of Company Arrangement ("DOCA") approved by the creditors. The deed administrator is Mr Bailey of O'Brien Palmer. I was told that Mr Zhang is currently in China.
- The proceedings arise out of a subcontract between Grandview, as head contractor, and Budget, as subcontractor, for demolition and excavation work at a development being constructed by Grandview at Villawood. That subcontract was entered into in June 2017. The contract price was approximately $2.5 million. Work began in July 2017 and the scheduled completion date was in December 2017.
- The parties fell into dispute and in late January 2018 Budget suspended work on the contract on the grounds of non-payment of an amount due under the Building and Construction Security of Payment Act 1999 (NSW) ("SOP Act"). In April 2018, not having paid the amount due, Grandview purported to terminate. Budget's position is that the purported termination was invalid and a repudiation by Grandview, which Budget accepted. The parties agree that the contract came to an end at that time.
- Grandview commenced these proceedings as plaintiff in February 2019. Grandview's pleaded claim involves three principal elements. First, Grandview claims liquidated damages from the contractual date of completion (December 2017) onwards until termination of the contract. Second, Grandview claims restitution of moneys paid pursuant to payment claims made under the SOP Act. Third, Grandview claims loss of bargain damages consequent upon what it contends was its effective termination of the contract. There is, of course, an overlap between the second and third claims. As well as defending each of these claims Budget has cross-claimed for amounts due under the SOP Act which remain unpaid.