© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2021] WASCA 130
Court of Appeal (WA)
2021-07-27
Murphy JA
Original judgment source is linked above.
The primary proceedings - overview[3] The land
The planning and environmental work - broad overview
The course of the Project - overview and the breakdown of the relationship between the parties
In dealing with the second access road and the golf course issues, I referred extensively to Mr Aleksovski's evidence, and explained why I accepted it, with one exception.
The exception was his explanation as to why he raised tax issues with Mr Payton. While I reject his explanation, it does not cause me to conclude that he was overall an untruthful witness. It was one answer in three days of cross-examination. It is more likely that he was too embarrassed to admit that he was trying to manipulate the Shire.
I also previously dealt with what he wrote in the May 2013 Strategy, being the untrue statement that [Pastoral Co] had discovered a [capital gains tax] issue after conducting further investigation. I explained that, while this was troubling, I was not satisfied it was written as part of a larger plan to delay or impede implementation of the Project or because the [alleged Refusal to Proceed decision] had been made. It does not cause me to conclude he was an untruthful or unreliable witness. (footnote omitted)
(a) Mirvac had not, at any time, decided to exit the Project.[67]
(b) Any Mirvac decision to exit the Project would have involved him (Mr Draffen). No such decision was ever tabled for approval or made.[68]
(c) Mr Draffen never reached the view, nor was he ever told, that there was no prospect that BN would vary the Services Agreement.[69]
(d) Mirvac did not believe that it was contractually bound to complete the Project.[70]
(e) Despite making a provision for the loan to BN in 2013, the Project Team continued to work on the Project and did so irrespective of the (deadlock) provision in the Services Agreement.[71]
The judge's findings in relation to the alleged Refusal to Proceed decision
(a) Mr Adam Davidson's evidence, and the Approval for Additional Costs document, clearly indicated that the internal rate of return of 21% came from the 'Latest Approval (Q3 Forecast)' and not the 'Approval to Purchase' document;
(b) Mr Draffen's evidence did not contradict Mr Adam Davidson's evidence;
(c) quarterly updates (although not formally approved) became the baseline for future status updates;
(d) the deterioration was not serious in the sense that it was outside of any tolerable level; and
(e) counsel for BN was 'unable to provide a convincing reason as to why the Perth team would want to deceive the national team in the manner alleged'.
[BN] submitted that the [September 2013] Options Memo shows there was no possibility that an [Approval to Commence Construction document] would ever have been given in the future. I do not accept this. The express terms of the [September 2013] Options Memo, in setting out options and advising that consideration be given to pursuing the third, is entirely inconsistent with a decision having been taken to pursue only option 3 and, if it failed, to stop work on the Project. On the contrary, the implication from the [September 2013] Options Memo is that, if option 3 failed, one of the other two options would be followed. (footnote omitted)
I accept Mr Draffen's account of the meeting. As at 3 April 2014, Mirvac's position, with which Mr Waller agreed, was that Mirvac would do some more work around the potential for a Stage 1 that would present the Project in its best light. The prospect of renegotiating the Services Agreement was left open.
I do not accept that anything Mr Draffen said in the meeting manifested the intention alleged by [BN]. Indeed, even Mr Waller's purported minutes do not assert that Mr Draffen said that Mirvac had decided not to proceed. (footnotes omitted)
Summary of the judge's findings in relation to BN's claims against Mirvac (WA)
A court of appeal is bound to conduct a 'real review' of the evidence given at first instance and of the judge's reasons for judgment to determine whether the trial judge has erred in fact or law. Appellate restraint with respect to interference with a trial judge's findings unless they are 'glaringly improbable' or 'contrary to compelling inferences' is as to factual findings which are likely to have been affected by impressions about the credibility and reliability of witnesses formed by the trial judge as a result of seeing and hearing them give their evidence. It includes findings of secondary facts which are based on a combination of these impressions and other inferences from primary facts. Thereafter, 'in general an appellate court is in as good a position as the trial judge to decide on the proper inference to be drawn from facts which are undisputed or which, having been disputed, are established by the findings of the trial judge'.
the disadvantage that the appellate court has when compared with the trial judge in respect of the evaluation of witnesses' credibility and of the 'feeling' of a case which an appellate court, reading the transcript, cannot always fully share. Furthermore, the appellate court does not typically get taken to, or read, all of the evidence taken at the trial. Commonly, the trial judge therefore has advantages that derive from the obligation at trial to receive and consider the entirety of the evidence and the opportunity, normally over a longer interval, to reflect upon that evidence and to draw conclusions from it, viewed as a whole. (footnotes omitted)
An outcome of the Design Enquiry Forum was support for the provision of a second access road to the Binningup town site. This has the capacity to reduce traffic on the existing Binningup Road and provide a permanent secondary emergency access and quicker and more direct access to the proposed Village Centre from the south. The 'Local Structure Plan Traffic Report' (Riley Consulting, Dec 2008) provided as a technical supplement to this report identifies that from a traffic perspective a second access would not be required until more than 1500 new dwellings are constructed and occupied within the development. It is proposed to review this analysis when 750 dwellings have been constructed and occupied.
We need to be very careful not to end up encouraging approval for the northern half only, but at the same time inclusion of the second access road within the current approvals process could cause delays of the type significant enough for Mirvac to walk away from this project. (So focus hard as the above is very serious for all of us).
Second Access Road
Amendment 63 to Shire of Harvey District Planning Scheme No 1 is not contingent on the provision of a second access road to the town site and as such the second access road does not form a part of the proposal.
Council has granted consent to advertise the proposed Binningup Beach Local Structure Plan whilst noting that several modifications are required prior to final consideration. One of these modifications relates to the inclusion of provisions addressing secondary road access to Binningup.
The Shire of Harvey and Mirvac jointly commissioned a further study into the provision of secondary access to Binningup to clarify the likely need for such an access. The results of that study indicate that, although development of the area addressed by Amendment 63 alone (to the maximum yield likely to be possible under the proposed Local Structure Plan) would be unlikely to trigger a requirement of a second access road, a second access road may be required when the potential for new homes on vacant land in the existing town site and other development sites in Binningup are taken into account.
The Shire has therefore indicated that provisions addressing the need for a secondary access road be included in the proposed Binningup Beach Local Structure Plan. The provisions are to provide for planning, approvals and ultimately construction of secondary access to Binningup in a timely and coordinated fashion based on the point at which a particular number of lots are constructed (if at all). Should the trigger points (in terms of number of lots) be reached and the necessary approvals not be obtained, then further development would be precluded. (emphasis added)
The investigations, approvals and timing for the provision of a second public access road to the site will be undertaken in accordance with the following development milestones:
No further subdivision will be permitted beyond each of the stipulated milestones until such time as the relevant actions have been undertaken to the satisfaction of the Shire of Harvey.
Shortly afterwards, Mr Adam Davidson was asked if he knew, when he wrote the Project synopsis, that there was no agreed outcome between Mirvac and the Shire. He replied:
'I think it was my belief, at the time, that we either had or it was very unlikely that the outcome would change. I thought that we, at least, had a - outcome with the officers and that it was very likely that that outcome would be upheld by council at the time.'
Earlier in the cross-examination, Mr Adam Davidson had said, in the context of the Shire's EPA Letter:
'I guess in dealing with council officers, and particularly senior ones, you assume that they understand the limits of their own authority and operate within those.'
An outcome of the Design Enquiry Forum was support for the provision of a second access road to the Binningup town site. This has the capacity to reduce traffic on the existing Binningup Road and provide a permanent secondary emergency access and quicker and more direct access to the proposed Village Centre from the south. The 'Local Structure Plan Traffic Report' (Riley Consulting, May 2011) provided as a technical supplement to this report identifies from a traffic perspective a second access road would not be required until more than 1500 new dwellings are constructed and occupied within the development. ...
The pre-requisite triggers and timing for the provision of a second road have been agreed with the Shire of Harvey[.]
Revision B then set out the 2009 Trigger Provisions.
Final approval was received on the Federal Environmental referral and the Binningup structure plan was lodged in June. Detailed design of the subdivision is currently being finalised for application lodgement in September. A new feasibility is currently being undertaken as part of Q1 update. Given the reduced yield as a result of the environmental approval, it's likely that a review of the agreement with the current landowner will be undertaken to [ensure] returns to both parties are acceptable prior to commencement on site. (footnotes omitted) (emphasis added)
Yield decreased due to Federal Environmental issues. Three year delay due to Federal environmental issues. Discussing with the owner of the land a restructure of the [Services Agreement] to improve Mirvac returns. (emphasis added)
A variety of deal restructure scenarios are being considered prior to re‑entering negotiations with the landowner. Redesign incorporating new yield is realistic while seeking to optimise return on capital.
Mirvac has met with the land owner [BN] to discuss restructuring the agreement to provide a better return for Mirvac and we have agreed a target date of December 2011 to have an in principle agreement to revised terms.
Mr Waller used words to the effect that he understood what we were saying to him and what we were telling him. He also used words to the effect that, 'I know that we have to make this work for both parties and I will go away and consider what you're asking of me'.
Mirvac met with the land owner [BN] in December 2011 and there is an acknowledgement from the landowner that the project will be restructured. The land owner requested we meet in January along with his Trustee to workshop the project structure to seek an agreed outcome.
It was evident during the conversation that [Mr Waller's] views on the immediate and long term future of the project are polarised from Mirvacs [sic] position. As you are aware the position at project level is to progress to structure plan approval to protect our position and this was all endorsed in principle at the [Project Control Group meeting] - bringing with it an expectation on the face of it that the [Project Control Group] would be presenting an ACC [Approval to Commence Construction document] for subdivision works shortly thereafter - this being late July/August. It seems clear to me that at this point Mirvac [Development Approval Meeting] would not give this approval and the shareholders [Project Control Group] will then be at a potential deadlock.
...
