REASONS FOR JUDGMENT
1 This is an application by the applicant for an interlocutory injunction restraining the respondent from having recourse to two bank guarantees in relation to certain claims made by the respondent against the applicant. The bank guarantees were provided by the applicant pursuant to a Subcontract Agreement between the applicant and the respondent and they were given by the applicant's banker, the National Australia Bank Limited ("National Bank"), on 4 September 2013 ("the Bank Guarantees"). After an ex parte hearing on 28 October 2015, I granted the injunction sought by the applicant. On 2 November 2015, I heard full submissions from the applicant and the respondent on the issue of whether an interlocutory injunction should be granted and I reserved my decision. The applicant provided the usual undertaking as to damages, and the respondent by its counsel gave an undertaking in terms of the injunction previously granted until judgment was given on the applicant's application for an interlocutory injunction.
2 For the reasons set out below, I have reached the conclusion that the applicant's application for an interlocutory injunction should be refused and the respondent should be released from its undertaking.
3 The applicant as the Subcontractor and the respondent as the Contractor entered into a Subcontract Agreement on 15 July 2013 in connection with a project involving the construction of a Northern Water Treatment Plant and Associated Infrastructure near Wandoan in Queensland. Under the Subcontract Agreement, the applicant undertook to supply and install pond liners and leak detection systems for two water treatment ponds. The applicant's work under the Subcontract Agreement was divided into two separable portions. Separable Portion 1 ("SP1") involved a 1200 ml Clarified Water Pond and the Date for Substantial Completion was 30 March 2014, later extended on an interim basis to 19 April 2014. The evidence in the case establishes that the Date of Substantial Completion was 19 June 2014. Under the Subcontract Agreement, the Date of Substantial Completion is the date upon which the Contractor's Representative is reasonably satisfied that Substantial Completion has been achieved. The Subcontract Agreement provided for the provision of bank guarantees or the retention of monies. In this case, bank guarantees were provided. In the case of bank guarantees, the Subcontract Agreement provided that two guarantees for 10% of the Subcontract Sum were to be provided in relation to SP1. One of the Bank Guarantees provided was released on substantial completion as provided by the Subcontract Agreement. The other Bank Guarantee is the subject of the applicant's application for an interlocutory injunction. Separable Portion 2 ("SP2") involved a 600 ml Reverse Osmosis Reject Pond and the Date for Substantial Completion was 30 June 2014. The evidence in this case establishes that the Date of Substantial Completion was 6 September 2014. The Subcontract Agreement provided for the provision of bank guarantees or the retention of monies. In this case, bank guarantees were provided. In the case of bank guarantees, the Subcontract Agreement provided that two guarantees for 10% of the Subcontract Sum were to be provided in relation to SP2. One of the Bank Guarantees provided was released on substantial completion as provided by the Subcontract Agreement. The other Bank Guarantee is the subject of the applicant's application for an interlocutory injunction. The total amount of the two extant Bank Guarantees is $1,121,146.33.
4 The applicant commenced work in July 2013.
5 The Subcontract Agreement fell within the terms of the Building and Construction Industry Payments Act 2004 (Qld) ("the Act"). Pursuant to s 17 of the Act, the applicant made a payment claim dated 13 April 2015 and that payment claim was served on the respondent on 14 April 2015. The payment claim was disputed by the respondent by way of a payment schedule served on the applicant and dated 28 April 2015. The applicant's payment claim went to adjudication under s 21 of the Act and on 16 September 2015, the adjudicator made a decision in the applicant's favour awarding it an amount of $4,019,863.73 plus interest and 75% of the adjudicator's costs. On 25 September 2015, the respondent commenced proceedings in the Supreme Court of Queensland seeking a declaration that the adjudication decision was void. On 16 October 2015, the respondent discontinued its proceeding in the Supreme Court and the applicant was paid the amount which had been awarded to it.
6 On 27 October 2015, the respondent wrote to the applicant summarising various claims "for the purposes of clause 6.2 of the Subcontract". That clause provides for recourse to the Bank Guarantees and is set out below (at [8]). First, the respondent claimed that it had made overpayments to the applicant in the sum of $3,720,916.15 and it sought to recover that amount. The overpayments represented the amount or part of the amount paid to the applicant under the adjudicator's decision. The respondent's case is that the adjudicator erred. I will refer to this claim as the recovery claim. One element of the recovery claim is an amount for "leak detection" of $2,533,069.71. In relation to that amount, the respondent claimed that it was entitled to recover the amount as an overpayment and, in addition, as damages for misleading or deceptive conduct under s 18 of the Australian Consumer Law (Schedule 2 to the Competition and Consumer Act 2010 (Cth)). Secondly, the respondent claimed an amount of $2,218,930.54 for liquidated damages. The claim for liquidated damages comprises an amount of $1,049,261.73 for a delay period of 61 days in relation to SP1, and an amount of $1,169,668.81 for a delay period of 68 days in relation to SP2. The claim for liquidated damages alone exceeds the amount of the Bank Guarantees. I will refer to this claim as the liquidated damages claim. In the letter dated 27 October 2015, the respondent gave the applicant 24 hours' notice of its intention to call on the Bank Guarantees.
7 The evidence establishes that the first time the respondent made its claim for liquidated damages was in its letter dated 27 October 2015. The respondent did not raise such a claim when its representative decided he was reasonably satisfied that Substantial Completion had occurred (i.e., Date of Substantial Completion). Nor was the claim raised before the adjudicator. The adjudicator did consider delay in the progress of the Subcontract because the applicant claimed stand-down costs as part of its claim. The respondent relied on an expert's report from Tracey Brunstrom & Hammond Pty Ltd before the adjudicator, and the applicant pointed to the fact the respondent's expert concluded that the applicant was responsible for a delay of 7.32 days (Executive Summary, paragraph 20).
