THE DEFENDANT'S OBERON OPERATIONS AND SURROUNDS
10. The Defendant holds Environment Protection Licence 3035 (the Licence) which permits the activities of "chemical production" and "'wood or timber milling and processing" at the Premises. A copy of the Licence is located at Tab 2.
11. The Defendant carries out the licensed activities in the course of processing and manufacturing wood panelling and joinery components. The Defendant receives woodchips and timber which it processes and treats in order to produce the manufactured products.
12. The Defendant's manufacturing process generates effluent. The effluent comprises both organic material extracted from the timber and woodchips prior to processing and the residues of chemicals used during the treatment and production process.
13. Condition L1.1 of the Licence prohibits the pollution of waters otherwise than in accordance with the requirements and limits set out in the Licence at condition L2.
14. The Licence permits the Defendant to lawfully discharge pollutants within prescribed limits, via a licence discharge point (the LDP). The location of the LDP is indicated at 'Site 6' on the Aerial Map.
15. The discharge of the Pollutant through the Hose into the Channel was not permitted under the Licence.
WOODCHEM PTY LTD
16. Located next to the Defendant's Premises in the Oberon Timber Complex is a chemical production facility, owned by Woodchem Pty Ltd ACN 080 088 777 (Woodchem). Woodchem is part of the Borg Group of companies and is a wholly owned subsidiary of Borg Investments Pty Ltd (ACN 123 740 287).
17. Woodchem manufactures and stores various chemicals, including formaldehyde, which the Defendant uses during the manufacturing and treatment process carried out at the Premises. Woodchem holds environment protection licence 11308 (the Woodchem Licence). A copy of the Woodchem Licence is at Tab 3.
18. Effluent containing chemical residues generated during Woodchem's chemical manufacturing process is received by the Sludge Dam on the Defendant's Premises for the purpose of being treated and re-used by the Defendant in its timber treatment and manufacturing process.
19. The Woodchem Licence permits the discharge to stormwater of various pollutants in limited concentrations via a licenced discharge point from a stormwater retention basin located on Woodchem's eastern boundary into the Drainage Channel upstream of the Defendant's LDP.
20. Rainfall runoff at the Woodchem Premises is diverted into the stormwater retention basin dam on Woodchem's eastern boundary.
21. Woodchem has not discharged any pollutants from its premises into the Drainage Channel via its licenced discharge point since 2011.
THE WASTE WATER TREATMENT PLANT
22 The Defendant's manufacturing process incorporates a wastewater treatment plant (the WTP) designed to capture, treat and re-use all water and effluent used and generated during the timber manufacturing process. The location of the WTP is indicated on the Aerial Map by the letters "WTP".
The Sludge Dam
23. A component of the WTP is the Sludge Dam, which is situated adjacent to the Premise's eastern perimeter and the Channel.
24. The Sludge Dam is separated from the Channel by a wire fence (the Wire Fence) and an earthen bank (the Earthen Bank). A photo showing parts of the Sludge Dam, the Wire Fence and the Earthen Bank is at Tab 4.
25. The Sludge Dam is approximately 60 metres long and 54 metres wide and has a holding capacity of approximately 10,000,000 litres.
26. The Sludge Dam receives and stores effluent from the following components of the Defendant's and Woodchem's manufacturing processes:
a. fluid from the chip wash and handling system;
b. fluid from boilers;
c. fluid from cooling towers;
d. fluid from condenser blow downs;
e. fluid from Woodchem boiler blowdowns;
f. fluid from Woodchem cooling tower bleeds;
g. wash water from Woodchem;
h. washwater from paper treater;
i. rainwater trapped in the WTP clarifier bund; and
j. rainwater washed into effluent drains.
27. The various streams of effluent received by the Sludge Dam contain substances and chemicals used in, or generated by, the Defendant's and Woodchem's treatment and manufacturing process including:
a. urea;
b. sodium hydroxide;
c. ammonium;
d. nitrogen;
e. formaldehyde;
f. traces of amino resins;
g. nitrogen compounds including melamine and urea; and
h. wood fibre.