[Mr Waller] requested another [Project Control Group meeting] at the end of June and he is expecting a timely response from Mirvac with respect [to] his stated position on the [Services Agreement] framework and the commitments there under from Mirvac.
Can we discuss this please at your best opportunity? It would appear the time has come to brief [Mr Wallace] and [Mr Draffen] on this and determine a course of action for Mirvac. (emphasis added by primary judge)
In my view, the document reflected Mirvac's view that it was unlikely there would be any sales (at least not of significance) in the five-year period. This is not surprising given the length of the Project (anticipated to exceed 20 years), the stage of the Project and Mirvac's view of the market conditions at that time and in the near future. The document does not show that a decision had been made never to proceed (or not to proceed unless the Services Agreement was varied). It recognised the current reality.
Counsel for [BN] put to Mr Draffen that 'the position is that you knew in June 2012 that Mirvac had made a decision - and you in particular on its behalf had made a decision - that Mirvac would not be proceeding to carry out the subdivision project at [BN]'. Mr Draffen said:
'That's incorrect. We - the position - we had never taken a position not to proceed with the project. Sure that it was - absolutely the project was - was financially challenging and we were attempting to find a pathway to at least come up with a viable Stage 1 to at least allow the project to proceed in some shape or form. Now, to proceed further, you know, our view at the time was that some form of renegotiation would be required for that to happen. But, no, we hadn't made we had absolutely not made a decision not to proceed.'
This does not show the [alleged Refusal to Proceed decision] had been made. On the contrary, it refers to negotiations 'to attempt to mitigate' the impact of certain matters. Further, in stating 'Current assumptions are predicated on a satisfactory renegotiation of pertinent elements of the Services Agreement', it merely records that Mirvac believed the Services Agreement would be varied and the development would proceed under a varied Services Agreement. It does not suggest that Mirvac had decided not to proceed unless the Services Agreement was varied. (emphasis added)
Mr Aleksovski said he did not have any involvement in the June 2012 Report and was not aware that the Project was monitored and reported on a watch list. It is, of course, not surprising that Mirvac would have a watch list for its marginal projects. The Project's presence on this list says nothing about whether the [alleged Refusal to Proceed decision] had been made. Later, I will set out the evidence that shows Mirvac made a provision in relation to the Binningup Project, to reflect the risk that the loan would not be fully repaid. As will be seen, Mr Aleksovski said that '[t]here were other projects with larger provisions that were eventually developed and that are still being sold now'. (emphasis added) (footnotes omitted)
I note the comprehensive Fire Management Plan which has been submitted however there has been no representation by Mirvac in regard to the Second Access timing. As you recall from our previous meetings, I have requested at the least, and upfront, an easement over the land and a legal agreement which includes the adjoining neighbour and all weather gravel/limestone construction with appropriate fire access gates. Plus a timing/programme to be agreed upon for its upgrading to a full roadway phases [sic]. This is a separate requirement from the FMP and is required to be resolved. I notice reference to 500 lots in your response to the submissions - however this figure has not been discussed or agreed upon by Council.
A variety of deal restructure scenarios were considered, however, negotiations with the landowner indicate that there is unwillingness to change. Therefore, continue to be modelled according to current [Services Agreement] in the Q1 FY13 forecast.
Mr Draffen said he thought the team was looking at various options but, because there had been no agreement with [BN], Mirvac continued to maintain a position of undertaking the Project in accordance with the Services Agreement. Mr Draffen agreed that the landowner [BN] had expressed an unwillingness to vary the Services Agreement. However, he said he did not think it was definitive and it was never reported to him that it was 'an absolute no'. He said Mirvac remained of the view that there was a potential for negotiation and said that he remembered subsequent reports from the team in late 2013 that continued to indicate that potential. He said:
'The team still remained confident of the potential for a negotiation. Again remember at this time there was still no structure plan approval, so it was very hard to advance the project until we actually got through all the required approvals to actually form up something that could be considered.'
This evidence is supported by Mr Waller's own evidence of his ongoing willingness to talk, but of wanting some progress to be made before any agreement was reached. I accept Mr Draffen's evidence on this point. (footnotes omitted)
Mr Draffen said that he thought the reason the forecast was anticipated to be based on the current Services Agreement was because, as at that time, it had not been agreed that the Services Agreement would be renegotiated. This explanation is consistent with the terms of the document and I accept it. The statement in the document, that the forecast is anticipated to be based on the current Services Agreement, is not consistent with the [alleged Refusal to Proceed decision]. (footnote omitted)
When asked if he knew that significant development expenditures had been deferred, Mr Aleksovski said no. He said he was never told to defer any expenditure and he did not defer any expenditure. He said he continued to incur costs to obtain the approval of the Plan, to maintain and manage various aspects of the Project and other miscellaneous costs. In relation to costs that would be incurred after Plan approval, he said that the Project had not reached that point, but said he was not aware of any decision to defer those costs. Mr Aleksovski said he was performing his duties.
Mr Draffen was not asked about this part of the document, or about similar statements in three other spreadsheets.
...
From the context given by the entirety of these documents, it appears that 'deferred' was being used in an accounting sense, in that anticipated (and budgeted) estimated expenditure was now likely to occur later in time. In any event, finance personnel had no authority to direct what was done by the Project team with respect to the Project.
I accept Mr Aleksovski's evidence that he had not deferred any expenditure. His evidence was consistent with the evidence that showed the work Mirvac was doing throughout the period when the Project was on foot. Further, as I later discuss, I found him to be a truthful witness.
Mr Aleksovski's evidence is also supported by Mr Draffen's evidence. Although Mr Draffen was not asked about the statements that expenditure had been deferred, he gave evidence as to the purpose of various financial records. He explained, for example, that the purpose of the June 2012 Report was to enable Mirvac to calculate the carrying value of its inventory in its statutory accounts. He also explained why the Board had taken a provision in relation to the Project, discussed later, and what that implied (and did not imply) about decisions Mirvac had made. Mr Draffen gave evidence about the interaction between Mirvac's development personnel and their finance personnel, saying that finance personnel had no authority to direct what was done by the Project team with respect to the Project.
Mr Draffen also gave evidence that Mirvac had not, at any time, decided to exit the Project. The statements in the spreadsheets to the effect that the forecast had been based on the Services Agreement are consistent with this evidence and inconsistent with the [alleged Refusal to Proceed decision]. I accept Mr Draffen's evidence. (footnotes omitted) (emphasis added)
The September spreadsheet also said 'The landowner is unwilling to review the present [Services Agreement] which may lead to a threat in the viability of the project'. Mr Draffen was asked about this. He said that, at that time, Mirvac knew the Project 'was challenged'. However, he said Mirvac did not believe that the Transaction Documents said that the Project would have to be developed irrespective of the market, as there were provisions in the Services Agreement that permitted Mirvac WA to approve (or disapprove) a budget and programme. He was asked if he was thinking along those lines at that time and he said 'we were just trying to find a viable way to move the project forward at this stage. You have to remember that at that time we didn't even have a structure plan approval'.
Mr Draffen's evidence that Mirvac did not believe that it was contractually bound to complete the Project under the Services Agreement is supported by a number of documents, and I accept this was Mirvac's belief. As I explain later, the belief was correct. (footnotes omitted) (emphasis added)
In the context of the spreadsheets as a whole, and the evidence as a whole, I am not satisfied that Mirvac did not spend money that it would have spent if it did not have concerns about the Project's viability. At the time these spreadsheets were produced, the [Local Structure Plan] had not been approved. Mr Aleksovski was working on obtaining the approval and was not deferring (and had not been told to defer) any expenses to achieve that. Perhaps in recognition of that, although these spreadsheets were in [BN's] Chronology, none were cited by [BN] in its written or oral closing submissions. (footnote omitted)
Project partner [BN] is aware of the issue and has expressed a willingness to work with Mirvac to achieve a suitable outcome for both parties however has indicated that certain terms and parameters of the original agreement are not negotiable. The impact amount is based on the current WIP of the project [if] an agreement cannot be reached.
The [Pastoral Co] has confirmed that it is willing to enter into the necessary arrangements to cede the required land to facilitate construction of the required temporary and permanent road access on the chosen alignment.
Further to the environmental approval process, the project yield has been reduced. However, there has been an unwillingness from [BN] to review the [Services Agreement]. Therefore, putting the viability of the project at threat. This may trigger an impairment to the loan balance currently carried.
The recoverability of the [Services Agreement] loan does not appear to be supported by the value of the land. ... The loan is secured against the development site but based on current assumed englobo valuation the security value is not sufficient to pay out the loan.
These documents show nothing more than that Mirvac recognised that, if the Services Agreement was not varied, it may need to make a provision to reflect the risk the loan would not be fully repaid.
There's no real way [Mr Waller] could stop the deadlock provisions being invoked. There is however scope to delay the provisions. There was no time limit placed on the preparation of a briefing paper outlining the dispute. So technically this could be said to being prepared for an extended time as a stalling tactic. We need to receive detailed legal advice in relation to how best to enact the deadlock provisions to ensure our actions are fully we [sic] are fully supported by the agreement. (emphasis added) (footnote omitted)
This email exchange shows Mirvac WA was considering the use of the deadlock provisions. It does not show Mirvac WA was contemplating breaching, or had decided to breach, the Services Agreement. Indeed, the last sentence is entirely inconsistent with such propositions.
The email exchange also does not show any decision had been made to cease to perform. The reference to a 'stalling tactic' is self-evidently a reference to the potential that [BN] would seek to delay the application of the deadlock provisions by delaying the production of its briefing paper. (emphasis added)
The assumption being adopted involves recouping the initial land advance of $25m. This requires the land owner agreeing to release Mirvac from its obligations under the [Services Agreement] and refund the initial $25m Land costs.
