"(i) In 1999 Avon Homes, a company, had been contracted to build the tavern at 'the site'. Mr C. Alio was a director of that company and a registered builder.
(ii) In early December 1999 Avon Homes contracted with Go Crete Pty Ltd (hereinafter called 'Go Crete') to supply, lay and erect footings, ground slab and pre-cast panels for the tavern. The defendant, Mr. Crawford, was a director of 'Go Crete' and the supervisor for the contracted work at 'the site'.
(iii) On the 15 December 1999 Mr. Crawford spoke with Mr. T Daly, an employee of Midland Crane Services, (hereinafter called 'Midland') about hiring a crane and operator to lift and place pre-cast concrete panels at various points on 'the site'. Both Crawford and Daly inspected the site and were aware that there were electricity cables suspended from poles which ran down the adjacent sides of 'the site', viz., on Knutsford Avenue and Wright Street.
(iv) Near the portico area close to boundary of Knutsford Avenue were 3 separate sets of overhead conductors which carried high voltage (a) 12.7 kV, (b) 240 Volts Blue phase and (c) a 240 volt street light cable belonging to the Western Power Corporation (hereinafter called 'Western Power')
(v) On the 16 December 1999 Mr Daly caused an application to be sent to the 'Western Power' to permit work over or close to overhead live conductors on 21 December 1999. The request stated the work address was 'Knutsford Avenue, Belmont' and that the work was 'near L.V. wires'. On the same day approval was given by 'Western Power' for the work on certain conditions, viz 'all care and caution to be taken' and 'The minimum clearance to be maintained is 3 metres.'
(vi) On the 21 December 1999 a 'Midland' crane operated by Mr. Hofmeyer arrived on 'the site' to lift panels and the work was done without incident and the majority of 30 panels were erected. The crane then left 'the site'.
(vii) On the 10th January 2000 Mr. Crawford arranged with Mr. Daly for the crane and Hofmeyer to return to 'the site' to erect the remaining panels. No further permit from 'Western Power' was sought
(viii) On the 12th January 2000 the crane and Mr. Hofmeyer returned to 'the site' where Mr. Crawford, Mr Toni Meehan, a rigger, and Mr. Bartler and Mr. Wilde, both labourers, were present.
(ix) At about 6.00 am a decision was made to shift a pre-cast panel 'PIO' into its position for the portico. The overhead power lines were directly above the concrete footing on which 'PIO' was to rest.
(x) The panel was lifted by the crane from the ground and moved at walking pace towards the footing. Mr. Meehan was giving directions to Mr. Hofmeyer by hand signals as to the direction in which the panel was to go. During the progress it was then ascertained that it was facing the wrong way and needed to be revolved.
(xi) When it became stationary about 3 metres from the footing the panel was revolved. It was then moved further towards the footing with Mr. Crawford and Mr. Meehan holding it so as to steady it.
(xii) When the panel was about 800 mm from its intended resting place the lifting chains on the crane came in close proximity to the red phase 12.7 KV conductor. Both Mr. Crawford and Mr. Meehan received an electric shock the result of which caused the latter's death.
(xiii) A visual inspection of the lifting chains showed high voltage burn marks as did one of the two wire slings.
(xiv) The lifting chains were attached at one end to the crane hook and at the other to two pulley blocks. Wire rope slings ran through the pulley block and were bolted to the panel.
(xv) From the method of attaching the slings to the panel to place the base of the panel in its position on the 'footing' the lifting chains had to be 1400 mm into space directly below the red phase and to achieve that the chains had to contact the red phase conductor."