28. After being allowed to settle in the Sludge Dam, the effluent was ordinarily pumped, via the Hose connected to a submersible pump located in the Sludge Dam, to a component of the WTP known as the sequential batch reactors. The sequential batch reactors are located immediately to the south of the Sludge Dam on the eastern perimeter of the Defendant's Premises. A photo showing part of the sequential batch reactors and the Sludge dam is at Tab 5.
29. The pump in the Sludge Dam is capable of pumping up to 180,000 litres per day at a flow rate of up to 125 litres per minute.
30. In the sequential batch reactors, the effluent undergoes a series of treatment and filtration processes before being re-used in various aspects of the Defendant's manufacturing process for purposes such as steam production and wash down water.
31. Up to and including 15 August 2014, the Hose was a flexible "layflat" hose approximately 50 metres long. The length of the Hose was designed to allow for the movement of the submersible pump to various locations on the bottom of the Sludge Dam to avoid clogging by sediment build-up within the Sludge Dam.
32. Prior to the Offence, the Defendant's employees had on occasions extended the Hose connected to the submersible pump in the Sludge Dam outside the Wire Fence onto the top of the Earthen Bank separating the Sludge Dam catchment and the Channel.
33. On these occasions the purpose of placing the Hose out on the top of the Earthen Bank was to avoid kinks forming when the submersible pump was moved closer to the sequential batch reactors. The Hose was also taken out of the Sludge Dam catchment onto the Earthen Bank to allow it to thaw out when it had become frozen and blocked.
34. Prior to the incident giving rise to the Offence, when the Defendant's employees placed the Hose on the top of the Earthen Bank above the Channel, it generally remained coupled to the sequential batch reactors. However, once or twice a year it had been uncoupled from the sequential batch reactors while remaining connected to the submersible pump in the Sludge Dam. The Hose had not previously been placed in the position it was on the day of the Offence.
35. Prior to the incident giving rise to the Offence the Defendant had not instructed its staff that the Hose should always be kept entirely within the Sludge Dam catchment and not taken outside the Wire Fence onto the Earthen Embankment.
THE DEFENDANT'S EMPLOYEES
36. At all relevant times the Defendant employed the following people:
a. Mr Mick Evans (Mr Evans) - Environmental Officer. At the time of the Offence Mr Evans had been employed in this position for approximately three and a half years. He was responsible for the day-to-day operation of the WTP. Mr Evans also supervised the Defendant's WTP operator, Mr Andrew Fagg.
b. Mr Andrew Fagg - WTP Operator. At the time of the Offence Mr Fagg had been employed in this position for ten years; and
c. Mr Aaron Evans - Process Development Manager. At the time of the Offence Mr Aaron Evans had been employed in this position for two and half years.
15 AUGUST 2014 - THE INCIDENT
37. Mr Evans arrived for work at the Premises at approximately 6:00am on Friday 15 August 2014.
38. At approximately 7:00am, Mr Evans switched on the submersible pump in the Sludge Dam in order to transfer effluent from the Sludge Dam to the sequential batch reactors. Mr Evans detected that there was no flow through the Hose which, at this stage, was connected to the sequential batch reactors.
39. Mr Evans uncoupled the Hose from the sequential batch reactors and determined that it was not flowing as it had become frozen for part of its length and therefore blocked.
40. Mr Evans then took the end of the Hose that had been coupled to the sequential batch reactors, dragged it through a gate in the Wire Fence and down the Earthen Bank. Mr Evans placed the end of the Hose at the edge of the Channel. Photos showing the position of the Hose and the Earthen Bank as placed by Mr Evans down the earthen bank to the Channel are at Tab 6.
41. Mr Evans intended to return to the Hose and recouple it to the sequential batch reactors, but forgot. When he completed his shift at the Premises, at approximately 2:30pm on 15 August 2014, the Hose remained in the same position on the Earthen Bank as placed by Mr Evans at approximately 7:30am that morning.
