Matters relevant to the overflow from the Rising Main between 14 and 16 January 2020
Cause of the Rising Main failure
49. Sydney Water has stated that the Rising Main failed longitudinally along the bottom of the pipe due to erosion of the invert of the pipe. Sydney Water has obtained the following reports in relation to the possible root cause of the split in the Rising Main:
a. In 2019, Sydney Water prepared a report titled: "Water Main/Pressure Sewer Pipe Inspection Report", dated 22 January 2019.
b. In February 2019, Philip Ferguson, of Pipeline Condition Assessment, prepared a report titled, "Failure Investigation SPS213 SRM - Preliminary Comments", dated 4 February 2019.
c. In July 2019, Philip Ferguson and Ronald Christian prepared a further report titled: "SPS0213 - DN600 CICL Failure Investigation Report", dated 15 July 2019.
d. In September 2019, Philip Ferguson and Ronald Christian prepared, and Tania Gonzalez reviewed, a further report titled: "SPS0213 - DN600 CICL Failure Investigation Report", dated 12 September 2019.
e. In November 2019, Philip Ferguson prepared a report titled: "Failure Investigation Final Report of SP213", dated 15 November 2019.
f. In December 2019, Philip Ferguson prepared, and Dr Matthew Tai reviewed, a report titled: "Failure Investigation Final Report of SP213", dated 17 December 2019.
Previous conditions assessments relating to the Rising Main
50. In March 2007, Sydney Water obtained a report titled: "Condition Assessment of SPS213 Sewer Rising Main for SWC", dated 5 March 2007, prepared by Philip Ferguson, EarthTech.
Matters relevant to the overflow from the Pumping Station between 15 and 16 January 2020
Cause of the overflow from the Pumping Station
51. Before the shutdown of the Pumping Station, Sydney Water considered the risk that sewage would overflow from the Pumping Station while it was shutdown. Sydney Water arranged for tankers to be present to manage the level of sewage flowing into the wet well of the Pumping Station by removing it from the wet well and transferring it to an alternative location. An overflow from the Pumping Station into Prospect Creek commenced, which occurred when the tankers were not able to keep up with the inflow into the Pumping Station. Only two tankers were filled at any time.
Matters relevant to the Isolation Valve
Reports relating to the Isolation Valve
52. In October 2019, Ventia was engaged by Sydney Water to prepare a report titled: "Ventia Mechanical Report SPS0187 - Valve Preliminary Inspection". The report related to the isolation valve (see par 15 above).
Maintenance schedule relating to the Rising Main
53. Sydney Water has advised that the Isolation Valve was replaced on 12 September 2019.
Actual and potential harm to the environment
54. The overflows that are the subject of proceedings 2020/11340 and 2020/11341 resulted in actual harm to the environment in the form of direct alteration of the chemical and biological characteristics of Prospect Creek waters.
55. The direct alterations to the characteristics of Prospect Creek waters relative to background conditions were:
a. increased density of indicator organism faecal coliforms exceeding the Australian and New Zealand Environment and Conservation Council (ANZECC) Australian Guidelines for Water Quality Monitoring and Reporting (2000) by up to 7,800 times;
b. increased density of indicator organism enterococci exceeding background level by up to 1,120 times;
c. increased levels of ammonia;
d. reduced dissolved oxygen levels;
e. observed sewage odour;
f. observed turbidity and/or change in colour.
Appendix A