Currently, this is considered the most likely scenario as the land owner is unlikely to proceed through the deadlock provision (further explored below) as this would result in them losing control of the land which is considered the crown jewel of their holdings. The land owner would receive all the planning and other associated intellectual property for free and would be simply returning the initial land advance.
There are risks associated with this scenario as the land owner is considered litigious and may be willing to defend his rights in the courts. If this negotiation is handled correctly, an outcome that benefits both parties could be reached. The alternative course of action could be laid out as Mirvac following the deadlock provisions which would result in the land being sold for an amount well below the land owner's view of its worth.
There is no real way the land owner could avoid the deadlock provisions being invoked. There is however scope to delay the provisions. There was no time limit placed on the preparation of a briefing paper outlining the dispute, so technically this could be used as a stalling tactic. We will need to receive further detailed legal advice in relation to how best to enact the deadlock provisions to ensure our actions are fully supported by the agreement. (emphasis added by primary judge)
The first and last italicised phrases confirm that Mirvac had no intention of breaching the Services Agreement. The first phrase refers to obtaining [BN's] agreement to release Mirvac from its obligations. The last phrase shows that Mirvac intended to ensure any use of the deadlock provisions would be contractually permissible.
The second italicised phrase could perhaps be interpreted as a suggestion to use the deadlock provisions as, in effect, an inducement to pressure [BN] to agree to vary the Services Agreement. If that was what was meant, a question would arise as to whether using the deadlock provisions for this purpose would breach the Good Faith Obligation. However, [BN] did not cross-examine either Mr Aleksovski or Mr Draffen about this phrase, nor make any submissions about it in its closing address, nor refer to it in its Chronology. I assume this was because the phrase was, at most, a suggestion about doing something in the future that was never actually done.
As noted in the discussion of the January email exchange, the reference to a 'stalling tactic' is a reference to the potential that [BN] would seek to delay the application of the deadlock provisions. (emphasis in original)
The deadlock provision sets out a procedure for dispute resolution which eventuates in the land being sold for an agreed sum if the disagreement cannot be resolved. The funds are then used to pay down the loan balance.
Based on discussions with the land owner and based on our knowledge of their intentions, it is not envisaged that the land owner would allow the deadlock to escalate to this level.
This is considered the least desirable situation. This scenario would involve outlaying approx. $210m in development costs over a 22 year period and results in a shortfall in the loan repayment of $18m based on revised assumptions.
This scenario takes into account a lot settlement profile in line with independent market advice and knowledge of the current and forecast Binningup sales environment and is represented in the preceding chart.
[T]o renegotiate the agreement to be more balanced between the parties given the revised assumptions. It is difficult to model this scenario as it will be based on a negotiation between the parties, however the position would see some improvement on the $18m shortfall. The Revised Assumption position is still favoured even under this option to maximise any potential negotiations.
There have been recent developments on how the [Services Agreement] is structured and how Mirvac intends to proceed with the [Services Agreement]. Based on recent advice from Mirvac legal it has been determined that there is no scope for Mirvac to exit the [Services Agreement] as a result of the agreement not being financially viable.
Negotiations with the Land Owner are in the early stages only and will be expected to be escalated over coming months. (emphasis added by primary judge)
There is nothing in the Board Paper that manifests a decision to stop performing under the Services Agreement. Nor do I accept that it shows there was no possibility that an [Approval to Commence Construction document] would ever be given in the future. The recommended option was subject to [BN] agreeing to release Mirvac from its obligations. One of the identified alternatives was to continue development under the current agreement.
Further, inconsistent with any decision to breach the Services Agreement is the statement that further detailed legal advice was required in relation to how best to enact the deadlock provisions 'to ensure our actions are fully supported by the agreement'. Although the Board Paper acknowledged that 'there is no scope for Mirvac to exit the Services Agreement as a result of the agreement not being financially viable', it clearly recognised that this did not mean that the deadlock provisions were inoperative.
It appears to be common ground that, around this time, the Board made a provision for $18 million in accordance with the Board Paper.
Mr Draffen said that the decision to take an $18 million provision in relation to the Binningup Project was based on a risk assessment that a deadlock leading to a negotiated termination of the Project was the most likely scenario based on the information they had at the time. He said it was not a decision to actually set out to bring about a deadlock or to exit the Project.
Mr Draffen denied that all Mirvac was doing was taking steps to force the Project into deadlock. He said that the team continued to work through the necessary works to prove up Stage 1. He said the project team continued to work on the Project irrespective of the provision.
Mr Aleksovski said that the fact that the Binningup Project had been provisioned did not affect his work. He said that '[t]here were other projects with larger provisions that were eventually developed and that are still being sold now. We were still working on the basis of delivering a residential estate'.
The Board Paper is not inconsistent with any of this evidence and I accept it. (footnotes omitted) (emphasis added)
Mr Draffen also said that any decision to exit the Project would need to have been made at a level within Mirvac that involved him. He said that no position for exit was ever tabled for approval. He said that no decision to exit the Services Agreement had been made prior to 31 December 2012, nor was such a decision made subsequently.
I accept this evidence in its limited terms. That is, I accept that no decision to exit was actually made. However, I find that Mirvac was contemplating using the deadlock provisions to cause [BN] to make a deal, but was first going to obtain legal advice to ensure that whatever it did was contractually permissible.
I earlier noted that, in considering the internal Mirvac documents, I have taken into account the other evidence that shows what else was happening at particular times. In relation to the Board Paper, for example, I considered the fact that, less than two months after it was produced, Mr Aleksovski first asked Mr Payton about possible tax issues. However, having considered the evidence as a whole, I remain of the view that Mirvac did not, at any time prior to the termination of the Services Agreement, make a decision to exit the Project. (footnotes omitted) (emphasis added)
Management as at 31 December 2012 have revised their assumptions around the future growth prospects of the Binningup region, and now consider that the current slump in demand will be protracted for a prolonged period. A decision has therefore been made to now exit the [Services Agreement] via the deadlock provisions included in the [Services Agreement].
The revised assumptions for this project include the following:
The revised assumptions have led to a need for a provision against this loan receivable of $18.0m.
...
Our own assessment is that Mirvac should recognise a provision of $28.0m. The additional $10.0m provision is the difference between the best and worst outcome of negotiating an exit. This is considered prudent given that legal advice is yet to be received on how to utilise the deadlock.
We have raised our own assessment with management. We note that management's view of the provision is based on their assessment of the strength of their future negotiating position and an understanding of the landowners' future intentions. We accept management's position however have included our judgemental additional provision on our [Summary of Unadjusted Misstatements]. (emphasis added by primary judge)
It is evident from the context of the document that the statement that Mirvac had decided to exit the Services Agreement via the deadlock provisions was not intended to mean that Mirvac had decided to trigger the deadlock provisions, leading to a sale of the land, the requirement on [BN] to repay the moneys owing and the termination of the Services Agreement. This can be seen from the fact that the Board was not provisioning for the worst case scenario (that the land would be sold following a deadlock) and PWC's statement that Mirvac was assuming the land would not be sold following a deadlock.
Rather, PWC was asserting that Mirvac intended to achieve an agreement with [BN] that it would be released from its obligations under the Services Agreement and [BN] would repay the Initial Advance. PWC was asserting that Mirvac believed that it would be able to achieve that agreement due to its power to trigger a deadlock and its belief that [BN] would not want the land to be sold following the operation of the deadlock provisions.
Further, the two underlined references to legal advice in the above extract support a conclusion that Mirvac intended to act in accordance with its contractual obligations, and was still waiting on further legal advice.
Taken as a whole, the PWC Report does not evidence a decision to stop performing under the Services Agreement.
As with earlier documents, it shows that Mirvac intended to try to negotiate with [BN] in a contractually permissible way. Mirvac believed, correctly, that there were deadlock provisions in the Services Agreement that could lead to the land being sold. It believed, rightly or wrongly, that [BN] would prefer the land was not sold and would be willing to negotiate outside of the Services Agreement to release Mirvac WA from its obligations and repay the Initial Advance or to renegotiate the Services Agreement.
It is unclear what Mirvac understood about the circumstances in which a deadlock could be triggered. The documents suggest Mirvac was aware it could disapprove a budget, but that it did not understand the contractual limitations on that power. Mirvac appeared to consider that it could decide to disapprove a budget solely for the purpose of triggering the deadlock provisions which would cause [BN] to make a deal. However, Mirvac also consistently expressed an intention to act in a way that was contractually permissible and to obtain legal advice to ensure that it did. Taken as a whole, the documents show that Mirvac was contemplating using the deadlock provisions to cause [BN] to make a deal, but was first going to obtain legal advice to ensure that whatever it did was contractually permissible. Having this intention was not a breach of its contractual obligations.
There is no suggestion that, if contractually permissible options failed, Mirvac would cease to work on the Project. Further, I do not accept that Mirvac made any decision to delay or stop work on the Project pending the anticipated deal being made. In addition, later documents are inconsistent with such a decision. (emphasis added)
It is difficult to understand why Mr Cross was referring to Binningup in the context of an englobo sale. The financial documents before and after this date that referred to an outcome other than Project completion did so on the basis that the most likely outcome was that [BN] would retain the land and repay the $25 million Initial Advance, not that the land would be sold englobo. The provision of $18 million had also been made on the basis that this was the most likely outcome. Given this context, I do not accept that Mr Cross' email should be treated as supporting the proposition that Mirvac had decided that the land would be sold englobo or that they should seek to achieve that outcome.
In other words, unlike the developers on some of the other projects referred to by Mr Cross, Mr Aleksovski was saying that the Binningup land was not going to be sold englobo by 30 June. Indeed, if the scenario predicted by Mirvac occurred, the land would never be sold englobo - rather, [BN] would keep the land and repay the $25 million Initial Advance.