42. Mr Andrew Fagg was present on the Premises until 1:30pm on the day of the Offence. At no stage did he enter the Sludge Dam catchment or see the Hose discharging the Pollutant into the Channel. Mr Aaron Evans was also present on the Premises on the day of the Offence. Prior to being notified by the EPA, he was not aware the Hose had been placed down the Earthen Bank discharging Pollutant into the Channel.
43. Between approximately 7:30am and 3:45pm on 15 August 2014, an unknown quantity of Pollutant from the Sludge Dam was discharged through the Hose into the Channel, the Tributary and KSC (the Incident).
15 AUGUST 2014 - THE EPA INVESTIGATION
44. At approximately 12:30 pm on 15 August 2014, the EPA was notified of the Incident by Oberon Council Health and Building Manager, Ms Jaclyn Burns.
45. Ms Burns notified the EPA after inspecting various locations on KSC between "Site 10" and "Site 2" on the Aerial Map in response to a report of an offensive odour and black coloured water in KSC. The report was received at approximately 8:00am from the owner of a property in Shakespeare Close Oberon. The resident's property adjoins KSC approximately 2 kilometres downstream of the Defendant's Premises. The location of the resident's property is indicated at "Site 10" on the Aerial Map.
46. At approximately 2:15 pm on 15 August 2014, EPA authorised officers Mr Mark Clyne and Mr Allan Adams met Ms Burns and carried out an investigation of the Incident giving rise to the Offence.
47. During this investigation, Mr Clyne and Mr Adams inspected a number of locations along KSC and the Tributary before locating the Hose discharging the pollutant from the Sludge Dam on the Defendant's Premises into the Channel at approximately 3:30pm. At this time, the submersible pump in the Sludge Dam was switched on. A photo showing the Pollutant discharging from the Hose at is at Tab 7.
48. The discharge of the Pollutant from the Hose ceased at approximately 3:45pm when Mr Aaron Evans, after being notified of the Incident by the EPA, met Mr Clyne and Mr Adams and switched off the pump at approximately 3:45pm.
49. The water in the Channel, the Tributary and KSC, between the location at which the Hose was discharging and "Site 10" on the Aerial Map, was black in colour and emanated a strong offensive odour. A white scum was also present on the surface of the water in KSC and the Tributary in several locations.
50. The water in the Drainage Channel, upstream of the location at which the Hose was discharging was clear in colour and did not possess any odour.
51. The water in KSC, upstream of the junction of the Tributary and KSC was also clear in colour and did not possess any odour.
52. The water discharging from the Premises through the LDP was a light tea colour and had mild odour of pine sap.
53. There were no other sources of effluent discharging into the Drainage Channel between the Hose and the junction of the Channel and the Tributary immediately below the LDP.
54. Mr Adams took a number of water samples at various locations in KSC, the Tributary and the Channel. He also took a sample from above the LDP and the discharge of effluent directly from the end of the Hose. A copy of the report of analysis in relation to the water samples taken by Mr Adams on 15 August 2014 and a table indicating the locations at which those samples were taken is at Tab 8.
20 AUGUST 2014 - THE EPA INVESTIGATION
55. On 20 August 2014, Mr Clyne and Mr Adams returned to the Defendant's Premises and carried out further investigations and inspections in relation to the Incident.
56. Mr Adams took a number of water samples at various locations in KSC, the Tributary and on the Premises. A copy of the report of analysis in relation to the water samples taken by Mr Adams on 20 August 2014 and a table indicating the locations at which those samples were taken is at Tab 9.
57. During this inspection, the Hose was contained entirely within the Sludge Dam catchment and was connected to the sequential batch reactors.
58. After leaving the Defendant's Premises, Mr Clyne and Mr Adams returned to a pool of water on the Tributary which they had previously inspected on 15 August 2014. The location of this pool of water is indicted as "Site 5" on the Aerial Map. The water in the pool was black in colour and had a scum on the surface similar to that observed on the day of the Incident.