8 The Bank Guarantees were provided pursuant to cl 6 of the Subcontract Agreement and that clause provides as follows, relevantly:
6. Retention
6.1 Amount and time for Provision
The Contractor will be entitled to retain from any payment made under the Subcontract or otherwise, the percentage stated in Item 12 of Schedule 1 of the Subcontract.
The Contractor may accept the provision by the Subcontractor of Bank Guarantees in lieu of retention for the amount stated in Item 12 of Schedule 1 of the Subcontract.
Without limiting the Contractor's discretion to approve the terms of a Bank Guarantee not provided in the form set out in Schedule 8, if the Subcontractor provides a Bank Guarantee that has an expiry date, the Subcontractor must replace the Bank Guarantee with another Bank Guarantee on the same terms no later than 45 days before its expiry. If the Subcontractor fails to replace a Bank Guarantee no later than 45 days before its expiry, the Contractor may convert the Bank Guarantee to cash.
6.2 Recourse to Bank Guarantees and Retention
The Contractor may have recourse to the Bank Guarantees or any sum retained pursuant to the preceding clause whenever the Contractor claims to be entitled to claim the payment of monies by the Subcontractor.
6.3 Release of Bank Guarantees
Subject to clause 6.5, within 10 working days after the later of the Date of Substantial Completion and date of Practical Completion for the whole of the Head Contract Works, the Contractor will release the percentage stated in Item 13 of Schedule 1 of the Bank Guarantees then held. The Contractor will release the balance promptly once the Subcontractor's obligations are complete and the Defects Liability Period has expired.
6.4 Release of Retention
Subject to clause 6.5, within 10 working days after the later of the Date of Substantial Completion and the date of Practical Completion for the whole of the Head Contract Works, the Contractor will release the percentage stated in Item 14 of Schedule 1 of any amount then held which has been retained under clause 6.1.
Subject to clause 6.5, within 10 working days after the Contractor's Representative issues a Final Certificate under clause 14.16, the Contractor will release the balance of any amount held which has been retained under clause 6.1.
6.5 Unsatisfied Claims
If, at any time when the Contractor is required to release Bank Guarantees or retention money to the Subcontractor, the Contractor considers it has any unpaid moneys due or unsatisfied claims against the Subcontractor, the Contractor shall only be obliged to release the Bank Guarantee or retention moneys to the extent that the aggregate of the Bank Guarantee and the retention moneys exceeds the aggregate of:
(a) the amount the Contractor is otherwise still entitled to retain under the Subcontract; and
(b) the amount of the Contractor's unpaid moneys due and unsatisfied claims,
but the Contractor shall release the excess amount of Bank Guarantee and/or retention moneys held under this clause (if any), within 10 working days of the unpaid moneys due and unsatisfied claims being paid or satisfied.
…
9 On the face of it, cl 6.2 is not conditional on the respondent acting reasonably or establishing that it has a good claim. Nevertheless, the applicant submits that the provision of the Bank Guarantees acts as the provision of security and not as a risk allocation device as to which party should be out of pocket pending the resolution of a dispute. It points to the fact that the definition of "Bank Guarantees" in cl 1.1 of the Subcontract Agreement refers to the provision of the guarantees from an institution approved by the respondent "for the purpose of ensuring the [applicant's] performance of the Subcontract". I reject that submission. I do not think the definition has the effect of providing that the Bank Guarantees had effect as security, and not as security and as a risk allocation device, but even if it could be construed in that way, it could not prevail over the clear terms of cl 6 and the Bank Guarantees which were in the form provided in the Subcontract Agreement.
10 The contractual provisions in this case are in clearer terms than they were in Clough Engineering Limited v Oil and Natural Gas Corporation Limited [2008] FCAFC 136; (2008) 249 ALR 458 ("Clough Engineering"). In other words, it is even plainer in this case that the Bank Guarantees are a risk allocation device as to which party should be out of pocket pending the resolution of a dispute (Clough Engineering at 482 [99]). It may also be noted that this is not a case where there is an express requirement that the beneficiary of the Bank Guarantees act reasonably in seeking recourse to the Bank Guarantees as there was in Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 98 ("Sugar Australia").
11 Both parties accept that I must consider whether the applicant has established a prima facie case in the sense identified by Gummow and Hayne JJ in Australian Broadcasting Corporation v O'Neill (2006) 227 CLR 57 at 81-82 [65] (see also Gleeson CJ and Crennan J at 68-69 [19]) and that the balance of convenience favours the grant of an injunction.
12 The applicant relies on four grounds in support of its claim that it had a prima face case in the relevant sense. First, it submits that the respondent's recovery claim and liquidated damages claim do not fall within the terms of cl 6.2 of the Subcontract Agreement. Secondly, it submits that to the extent that cl 6.2 may otherwise enable the respondent to have recourse to the Bank Guarantees, it is void in the circumstances of this case because it purports "to annul, exclude, modify, restrict or otherwise change the effect of a provision" of the Act within s 99 of the Act. Thirdly, it submits that having regard to the circumstances it identified, it would be unconscionable within s 20 of the Australian Consumer Law for the respondent to have recourse to the Bank Guarantees. Finally, the applicant submits that for the same reasons it relies on in support of its third argument, to allow the respondent to have recourse to the Bank Guarantees would breach the respondent's implied obligation to act in good faith.
13 For the reasons which follow, I am not satisfied that the applicant has established a prima facie case in the relevant sense.