Mr Aleksovski's evidence was that, in referring to 'our strategy to exit', he was just reciprocating the language of the email he had received. Mr Aleksovski said:
'My role as project manager was to ensure the project got delivered. It was not my role to conduct any negotiations with Mr Waller directly about how we should structure the project. All I could do was try to find a solution to the issue of the loan shortfall, while also progressing the project to get the [Local Structure Plan] approved and start subdividing the land for development.
Although I was asked to look at the dispute and deadlock provisions of the Services Agreement, as far as I am aware, there was never a decision made at Mirvac to drive the Binningup project to a deadlock, nor was I ever asked to do that.'
Biningup [sic] Exit Strategy
High Risk
The assumption adopted for Q2 involved the recouping of the initial $25m land advance. This requires the land owner agreeing to release Mirvac from its obligations under the [Services Agreement] and refund the initial $25m Land costs.
Currently, this is considered the most likely scenario as the land owner is unlikely to proceed through the deadlock provisions as this would result in the loss of control of the land which is considered the crown jewel of their holdings.
In this scenario the land owner would receive all the planning and other associated intellectual property for free and would simply return the initial land advance.
There are risks associated with this scenario as the land owner is considered litigious and may be willing to defend his rights in the courts. If this negotiation is handled correctly, an outcome that benefits both parties could be reached. The alternative course of action would involve Mirvac following the deadlock provisions resulting in the land being sold for an amount well below the land owner's view of its worth.
Discussions have commenced with the land owner in order to facilitate this process. The first step is to determine how a budget deadlock can be initiated. The current intention is to agree project parameters and to have them agreed by external parties. Once this has been carried out it is proposed that an [Approval to Commence Construction document] will be submitted with the view of it being knocked back. Once the [Approval to Commence Construction document] has been knocked back it is assumed budget deadlock will be reached which raises the potential for the deadlock provisions to be enacted.
This is the point at which negotiations with the land owner will commence. Once in Deadlock the two parties will be presented with 2 scenarios:
This process is contingent upon many factors and a reliable timeframe is hard to define. Based on the current assessment the process is assumed to be finalised by Dec 2013. (emphasis added by primary judge)
Mr Draffen said that he understood the document to be addressing how the provision would be released, rather than a strategy as such. (Mr Draffen used 'released' to describe a provisional loss becoming an actual loss.) Mr Draffen said it looked like they were setting out potential ways in which the provision could be released over time, and noted that the document referred to further negotiations to be had.
This explanation is consistent with the email that prompted the drafting of this document and I accept it. Further, the finance team were not responsible for making decisions as to the progress of projects. Even if the email had reflected a decision made by Mr Wiese, he had no authority to direct Mr Aleksovski. In any event, there is no direction in this email that work on the Project should or would be stopped.
The document does record what Mr Wiese believed had been decided or what he was himself proposing - namely that it should be determined how a budget deadlock could be initiated. This is unremarkable.
Of more interest is the statement 'Once this has been carried out it is proposed that an [Approval to Commence Construction document] will be submitted with the view of it being knocked back'. This suggests that Mr Wiese was assuming that an [Approval to Commence Construction document] would be submitted for the sole purpose of being rejected, which would mean that the Mirvac representatives would then vote against the budget in the [Project Control Group] meeting, which may then lead to a deadlock (or at least he was proposing that this be done).
If in fact Mirvac WA had submitted an [Approval to Commence Construction document] on the basis that it would be disapproved which would lead to a deadlock, and had then put up a budget as a step in that plan, [BN's] case would be quite different. However, that was not done and that would explain why [BN] did not rely on this statement.
I accept Mirvac WA's submissions that this email exchange shows no intention to act contrary to contractual obligations. This is most easily seen from the first two italicised phrases. As with earlier documents, it records the prospect of using the deadlock provisions in a way that was contractually permissible and does not suggest any intention to delay or stop work on the Project pending the anticipated negotiated outcome. (footnotes omitted) (emphasis added)
Mirvac's instruction from the landowner is to proceed to formally requesting a deemed refusal on the [Local Structure Plan] if a decision is not forthcoming.
However, depending on Council's position, there may be an opportunity for further discussion to resolve the issue, but either way we need to be moving towards some form of determination.
The proposed extension (the Extension) is located on land held by a third party, namely [Pastoral Co] ... [Pastoral Co] has previously indicated that it was willing to enter into the necessary arrangements to provide the required land.
However, further investigation by [Pastoral Co] has revealed that provision of the required land via subdivision and private sale will trigger a significant tax implication for [Pastoral Co]. The provisional sum of this liability far exceeds the capital value of the land required for the Extension and is beyond the scope of [BN] to provide compensation.
It may remain open to Council to enter into separate negotiations with [Pastoral Co] to compulsorily acquire the required land. [Pastoral Co] has not advised [BN] whether this will trigger similar tax implications.
Second Access Road Strategy
Based on the new information detailed above the proposal for the provision of the SAR dated 17th December 2012 is no longer feasible. In lieu of this agreement, [BN] now proposes to provide the SAR for emergency purposes only, rather than as a gazetted road. As an act [of] good faith that recognises its previous undertakings, [BN] is still prepared to make a per lot contribution to the construction of a gazetted road in the event that the required land can be provided.
The approvals and timing for the provision of secondary access to the site will be undertaken in accordance with the following development milestones.
...
Previous discussions regarding a staged approach to this road have been that [BN] would upgrade a firebreak to a roadway after trigger points have been reached. In this scenario - the emphasis is on Council not [BN] to have the roadway gazetted and constructed. Why the change in approach? The revised strategy recognises that the financial implications of purchasing the land no longer make it feasible to be dealt with through a private sale. The suggested process is rather for the Shire to acquire the land by resumption under the DPS/Public Works Act (as applicable) to avoid the tax liability. [BN] will make appropriate contributions to the construction of the road as per 3 above.
Please refer to email response from [Mr Payton] below.
He is not willing to provide the tax advice as requested in order for Mirvac to satisfy itself that there will be no tax implications in the future and is suggesting that Mirvac rely upon his opinion based upon him achieving his recent qualifications and learning's [sic] - suffice to say this will not suit.
Our group tax manager was in Perth today and I discussed this with him at length and the basic answer is that like any acquisition Mirvac conducts, no matter how large or small, we need to understand the tax position of the entity we purchase from in order to structure the deal accordingly to meet Mirvac's and in this case [BN's] tax requirements.
Suffice to say, this is the exact reason why planning procedures do not and should not be incumbent and reliant on a third parties involvement in issues and matters that clearly can be resolved by the responsible local authority within the planning parameters and context set out by WAPC and [the Department of Planning].
Unless the Shire of Harvey are willing to change their stance on the second access road, Mirvac and [BN] have no option but to deem the [Local Structure Plan] refused by the Shire of Harvey and immediately move on with the [Local Structure Plan] process that has been ongoing since 2009 at a significant expense, to the point now where the project is at a rather precarious financial position - the impact of interest alone over the last 4 years is in the order of $8.4m.
Mirvac have always indicated that they would be happy to construct firstly an emergency access road into the site and then finally a sealed second road into Binningup and we are still committed to this occurring however there are various mechanisms for the Shire of Harvey to acquire the land with the current planning framework and this should be the case and not subject to Mirvac engaging a third party, and subsequently be held [to] ransom to do so.
I trust this clearly outlines our position on this matter and look forward to progressing the [Local Structure Plan].
As Council is not prepared to accept the terms of the Draft Second Access Road Strategy dated 27th May 2013 ... we have now reached a stalemate on this issue and we are obliged to trigger the deemed refusal provisions[.]
Project Description
... At Q3 FY13 Mirvac took an $18m provision on the loan balance to reflect the risk associated with the recoverability of the loan. [sic] and to reflect the current intention to exit the [Services Agreement].
Project Variances
The settlements over the next five years have been reviewed to take into consideration current market conditions and the delay in environmental and planning approvals. [BN] have also indicated that they are no longer willing to re-negotiate the [Services Agreement]. In addition, the recognition of interest income has been taken out from FY14 onwards in order to limit the exposure to the [Services Agreement] loan. Mirvac's strategic decision is to work towards a deadlock by Jun‑13 which has resulted in an impairment to the loan amount being taken up and a recovery of the initial loan of 25m from the [Services Agreement] partner by Jun-14. (footnotes omitted) (emphasis added by primary judge)
Mr Aleksovski said the document was a financial accounting document and, while he would have seen it, he would not have had any input into it.
Mr Draffen said:
'I think this is a forecast that reflects the fact that we've taken the impairment as at 31 December 2012 and for the purposes of financial projections going forward from an earning perspective and because of everything that was unknown related to the project at the time, that the forecast was just assuming the - effectively the same logic as the provision.'
The spreadsheet also said, under 'Project Risks':
'There are risks around the recoverability of the [Services Agreement] loan due to the underlying land value and the viability of future development. The FY13 Q3 forecast is based on the deadlock position by Jun-13 with a settlement outcome by Jun-14.'
Mr Draffen said this noted the risks of achieving the assumption that had been made for the purpose of the provision amount - because the provision amount relied upon negotiation between the parties.
Nevertheless, the italicised phrases disclose, on their face, an intention to work towards a deadlock and exit the Services Agreement. However, earlier documents show Mirvac had received some advice, but wanted to obtain 'further detailed legal advice in relation to how best to enact the deadlock provisions to ensure our actions are fully supported by the agreement'. The next document to be discussed suggests that it did get further advice.[311] (footnotes omitted) (emphasis added)
Mirvac advised the [Project Control Group] that it had formally advised the Shire of Harvey via correspondence dated 20th June 2012 [sic ‑ 2013] that as per the provisions set out in the District Planning Scheme, the [Local Structure Plan] was deemed refused due to the stalemate reached with the Shire in regards to the second access road and the [Local Structure Plan] was now with WAPC for consideration.
...