59. At the direction of Mr Clyne, the Defendant's employees removed the water and scum from the pool located at "Site 5" on the Aerial Map by pumping it to a location away from KSC.
60. Mr Clyne and Mr Adams then inspected locations on KSC indicated on the Aerial Map at "Site 2", "Site 9" and "Site 10".
61. The water in KSC at "Site 2" was clearer in colour than on the day of the Offence and there was only a slight odour present at this location. The water in KSC at both the locations indicated by "Site 9" and "Site 10" was also considerably clearer than on the day of the Offence with only a slight odour present and small amounts of surface scum trapped in obstructions in KSC.
23 SEPTEMBER 2014 - EPA INVESTIGATION
62. On 23 September 2014, Mr Clyne and Mr Adams returned to various locations along the Tributary and KSC and carried out further inspections in relation to the Incident.
63. Mr Adams took a number of water samples in KSC, the Tributary and in the Fish River. A copy of the reports of analyses in relation to the water samples taken by Mr Adams on 23 September 2014 and a table indicating the locations at which those samples were taken is at Tab 10.
ENVIRONMENTAL HARM
64. In relation to the environmental harm caused by the Offence, the Prosecutor relies on the affidavits of Moreno Julli, dated and filed 26 October 2015 and 24 March 2016.
65. In relation to the environmental harm caused by the Offence, the Defendant relies on the affidavit of Dr Daniel Martens dated 3 February 2016 and filed 9 February 2016.
DEFENDANT'S WRITTEN POLICES AND PROCEDURES IN PLACE AT THE TIME OF THE OFFENCE
66. At the time of the Incident, the Defendant did not have in place any written policies or procedures that:
a. specifically dealt with the steps to be taken by employees when the Hose connected to the submersible pump in the Sludge Dam became frozen; or
b. prohibited the placement of the Hose connected to the submersible pump in the Sludge Dam outside the Sludge Dam catchment area and onto the earthen bank adjacent to the Channel.
67. At the time of the Offence there was no procedures in place, such as logbooks or checklists, whereby the Defendant's employees were required to record actions taken in relation to the operation or movement of the Hose connected to the submersible pump in the Sludge Dam.
THE PRACTICAL MEASURES THAT MAY BE TAKEN TO PREVENT THE HARM CAUSED BY THE OFFENCE
68. The following practical measures could have been taken by the Defendant to prevent the harm caused by the Offence:
a. not placing the Hose outside the Sludge Dam catchment at the bottom of the Earthen Bank and into the Channel;
b. having appropriate policies and standard operating procedures in place;
c. instructing staff not to take the Hose outside the Sludge Dam catchment under any circumstances; and
d. replacing the Hose with a fixed pipe (see measures taken by the Defendant since the incident).
CONTROL OVER THE CAUSES THAT GAVE RISE TO THE OFFENCE
69. The Defendant had complete control over the causes that gave rise to the Offence.
MEASURES TAKEN BY THE DEFENDANT SINCE THE INCIDENT
70. The Defendant has taken the following measures to ensure that a similar incident does not occur again:
a. replaced the submersible pump and Hose with a floating pump connected to a fixed polyurethane pipe (the new pipe is not long enough to be extended outside the Sludge Dam catchment area and onto the earthen bank above the Channel);
b. introduced a 'Dam Checklist' standard operating procedure which includes daily monitoring of all dams on site including the Sludge Dam; and
c. Introducing a visible and audible level alarm system connected to the Sludge Dam.
PLEA OF GUILTY
71. The Defendant entered its plea at the earliest available opportunity.
COOPERATION WITH PROSECUTOR
72. The Defendant has cooperated with the Prosecutor at all stages of its investigation into the Offence, including by voluntarily making its employees available for recorded interviews and by agreeing to the matters in this Statement of Facts.
PRIOR CONVICTIONS
73. The Defendant has no prior convictions for any environmental offence.