General Trade Industries Pty Ltd (in liquidation) v AGL Energy Limited
[2020] FCA 1562
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2020-10-29
Before
Derrington J
Source
Original judgment source is linked above.
Judgment (19 paragraphs)
Introduction 1 This was an application for security for costs brought by the respondent in the proceedings, AGL Energy Ltd (AGL), pursuant to s 1335 of the Corporations Act 2001 (Cth) (Corporations Act), s 56 of the Federal Court of Australia Act 1976 (Cth) (Federal Court Act) and r 19.01(1)(a) of the Federal Court Rules 2011 (Cth) (the Rules). AGL also sought to have the proceeding stayed or dismissed, pursuant to s 56(4) of the Federal Court Act and r 19.01(1)(c) of the Rules, if any security ordered is not provided within 14 days. 2 The applicant in the primary proceeding, General Trade Industries Pty Ltd (in liq) (General Trade) resisted the making of any order for security.
Background facts 3 On 20 December 2013, AGL entered into a building construction contract (the Construction Agreement) with General Trade for the latter to carry out civil, mechanical and electrical work at AGL's Wullumbilla LPG Plant and Silver Springs Plant. In these reasons the construction project is referred to as "the Silver Springs Project", Between the date of entering into the contract and 13 August 2014, substantial work was undertaken for which General Trade was paid $20,857,897 exclusive of GST. 4 In or around November 2014, a dispute emerged between AGL and General Trade in relation to the work carried out under the Construction Agreement. AGL claimed that certain work was defective, which General Trade rejected and countered with the assertion that it had not been fully paid in relation to certain payment claims (PC10 and PC11) which it had issued to AGL. A period of negotiation followed, during which General Trade issued a statutory demand. The dispute was seemingly resolved by the parties entering into what was called a "Deed of Release" (the Deed), pursuant to which the parties agreed to settle their respective claims. One of the recitals to the Deed provided: 8 Subject to the terms of this deed, the parties wish to release all conceivable claims against each other in respect of the Contract and the Dispute, whether or not all material facts are known to the party giving the release, and wish this deed to have effect in a manner that most effectively releases any claims of the parties against each other in relation to the Contract and the Dispute. 5 The "Dispute" was defined in the recitals in the following terms: A dispute has arisen between the parties in connection with the WUC, including the amounts claimed in Progress Claim 10, Progress Claim 11 and the Contract Sum, and the Statutory Demand (the Dispute). 6 The effect of the payment terms in the Deed was that in settlement of the "Dispute", AGL would pay to General Trade the amount of $6,642,103, such that the total amount paid by it under the Construction Agreement was $27,500,000. 7 By cl 1.5 of the Deed the parties covenanted as follows: 1.5 Contractor's full entitlement under or in connection with the Contract (a) The parties acknowledge and agree that the payments contemplated in this clause 1, together with the Sum Paid to Date, constitute the full amount that the Contractor is entitled to under or in connection with the Contract, including any and all variations to the Contract for the WUC performed up to and including 31 July 2014, and the Contractor shall have no entitlement to any further payment under or in connection with the Contract and the Company shall have no further liability to the Contractor other than as provided for in this clause 1. (b) For the avoidance of doubt, the parties agree that the payments to be made in accordance with this clause 1 constitute the full and final payment of any amount payable to the Contractor in respect of, among other things, the amounts claimed by the Contractor in Payment Claim 10 and Payment Claim 11. 8 By cl 5 of the Deed the parties agreed to mutual releases of liability in the following terms: Mutual Release (a) Subject to clause 3 and clause 5(c), each party releases and discharges the other party and each of its related bodies corporate as defined in the Corporations Act 2001 (Cth) and the directors, servants and agents of each of them (Related Parties) severally from any claim, action, demand, suit or proceeding for damages, debt, restitution, equitable compensation, account, injunction, specific performance or any other remedy that each party has or may have against the other or any of its Related Parties in respect of: (1) The Contract; (2) the subject matter of the Dispute or any part of the Dispute; and (3) any thing related to the Dispute including, without limitation, any damage, loss, cost or expense suffered as a result of the Dispute, whether known or unknown at the date of this deed, and whether arising at common law, in equity, or under statute or otherwise (the Released Matters). (b) In support of the releases in clause 5(a) above each party covenants with the other party and each of its Related Parties severally not to claim, sue or take any action against the other party or any of its Related Parties in respect of the Released Matters. (c) Nothing in clause 5(a) releases, discharges or terminates, and clause 5(b) does not apply to the obligations contained in clauses 2A, 5, 29, 34.6 and 35 of the Contract which, for the avoidance of doubt, the parties agree continue to have effect. 9 AGL paid the amounts required of it under Deed and, as also required by the Deed, on 19 May 2015 it issued a Certificate of Practical Completion in accordance with cl 34.6 of the Construction Agreement within 5 days of making the last payment. 10 From around 17 September 2014, pursuant to cl 29 of the Construction Agreement, AGL's superintendent under the construction agreement issued a number of notices to General Trade requiring the latter to rectify defective work. It appears that certain work undertaken was not to the satisfaction of the superintendent, such that the subsequently issued Certificate of Practical Completion attached a list of outstanding works and a reminder to General Trade of its obligation to rectify all defects and complete unfinished work. It also confirmed that the defects liability period commenced on 4.00pm on the date of the Certificate of Practical Completion. 11 Central to the present dispute between the parties is that on 19 August 2015, General Trade gave to AGL a document called "Progress Claim No. 12" (PC12). It was purportedly sent pursuant to the terms of the Construction Agreement and sought the payment of a further amount of $3,474,074.83. PC12 included an Excel spreadsheet of many pages in length and an electronic folder of what was said to be supporting documents. 12 AGL has denied that it is liable to pay any further amounts under the Construction Agreement. Firstly, it says that given the terms of the Deed and its payment of the settlement sum, no further amount can be payable under the agreement. Second, it alleges that PC12 includes amounts which do not relate to the Construction Agreement or any work on the project or, otherwise, relate to rectification work for which no remuneration is payable.