Mirvac advised ... that it had drafted a strategy (as per the requirement of the Scheme Amendment) in regards to the preferred location, construction standard and timing of the second access road to the project. The preferred location, construction standard and timing of the second access road was agreed with the Shire of Harvey at a meeting in August 2012 to be funded by depositing in a trust account $4000/lot from the sale proceeds of the first 500 lots being sold and settled, such than an amount of $2m will be available to the Shire of Harvey to construct the road. The Shire of Harvey was advised by Mirvac that the land required for the second access road will need to be negotiated with [Pastoral Co] and acquired by the Shire within the limitations of the existing planning framework as it allowed for the compulsory acquisition of land for public roads. The Shire of Harvey has since decided that the second access road is a priority and has refused to assess the [Local Structure Plan]. (emphasis added by primary judge)
2, Mr Aleksovski was not seeking to delay the Project by the Deemed Refusal Notice as, had he been seeking to do so, he would not have reiterated in the Deemed Refusal Notice the commitments to provide emergency access to the site and monetary contribution to the future construction of a second access road and that BN was willing to enter into a legal agreement confirming those commitments.
negotiations between Mirvac and [BN] in respect to the [Services Agreement] could in fact be held and completed between both parties outside of the current agreement framework. It was suggested by Mirvac Legal that this be the preferred option, subject to Mirvac having a preferred outcome that it wished to achieve.
'consistent with our approach that we wanted to try and find a way, with Mr Waller, to agree a way to move forward and part of that would have been to continue those negotiations. Equally, it was focused on trying to agree a logical way to move forward with Stage 1 of the project. ... what we were hopeful of is that we could agree to - a pathway to move forward with a logical Stage 1 and that may or may not have, at the time, depending on the negotiations, resulted in certain amendments to the [Services Agreement] but it was subject to a negotiation.'
Mr Draffen himself later had discussions with Mr Waller. He said:
'[I]t was trying to land on options to move forward. Those options may or may not have involved variation to the [Services Agreement]. That was something that would have needed to be negotiated. The focus of my input post that was, really, trying to work with the team to find a solution to advance the project with a logical Stage 1.'
[BN] submitted that the [September 2013] Options Memo shows there was no possibility that an [Approval to Commence Construction document] would ever have been given in the future. I do not accept this. The express terms of the [September 2013] Options Memo, in setting out options and advising that consideration be given to pursuing the third, is entirely inconsistent with a decision having been taken to pursue only option 3 and, if it failed, to stop work on the Project. On the contrary, the implication from the [September 2013] Options Memo is that, if option 3 failed, one of the other two options would be followed. (footnote omitted)
Yesterday myself, [Mr Scott] and [Mr Doyle] met with [Mr Parker] and [Mr Hall] at the Shire of Harvey's offices in Harvey.
Our main discussion was the current impediment delaying the Binningup approvals from the Harvey Shire.
We had a very cordial and open discussion with both [Mr Parker] and [Mr Hall]. [Mr Hall] did mention that his dealings with both you and [Mr Pearce] have been very good.
The Shires [sic] position is that there must be agreement with the Shire of Harvey by [BN] that it agrees to construct the 2nd access road at the same time as the 1st stage of development is undertaken as planned in the submissions to council.
We have been assured this is the only matter now outstanding with the Shire. When this commitment is dealt with the Shire will be pleased to have the planning matters put to the next earliest meeting to have the matter dealt with. (There may [be] some other small issues but would not hold up the approval process.)
On behalf of [BN] we committed to [Mr Parker] and [Mr Hall] we would agree to their request for the 2nd access road construction and immediately make arrangements to acquire the land in question.
[Mr Aleksovski], I am aware you have discussed the price with the vendor, we now need to arrange the purchase of this land for the price discussed. Can you and or [Mr Pearce] please arrange to meet with the vendors and make the necessary arrangements.
[Mr Hall] has agreed to supply us with a note which will cover the Shires [sic] expectation for inclusion in our official commitment letter.
Could you or [Mr Pearce] contact [Mr Hall] to discuss the details. (emphasis added)
I just highlighted to him that, look, you know, we were heading down a certain path. We were close to getting the structure plan approved, because previous to that I had - I had submitted a deemed refusal to - to the Shire of Harvey, because they hadn't dealt with the structure plan in - in - in accordance with the provisions of the scheme in a timely manner. And I just highlighted concerns that, look, the - the adjoining neighbours, being the [Paytons] or [Pastoral Co], now knew that we needed this - this road as part of Stage 1. So, you know, my concerns that I raised with Mr Waller was, 'What if these guys turn around and say, 'Well, we want one, two, three million dollars for this,' for this piece of land that's now deemed to be pretty strategic? Because without it we can't commence development'. You know, well, we could potentially be - be held to ransom by - by them, which is effectively what - what the Shire of Harvey were doing to us at the time. They were trying to hold us to ransom with this particular - particular road. And I remember Mr Waller saying to me, 'Look, I've dealt with the [Paytons] over the time. I know them pretty well. They're good people. Don't worry about it. I will handle the acquisition of the land for the road'. (emphasis added)
After consideration by the Shire the proponent of the two options the extension of the Springhill Road was selected as the preferred option. It has been agreed with the Shire that the land required for the road will be acquired by [BN] and the road will be constructed to a sealed and line mark standard to the specification of the [Shire], and reserved as part of the works for [Stage 1] of the development. This commitment is secured by the inclusion of relevant provisions of Part One, Table 4 - Provision 4 of the Local Structure Plan.
As conditions of the first stage of subdivision the [Shire] will require the landowner/applicant to:
(1) Secure the land required for the second access road, being an extension of the existing Springhill Road to the subject site, on an alignment generally in accordance with that depicted in the Local Structure Plan (Plan 1);
(2) Construct and drain the road at the full cost to the landowner/applicant; and
(3) Set out the road reserve on a separate diagram or plan of survey ... and transfer the road free of cost to the Local Government for road purposes and without any payment of compensation.
I accept Mr Draffen's account of the meeting. As at 3 April 2014, Mirvac's position, with which Mr Waller agreed, was that Mirvac would do some more work around the potential for a Stage 1 that would present the Project in its best light. The prospect of renegotiating the Services Agreement was left open.
I do not accept that anything Mr Draffen said in the meeting manifested the intention alleged by [BN]. Indeed, even Mr Waller's purported minutes do not assert that Mr Draffen said that Mirvac had decided not to proceed. (footnotes omitted)
I accept that evidence. However, I do not consider Mr Lawrance's statement was repudiatory or one which manifested the intention alleged by [BN]. As will be seen, Mirvac WA had the right to disapprove a budget as a member of the [Project Control Group]. Before a [Project Control Group] meeting at which a budget was to be approved or disapproved by the [Project Control Group], it is to be expected that Mirvac would go through an internal approval process to enable their representatives on the [Project Control Group] to be in a position to vote appropriately, as explained by Mr Draffen in a passage extracted above. There is nothing repudiatory or sinister about this. Indeed, Mr Waller said he would think that would be logical. (footnotes omitted)
Clause 5.10(c) of the Services Agreement provides that [Project Control Group] meetings may be conducted by telephone conference, video conference or any similar means of audio or audio-visual communication. Neither it, nor any other clause, provides for the recording of meetings.
Mirvac WA's refusal to agree to meetings being recorded was not a breach of its obligations, good faith or otherwise. I am also not satisfied it refused in order to delay or stop the Project. The documentary evidence showed that, by September 2014, the relationship between the parties was combative. Mirvac WA had said it was willing to attend a meeting if it was not recorded, and was willing to pay for an independent minute-taker. This was not an unreasonable stance, in all of the circumstances. Mirvac WA's Good Faith Obligation did not require it to agree to the meeting being recorded.
Either party could have utilised the dispute resolution process in the Services Agreement to resolve the issue. Instead, [BN] sent its Termination Notice.
Errors of fact - second access road, golf course and Mirvac's internal documents
The judge erred in fact in accepting, at [115] and [144], Mr Adam Davidson's evidence about the purpose of avoiding the imposition of a condition of planning approval requiring immediate construction of a second access road. Mr Adam Davidson's evidence was contradicted by his 24 August 2009 email to Mirvac's consultants, containing the draft of a proposed response by the Shire to the EPA.[374] The correct inference, based on the 24 August 2009 email and Mirvac (WA)'s subsequent conduct referred to in grounds 6.3, 6.4, 6.6 and 7 - 11 below, was that if such a condition were imposed it would cause Mirvac (WA) not to proceed with the Project.[375]
The judge erred in fact in finding, at [150] and [158], that the email from Mr Aleksovski to Mr Hall of the Shire dated 5 September 2011,[376] and the email between Mr Adam Davidson of Mirvac (WA) and Mr Jake Davidson of the Shire dated 9 September 2009,[377] recorded a preliminary agreement between Mirvac (WA) and Shire Officers. Instead, they were nothing more than an incomplete preliminary negotiation concerning a draft provision for inclusion in a Local Structure Plan, having regard to the terms of the email.[378]
The judge erred at [158] - [163] in construing the words 'agreed outcome with the Shire' in Mr Adam Davidson's 'handover notes' to Mr Aleksovski in an email dated 22 May 2010[379] when (1) as alleged in ground 6.3, there was no such agreement with the Shire, and (2) the adoption of a Local Structure Plan required a resolution of the Council of the Shire, and not merely an agreement reached with a Shire Officer, as Mr Adam Davidson accepted (at ts 561.2).[380]
Accordingly, the correct inferences were (1) Mr Adam Davidson knew that there was 'no agreed outcome with the Shire' as stated in the handover notes, (2) the reason that he made the note was, in effect, to dishonestly create a false record to enable his successors to falsely represent to the Shire that a binding agreement had been reached with the Shire,[381] and (3) the reason that Mirvac (WA) wished to assert such an agreement was that it would enable it to be able to increase the value of the Project land by obtaining a rezoning which was not conditional on the construction of a second access road - a matter put to Mr Adam Davidson at ts 392 - 393.[382]
The judge erred in fact at [159] in accepting the evidence of Mr Adam Davidson and Mr Aleksovski insofar as they referred to agreements with 'the Shire' as meaning the results of their discussions with Shire Officers and not a binding agreement with the Council. The correct inference was that both witnesses knew that any agreement reached with officers of the Shire concerning the terms of a Local Structure Plan would require approval by the Council, in order for the Local Structure Plan to be adopted by the Council.[383]
The judge erred in fact at [172] in finding that (1) an agreement had been reached about trigger points as to the need for and timely construction of a second access road, and (2) that Mr Aleksovski's statement in an email responding to Mr Hall of the Shire dated 5 September 2011[384] was not false, when Mr Aleksovski said in his witness statement that 'a negotiated position with respect to the second access road was agreed [by Mr Adam Davidson and Mr Jake Davidson] and other council departments concerned'. Rather, his evidence was false and the judge should have inferred that Mr Aleksovski knew that there had been no negotiated position, and that there had been no agreement binding on the Shire, because the draft provision had not been adopted by a Council resolution adopting the Local Structure Plan.[385]
The judge erred in fact in finding, at [179] - [181], that BN's assertion (at 3.4.7 and 3.5 of its closing submissions[386]) that Mr Adam Davidson was acting to avoid costs being incurred before the Local Structure Plan was approved, did not make sense.[387] BN's assertion at the time was that Mr Adam Davidson was acting to avoid the carrying out of the construction of a second access road (which was required to satisfy a condition of approval of the Scheme Amendment itself) so that Mirvac (WA) could obtain the benefit of the Scheme Amendment increasing the value of the Project Land, but without having to pay for the construction of a second access road before the Scheme Amendment became operative.
