CONSIDERATION
25 The obvious must be emphasised: Allied did not accept Eden's tender, and Eden has not sued Allied for breach of any kind of contract. Eden contends that there was a "process contract" between Eden and Allied, and that the State unlawfully interfered with that contract.
26 Eden refers to Hughes Aircraft Systems International v Airservices Australia (1997) 76 FCR 151 (Hughes)and Cubic Transportation Systems Inc v State of New South Wales [2002] NSWSC 656 (Cubic Transportation). The facts of Hughes were vastly different from those of the present case. In Hughes,there were two competing tenderers, the applicant in the proceeding being the unsuccessful one. Finn J held that in the circumstances of the case, there was an implied contract that might be called a "process contract", according to which Airservices Australia incurred implied contractual obligations in favour of the tenderers, including an implied obligation to conduct its evaluation fairly and in a manner that would ensure equal opportunity as between them. Cubic Transportation also concerned competing tenderers.
27 Eden's case as now presented is that there was a process contract between Allied and Eden, and that the DPWS induced Allied to breach that contract by not accepting Eden's tender. Eden has not referred to evidence of any competing tenderer on the scene. Indeed, Eden has not referred to any evidence of the terms on which it tendered to Allied. So far as I know, the circumstances were simply that Eden tendered; Allied was disposed but not bound to accept Eden's tender; and Allied decided not to do so for the reasons mentioned.
28 The first reason why Eden's present application fails is that Eden did not make the present claim at trial. Notwithstanding the attempt by Senior Counsel for Eden to suggest otherwise, the fact is that the relevant parts of Eden's amended points of claim alleged only that DPWS made representations to Allied and that as a result Allied did not engage Eden as its subcontractor on the Moruya Heads Project. Eden did not make submissions to his Honour in support of the existence of a tender process contract. A Full Court would not permit Eden to raise an entirely new case for the first time at the appellate level.
29 Secondly, Eden has not pointed to any circumstances giving rise to the supposed implied tender process contract or suggested what the content of the implied contract would be. These two matters are closely interrelated. On the hearing, I raised the following question: what was the implied contractual obligation that DPWS is said to have induced Allied to breach? However, in its post-hearing written submissions, Eden has not attempted to identify that obligation.
30 The evidence showed that Allied had heard bad things about Eden from the DPWS, and that Allied itself had become concerned over the attitude of Eden's managing director, and so had ceased to be of a mind to accept Eden's tender. So, perhaps it might be suggested that the implied contractual obligation was that Allied would not pay any attention to anything damaging to Eden that it heard or decline to accept Eden's tender on the basis of that information without giving Eden an opportunity to be heard, while remaining free to decline to accept it for other reasons. I do not accept that the relationship of principal and tenderer gives rise as a matter of law to such an implied obligation, including in circumstances where a job is tendered for and the principal's conduct evinces a present intention to accept the tender.
31 Thirdly, if we assume that the implied contractual obligation was of the kind that I have outlined, the State did not induce Allied to breach the supposed process contract. Rather, the State merely provided the substratum on which Allied's contractual obligation was enlivened. Indeed, the implied contractual obligation, formulated as I have suggested, would assume as its starting point that Eden had been "bad mouthed" by someone. The State would have had to do something further to induce Allied to breach the supposed process contract.
32 Fourthly, it is clear that Eden had consented to the DPWS's use of the information that it had gained from the Contractor Performance Reports in the way in which the DPWS apparently used that information. Although the primary Judge did not have to deal with this point, it is plain that his Honour would have held that the standard clauses set out at [15] and [16] above provided a complete answer to Eden's claim.
33 In addition to the above reasons, there are discretionary reasons why an appeal by Eden should not be permitted to proceed.
34 First, the present application is not Eden's first attempt to obtain an extension of time in which to file and serve notice of an appeal. On or about 4 July 2007, Eden made a similar application to the present one, and on 22 August 2007, Stone J dismissed that application and ordered that Eden pay the State's costs of that proceeding: see Eden Construction Pty Ltd v State of New South Wales [2007] FCA 1317. Eden did not raise the process contract argument before her Honour. Stone J permitted Eden to appear by its managing director, Mr Filardo. Eden applied for an adjournment of the hearing of its application on the ground that its impecunious situation had not permitted it to engage legal representation (see [35] ff below). Although it is understandable that the present process contract argument was not raised by Mr Filardo, the fact remains that it was not raised, and that the State incurred the costs associated with resisting Eden's application on that occasion.
35 Secondly, there is evidence suggesting that Eden is insolvent, or, at least, would not be able to satisfy a costs order made against it on the appeal, or to provide security for the State's costs of an appeal.
36 On 26 April 2006, Graham J ordered Eden to pay the State's costs of Eden's motion to file further amended points of claim. His Honour also ordered that such costs might be taxed and should be payable forthwith: see Eden Construction Pty Ltd v State of New South Wales [2006] FCA 476.
37 The State prepared and filed a party/party bill of costs pursuant to that order on 29 June 2006. Eden attempted to file a notice of objection but it was rejected by the Court because Eden had not lodged security for the costs of taxation in accordance with O 62 r 46(3)(d) of the Federal Court Rules. The amount that Eden was required to pay as security but did not was only $1,250. On 12 September 2006, the Court certified the State's party/party costs on the above motion to be $14,200.
38 On 22 September 2006, the State's solicitors wrote to the then solicitors of Eden, Johninfo Lawyers, enclosing a copy of the certificate of taxation and demanding payment, but there was no response. In the absence of a response, on 10 November 2006, the State obtained and had entered an order by the Court that Eden pay the State $14,200.
39 On 1 February 2008, the State's solicitors sent to Eden by prepaid post a statutory demand under s 459E of the Corporations Act 2001 (Cth) requiring payment in accordance with the Court's order of 10 November 2006.
40 Payment in accordance with the statutory demand has not been made by Eden, nor has Eden applied to set aside the statutory demand. There has been email correspondence between Bartier Perry, the solicitors for the State, and Erlington Boardman Allport, the present solicitors for Eden, in relation to the statutory demand, but these have not led to any kind of resolution.
41 In all the circumstances, even if I had thought that there was an arguable ground of appeal, I would nonetheless have dismissed the present application on the discretionary grounds that Eden did not raise the present point before Stone J, and would be unable to meet any order for costs if it should fail in the appeal or provide security for the State's costs of the appeal.