The judge erred in fact in finding, at [205], that the December 2012 Strategy document[388] was a draft, when she should have found that it was the final version of the document which was sent to the Shire, given that the May 2013 Strategy[389] referred in its terms to a 17 December 2012 strategy document.[390]
The judge erred in fact in finding, at [215] - [216], (1) that the December 2012 Strategy did not reflect the final version given to the Shire, and (2) that, alternatively, other discussions had occurred after the December 2012 Strategy had been given to the Shire. Rather, the correct inference to be drawn from the 17 December 2012 Strategy,[391] and the May 2013 Strategy,[392] was that the italicised part of a responsive email from Mr Pearce (the consultant) to Mr Hall of the Shire dated 27 May 2013[393] at [215] was inaccurate.[394]
The judge erred in fact and law in finding, at [233], that the WAPC would have objectively considered whether it was appropriate to require Mirvac (WA) to acquire the land for what was to be a public road, in that (1) the WAPC knew[395] that Pastoral Co was prepared to sell the land, (2) the WAPC knew[396] that Pastoral Co had refuted the statement in the May 2013 Strategy that it would experience significant CGT issues on a sale, and (3) a condition requiring the developer to pay for the cost of acquiring a public road was a valid condition of a subdivision approval.[397]
The judge erred in fact in finding, at [263] - [270], that Mirvac (WA), through Mr Aleksovski, did not attempt to cause Pastoral Co not to sell the land as part of a larger plan in order to impede the implementation of the Project. The judge should have found that Mr Aleksovski did attempt to cause Pastoral Co not to sell the land, and that this was part of a larger plan to delay implementation of the Project because (1) the judge, having rejected Mr Aleksovski's explanation as to why CGT issues were raised with Pastoral Co,[398] ought then to have inferred that Mirvac (WA) was attempting to cause Pastoral Co not to sell the land for the second access road, and (2) Mr Aleksovski's discussions with Pastoral Co occurred over a period in which the books of Mirvac, as alleged in ground 10 below, indicate that Mirvac contemplated using the deadlock provision in the Services Agreement to persuade BN to agree to vary the Services Agreement. BN alleges that, therefore, the compelling inference to be drawn is that Mr Aleksovski was, in accordance with that position, attempting to cause Pastoral Co not to sell the land so as to delay progress of the Project.[399]
The judge erred in law at [341] in construing Mr Crockett's email dated 24 May 2012.[402] This email should have been construed as recording that (1) Mirvac's position was to progress to the point where the Local Structure Plan was approved 'to protect Mirvac's position', and (2) the Project Control Group had approved in principle the progression of the approval of the Local Structure Plan but had not done so 'to protect Mirvac's position'. Consequently, the judge erred in fact in not finding that Mr Crockett's email dated 24 May 2012 was a continuation of Mirvac's position reflected in the 24 August 2009 email (as alleged in grounds 6.1 and 6.2).[403]
The judge erred in fact at [350] - [352] in finding (by accepting Mr Draffen's evidence) that, as at June 2012, Mirvac had not manifested the alleged Refusal to Proceed decision. That is because Mr Draffen admitted at ts 668 - 669 that some form of renegotiation of the Services Agreement would be required for the Project to proceed past a viable Stage 1.[404]
The judge erred in fact at [356] in accepting Mr Draffen's evidence about the HY13 Draft Scenario document,[405] produced on 1 July 2012, which referred to 'englobo/superlot'. Mr Draffen's evidence was incorrect because Mirvac's position, as at June 2012, was that renegotiation of the Services Agreement was required for the Project to proceed past a viable Stage 1. Accordingly, the compelling inference was that Mirvac had implemented a strategy 'to proceed with an englobo sale of the Project [l]and unless there was a negotiated exit by Mirvac from the [Services Agreement] or a renegotiation' on terms favourable to Mirvac. Reference is made in this ground to Mr Draffen's evidence at ts 668 - 669 and 738 ‑ 739, and the HY13 Draft Scenario document to which Mr Draffen referred.[406]
The judge erred in fact and law in finding (with reference to Mr Draffen's evidence) at [374] that 'Mirvac did not believe' that it was contractually bound to complete the Project under the Services Agreement. The judge should have found, on the basis of Mirvac's books and 'other documents', that 'Mirvac personnel' including Mr Draffen held the view (based on advice) that (1) Mirvac (WA) was bound to carry out the Project under the Services Agreement, and (2) because of that, Mirvac was unable to exit the Services Agreement merely because Mirvac considered it not to be financially viable. Reference is made in this ground to the September 2013 Options Memo[407] and Mr Draffen's evidence at ts 698.[408]
The judge erred in fact and law in finding, at [380] ‑ [382], that as at January 2013 Mirvac had made no decision to cease performing the Services Agreement. The compelling inference from Mirvac's books (with reference to Mirvac's internal emails dated 22 January 2013 and 23 January 2013[409]) is that, whilst needing to receive legal advice as to how best to 'enact the deadlock', Mirvac 'had decided to cease to perform the [Services Agreement] and to enact the deadlock provisions'.[410]
The judge erred in fact and law, at [383] - [408], in finding that, as at February 2013, Mirvac had not made a decision to cease performing the Services Agreement. The compelling inference of the 4 February 2013 Board paper[411] is that Mirvac had no intention of performing the Services Agreement to completion unless BN agreed to a variation favourable to Mirvac.[412]
The judge erred in fact and law in finding, at [376] ‑ [378], that the agenda including the 25 October 2012 Risk Assessment,[413] and the 17 December 2012 spreadsheet,[414] did not provide a compelling inference that Mirvac was making a provision in respect of BN's debt on the basis that Mirvac had decided not to proceed with the Services Agreement and had decided to sell the land englobo if it could not procure a satisfactory variation of the Services Agreement.[415]
The judge erred in fact and law in finding, at [409] ‑ [417], that the PWC Report dated 7 February 2013[416] was not evidence of a decision by Mirvac 'to stop performing under the [Services Agreement]'. The compelling inference from the PWC Report is that Mirvac had decided to utilise the deadlock provisions, thereby manifesting the alleged Refusal to Proceed decision, and the only remaining issue was the method by which the deadlock provisions were being engaged.[417]
The judge erred in fact and law, at [432] - [437], in finding that in Mirvac's June 2013 Forecast document,[418] Mirvac had not evinced an intention to move towards deadlock and exit the Services Agreement and thus had not implemented the alleged Refusal to Proceed decision. Notwithstanding the evidence of Mr Aleksovski and Mr Draffen referred to at [433] - [434], the 'books and documents' in ground 10 provide a compelling inference that Mirvac had such an intention and had implemented the alleged Refusal to Proceed decision.[419]
The judge erred in fact and law in finding, at [446], by reference to the September 2013 Options Memo, that if Mirvac failed to renegotiate the Services Agreement, it would have continued to carry out the Project pursuant to the Services Agreement. The fact was that Mirvac, as at June 2012, had no intention to proceed past a viable Stage 1 if no renegotiation satisfactory to Mirvac occurred and, that being the case, the compelling inference was that, as at September 2013, that position had not changed. Mirvac had no intention to carry out the Project pursuant to the Services Agreement if a renegotiation satisfactory to Mirvac was not achieved.[420]
The judge erred in fact and law at [316] - [508] in:
(i) not holding that the books of Mirvac were prima facie proof of Mirvac's position and binding on Mirvac; and
(ii) accepting evidence from Mirvac officers asserting that particular books had effect and meaning different from the clear terms of the books.[421]
Mr Lawrance's statement on 13 June 2014 - alleged repudiatory statement
The issue of meetings of the Project Control Group being recorded - alleged repudiatory conduct
Mirvac's non-submission of a Programme Budget in relation to Subdivision and Construction Works
Tort of interference with contractual relations - Mirvac Ltd
17.1 The judge erred in law in holding, at [814], that the concept plan provided by BN's expert, Mr Maiorana, provided a shaky foundation for the valuation experts to provide their expert opinion.
17.2 The judge erred in law in holding, at [826], that Mr Maiorana's concept plan was an inadequate foundation for the valuation.
17.3 The judge erred in law in holding, at [823] - [827], that BN failed to prove what might have been implemented as a concept plan, as a result of Mr Maiorana's concept plan being inadequate, and that it would have been relatively simple and inexpensive for Mr Maiorana to prepare a suitable concept plan for these purposes.
17.4 The judge erred in law in holding, at [828] - [833], that BN was required to provide a net present value calculation or submissions as to an approach that the judge should take in assessing damages.
17.5 The judge erred in law in holding, at [876], that sales of lots would have commenced by May 2015 for the purposes of assessing the amount of the Initial Advance that would have been repaid by the proceeds of sale by the Anniversary Date.
18.1 Mr Maiorana's concept plan was an adequate foundation for the valuers to base their valuations on as it was based on Mirvac (WA)'s own plans;
18.2 BN was not required to prepare a concept plan that addressed Mr Maiorana's concerns as to requiring further input from necessary experts as this would have caused BN to incur costs which 'were entirely disproportionate to the task of preparing a concept plan for the assessment of damages';
18.3 BN was not required to adduce expert evidence of net present value as the uncertainty as to when possible subdivided lots would be sold and resulting uncertainty as to the projected selling prices for particular subdivided lots made calculation of net present value impossible; and
18.4 there was sufficient evidence adduced to enable the court to assess damages.
19.1 but for the operation of that principle or doctrine, Mirvac (WA) would have been entitled to enforce a judgment debt far in excess of the value of the Project land against the Project land under the Project Securities; and
19.2 BN retaining the Project land unencumbered by the Project Securities is a consequence of that principle and/or doctrine, and not a consequential advantage to BN of termination of the Services Agreement which should be deducted from its loss of bargain damages resulting from the Project not being carried out to Completion.
(i) the right of the Contractor to recover amounts owing by the Principal to the Contractor under this document is limited to the Contractor taking action to enforce:
(A) a judgment against the Principal against the Project Assets; and/or
(B) the Project Securities; and
(A) enforce a judgment against the Principal other than:
(1) against the Project Assets; and/or
(2) to enforce the Project Securities;
(B) apply to have the Principal made insolvent; or
(C) enforce a judgment or order or take any other action against the Principal's property other than permitted under this clause 1.5.
The Principal remains liable to pay all amounts which may from time to time be payable by it under this document.
(i) prevents the Contractor from bringing proceedings against the Principal to prevent any amount owing by the Principal to the Contractor under this document becoming statute-barred;
(ii) prevents the Contractor from applying to make the Principal Insolvent or taking any other action in the Insolvency of the Principal if another creditor has taken action to have the Principal made Insolvent; or
(iii) prevents the Contractor from seeking or obtaining equitable relief (including a declaration) in connection with this document or a Security other than an order requiring payment of money by the Principal to the Contractor otherwise than in accordance with this clause 1.5.
(a) a copy of any proposed Budget or Programme for a Stage for approval or disapproval by the Project Control Group; and
(b) a report setting out specified information including such other information 'as the Principal may reasonably require'.
If:
(a) a quorum is not present within 30 minutes of the time specified for the adjourned meeting of the Project Control Group; or
(b) a decision before the Project Control Group becomes deadlocked; and that deadlock is not resolved within 10 Business Days of the deadlock arising,
any resolutions to be put at that Project Control Group meeting or the deadlocked decision (as the case may be) must be determined under cl 15. (emphasis added)
(a) each of the parties must prepare a Briefing Paper setting out how that party would like the matter to be resolved, the outcome to each party if the matter were resolved in that manner and, if possible, the outcome for the Project if the dispute were resolved in that manner;
(b) the dispute and the Briefing Papers are to be referred to the Chief Executive Officers of the parties for resolution jointly and if the Chief Executives are able to resolve the matter, the parties must implement their decision; and
(c) if the Chief Executives cannot resolve the dispute, the parties must submit the dispute to an independent Expert for Expert determination as specified in cl 15.4(f).
The determination of the Expert:
(i) must be in writing;
(ii) will be final and binding on the parties subject to the following:
(A) if the determination relates to any matter other than a decision to disapprove a Budget or Programme under clause 5.2(a)(ii), the Expert's decision will, in the absence of manifest error, be final and binding on the Principal and the Contractor and not subject to review;
(B) if the determination relates to a dispute which arose to a decision of the Project Control Group to disapprove a Budget and/or a Programme under clause 5.2(a)(ii) the Expert's determination may be accepted on the election of the Contractor and the Principal but will not be final and binding. In that respect the Contractor and the Principal must notify each other within ten Business Days of receipt of the Expert's determination whether they accept the Expert's determination. If the Contractor or the Principal does not accept the Expert's determination the provisions of clause 15.5 will apply;
(iii) is to be given effect to by the parties unless and until it is reversed, overturned or otherwise changed by any validly applied process or by judgment or order of any Court or under clause 15.4(g)(iv);
(iv) upon submission by a party, the Expert may amend the determination to correct any clerical mistake, any error from an accidental slip or omission, any material miscalculation of figures or a material mistake in the description of any person, thing or manner or any defect in form;
(a) the Principal must offer the Project Assets for sale to the public at a price and on terms agreed by the Project Control Group;
(b) if the Project Control Group cannot agree on any matter or thing in relation to the sale of the Project Assets then that matter or thing must be determined by an Expert under clause 15.4;
(c) without affecting any accrued rights or liabilities of the parties under any Transaction Document, this document is terminated from the date on which completion of the sale of the Project Assets occurs as contemplated by this clause 15.5 (Termination Date); and
(d) in addition to any other monies owing to the Contractor under this document the Principal must pay to the Contractor the Termination Fee on the Termination Date.
In respect of a party, if that party does not pay any money payable under this document within five Business Days of the due date and otherwise in the manner required by this document.
[If a] party fails to carry out its obligations under this document (except any obligation which if not complied with would constitute a Monetary Event of Default) in a proper, timely, professional and workmanlike manner such that in the opinion, acting reasonably, of the party not in default such failure will have a material and adverse effect on the Project.
(a) Subject to clauses 7.2[435] and clause 5.6,[436] the Borrower must repay the Outstanding Loan Amount to the Financier at the times, in the amounts and otherwise in the manner specified in the [Services Agreement].
(b) The Borrower must repay to the Financier each part of an Advance used to pay a GST Amount on the GST Repayment Date for that Advance.
(a) Despite any other provision of this document, the Borrower must repay any unrepaid part of an Advance to the Financier no later than the tenth anniversary of the date on which that Advance was made or taken to be made by the Financier.
(b) For the purposes of clause 5.6(a), a repayment of Outstanding Principal will be applied against the unrepaid Advances according to the chronological order in which they were made.
(emphasis added)
(i) the right of the Financier to recover amounts owing by the Borrower to the Financier under this document is limited to the Financier taking action to enforce:
(A) a judgment against the Borrower against the Project Assets; and/or
(A) enforce a judgment against the Borrower other than:
(1) against the Project Assets; and/or
(2) to enforce the Project Securities;
(C) enforce a judgment or order or take any other action against the Borrower's property other than permitted under this clause 1.5.
(i) prevents the Financier from bringing proceedings against the Borrower to prevent any amount owing by the Borrower to the Financier under this document becoming statute-barred;
(ii) prevents the Financier from applying to make the Borrower insolvent or taking any other action in the insolvency of the Borrower if another creditor has taken action to have the Borrower made insolvent; or
(iii) prevents the Financier from seeking or obtaining equitable relief (including a declaration) in connection with this document or a Security other than an order requiring payment of money by the Borrower to the Financier otherwise than in accordance with this clause 1.5.
(a) If an Event of Default subsists the Financier may at any time by notice to the Borrower do either or both of the following:
(i) cancel the Facility or any part of it specified in the notice;
(ii) make the Outstanding Loan Amount or fees and any other money owing by the Borrower to the Financier in relation to the Transaction Documents either:
(b) On receipt of a notice under clause 7.2(a)(ii)(B), the Borrower must immediately pay in full the amounts referred to in that notice.
The proper construction of the Services Agreement and grounds 1 - 3 The judge's findings
I accept that, at first blush, it would seem odd if Mirvac WA had the right to disapprove a budget it had itself prepared. That is, it would seem odd if Mirvac WA could, having prepared a budget in good faith, be contractually permitted to disapprove that budget in good faith. However, as I will explain, on closer examination, it is not surprising.
Preparing a budget requires an analysis of the costs involved of doing something in a particular way. Then, once the parties know how much it is going to cost, they consider if they are willing to incur those costs. The budget establishes what the costs would be. The decision is then whether to incur those costs. Both parties had a legitimate interest in that decision. For example, incurring large project costs to make lots ready for sale well before it could be reasonably expected that sales would occur would require Mirvac WA to outlay those sums, and would start the clock running on [BN's] obligation to repay them, earlier than necessary. Further, if the market did not improve, the costs, and [BN's] obligation to repay them, could be incurred for no benefit to either party.
Mirvac WA was required to prepare in good faith a budget that set out a proper analysis of the expenditure required to develop a stage of the Project. However, in my view, it would not be odd if Mirvac WA had the right to consider whether the expenditure under the budget was warranted in view of the expected revenue and the likelihood of such revenue being earned in the future, under the relevant market conditions. It would not be odd if Mirvac WA had the right to disapprove a budget if it considered the estimated expenditure should not be undertaken, in view of the likely return having regard to the market conditions.
Further, by cl 8, Mirvac WA was required to fund its obligations under the Services Agreement to carry out the Project. There was no right of recovery from [BN] except as otherwise provided by the Services Agreement. If Mirvac WA did not have the right to disapprove a budget, it would be as if Mirvac WA had agreed to provide an open chequebook for the Project regardless of its viability. The expenses would have been significant, with one estimate putting it at approximately $210 million. Such a construction would be a commercial nonsense.
There is no reason why a reasonable person would have understood cl 5.2(a) to mean something other than its plain meaning, supported by the context of cl 5 as a whole, the Budget Provisions as a whole and the Transaction Documents as a whole.
[BN] submitted that, if Mirvac WA was entitled to disapprove a budget, then the Services Agreement effectively included a provision entitling Mirvac WA to terminate the Project for its own commercial convenience.
I do not accept this. Mirvac WA was required to provide a budget in good faith. It was required to provide a budget that set out a proper analysis of required expenditure to develop a stage of the Project. It was not entitled to put forward a budget that was absurd or wildly and deliberately inaccurate. It was also not entitled to disapprove a budget simply because it was commercially convenient to do so. However, it was entitled, having provided a budget in good faith, to consider whether the budget should be approved. And if, for example, having considered likely or projected revenue and profit, Mirvac WA concluded in good faith that the proposed expenditure was not feasible, it could disapprove the budget, consistent with its right to do so under the Services Agreement.
...
Contrary to [BN's] submissions, the Services Agreement plainly gave Mirvac WA the right to disapprove a budget. In addition to that right, it had the right to reject an expert's determination in relation to a dispute over a budget. These rights demonstrate that the objective intention of the parties was that Mirvac WA would have the right to consider the viability and merits of project expenditure under any budget. Mirvac WA was not required to approve a proposed budget if it considered the expenditure was improvident. Mirvac WA was permitted to consider market conditions, costs and potential revenue in deciding whether or not to approve a budget. (emphasis added) (footnotes omitted)
(a) clause 6.2 of the Services Agreement provides that Mirvac (WA) 'must perform the Services and procure Completion of the Project' in accordance with all Approvals and in a proper, timely, professional and workmanlike manner;
(b) clause 3.1 of the Loan Agreement required Mirvac (WA) to fund the Project to enable Completion;
(c) clause 1.5 of the Loan Agreement and cl 1.5 of the Services Agreement provided, in effect, that Mirvac (WA) was only entitled to recover the amounts advanced from the Project Assets;
(d) the express good faith obligation in cl 3 of the Services Agreement and the implied 'No Hindering Obligation'; and
(e) the express right given to BN to terminate under cl 17.1(a) of the Services Agreement where there is a Non Monetary Event of Default.
(a) in the Services Agreement, Mirvac (WA) is defined as 'Contractor', and whilst also defined as 'Financier' in cl 1.1, the latter term is only used in the Services Agreement in respect of tables allocating sequential preferential entitlements to proceeds of sale, with all other references being relevantly to Mirvac (WA) as Contractor and not as Financier;
(b) in the Loan Agreement, Mirvac (WA) is defined as 'Financier' and there is a definition of 'Contractor' in cl 1.1;
(c) the functions of the Project Control Group detailed in cl 5.2 and the obligations of the representatives of the Contractor in cl 5.3 all show that the involvement of Mirvac (WA) on the Project Control Group is solely as 'Contractor';
(d) a construction which would enable Mirvac (WA) representatives on the Project Control Group to disapprove a Budget or Programme submitted by it as Contractor, so as to bring about a deadlock and undermine Mirvac (WA)'s unconditional obligations as Financier under cl 3 of the Loan Agreement, thereby bringing the Project to an end, would (1) be inconsistent with the objects of the Services Agreement, and (2) not be the correct construction in the absence of clear words;
(e) in light of the above matters, the Services Agreement does not in clear words confer on Mirvac (WA) a discretion to disapprove a Budget or Programme; and
(f) accordingly the judge should have held that, on the proper construction of the Transaction Documents, Mirvac (WA) did not have the right of disapproval of Budgets or Programmes, and Completion was a contractual benefit conferred on BN which was not qualified by any rights given to Mirvac (WA).
The [j]udge should have held that, by reason of the matters referred to in ground 2, on the proper construction of the Transaction Documents it was a term implied by law in the [Loan Agreement] that Mirvac (WA) not hinder or prevent the fulfilment of the purpose of the [Services Agreement] by causing the Initial Advance or any subsequent Advance ... not to be wholly, alternatively substantially, repaid (by payments to Mirvac (WA) in its capacity as Financier under cl 11) 10 years after the Advance was made.
A potential third construction: the parties' submissions
(a) there are no words in cl 5.2(a) which constrain the reasons why members of the Project Control Group may decide to approve or disapprove a proposed Budget or Programme; and
(b) similarly, there are no words in cl 15.5(g)(ii)(B) which constrain the reasons why a party may 'elect' not to accept an Expert determination.
[I]f the third possible construction is adopted by the Court, BN accepts (and has always accepted) that it will not obtain in this appeal judgment in its favour under the counterclaim unless the Court also concludes that the [Services Agreement] was validly terminated by BN for repudiation by [Mirvac (WA)] or under cl 17.1(a) of the [Services Agreement]. That is why all of the grounds of appeal have been pursued.
A duty to co‑operate in, or not to prevent, fulfilment of performance of a contract only has content by virtue of the express terms of the contract and the law can only enforce a duty of co‑operation to the extent that it is necessary to make the contract workable. The court cannot, by implication of such a duty, exact a higher degree of co‑operation than that which could be defined by reference to the necessities of the contract. The duty of co‑operation or prevention/inhibition of performance is required to be determined, not by what might appear reasonable, but by the obligations imposed upon each party by the agreement itself.
In the absence of a fiduciary relationship, there cannot be a duty to cooperate in bringing about something which the contract does not require to happen: Australis Media Holdings Pty Ltd v Telstra Corporation Ltd (1998) 43 NSWLR 104 at 124D. In that case, the Court of Appeal said at 125: 'A contract may "contemplate" many benefits for the respective parties, but each can only call on the other to provide, or cooperate in the providing of, benefits promised by that party'. (original emphasis)
It is easy to imply a duty to co-operate in the doing of acts which are necessary to the performance by the parties or by one of the parties of fundamental obligations under the contract. It is not quite so easy to make the implication when the acts in question are necessary to entitle the other contracting party to a benefit under the contract but are not essential to the performance of that party's obligations and are not fundamental to the contract. Then the question arises whether the contract imposes a duty to co-operate on the first party or whether it leaves him at liberty to decide for himself whether the acts shall be done, even if the consequence of his decision is to disentitle the other party to a benefit. In such a case, the correct interpretation of the contract depends, as it seems to me, not so much on the application of the general rule of construction as on the intention of the parties as manifested by the contract itself.
The purchaser may enter the property ... at any time after the date of this Contract ... to work up ground for crops such work to be at his expense and risk and in locations first approved by the vendor[.] (emphasis added)
Special condition 24 must be construed in the light of the circumstances surrounding the contract, and the purpose the condition was intended to serve. The background to special condition 24 was that, the [vendor] being ill and unable to work the property himself, it was in the mutual contemplation of the parties that whoever bought the property would enter into possession immediately, and farm the land. The time of year at which the sale took place reinforced the importance of that aspect of the bargain. No doubt the [purchasers'] right of access to the land to grow crops was a factor in the agreed price. At the same time, there could be a number of reasons why the contract might not proceed to completion, and it was reasonable to protect the interests of the [vendor] by reserving to him the power to approve, or withhold approval of, the locations at which such activity was to occur. Infrastructure, especially uncompleted infrastructure, would not necessarily increase the value of the land. It was foreseeable that the [vendor] could suffer adverse consequences from development activity undertaken prior to completion by the [purchasers]. At the same time, the [vendor] had told the [purchasers] that there was 'plenty of land' available for development for rice growing and, provided the [vendor's] interests were adequately protected, it is unlikely to have been the intention of the parties that he could obstruct development unreasonably. The [vendor] was to approve the locations of any development, having regard to what the proposed development involved. The provision should be understood as meaning that the [vendor], in granting or withholding approval, was required to act reasonably, having regard to the legitimate interests of the [vendor] which the requirement of approval was there to protect. (emphasis added)
Analysis: the proper construction of the Services Agreement and grounds 1 and 2
(a) how to implement the Project (as defined), including the manner and timing of its implementation via Stages; and
(b) the Services which are necessary or desirable to carry out the Project in accordance with its determination as to how to implement the Project.
[M]ay be accepted on the election of the Contractor and the Principal but will not be final and binding. In that respect the Contractor and the Principal must notify each other within 10 Business Days of receipt of the Expert's determination whether they accept the Expert's determination. If the Contractor or the Principal does not accept the Expert's determination ... clause 15.5 will apply.
(a) each party to ensure that its respective appointed members would act honestly and give genuine consideration to the proposed Budget or Programme at Project Control Group meetings for the purposes of cl 5 of the Services Agreement; and
(b) each party (through its members on the Project Control Group) to exercise its right to approve or disapprove a proposed Programme or Budget, having regard to the (objective) contractual purpose served by the right of approval/disapproval.
The parties' submissions: grounds 6 - 13 BN's submissions
Ground 6 - imposition of second access road condition
9.1 Grounds 6.1 and 6.2: As detailed in items 1 and 2 of [BN's] Schedule [the email of 24 August 2009] clearly states Mirvac's then position, which was that, if construction of a second access road was imposed as a condition of approval of [proposed Scheme Amendment 63], which was required to be complied with before the Project proceeded further (including a condition imposed by the EPA under the [EP Act] in assessing [proposed Scheme Amendment 63]) (together Planning Approval), the delays that would flow as a result of that condition - ie delays through the condition not being complied with - would be significant enough 'for Mirvac to walk away from [the] [P]roject'. That clear contemporary written statement in [the email of 24 August 2009] is not, based on the language, merely [Mr Adam Davidson] 'putting the wind up the consultants', (and his evidence to that effect was glaringly improbable), and the literal meaning is also consistent with Mirvac's subsequent actions and position.
9.2 Grounds 6.3 and 6.4: [Mr Adam Davidson] admitted he was well aware, when the purported agreement was reached with [Mr Jake Davidson] of the [Shire], that unless and until a resolution was passed by the Council of the Shire (Council) approving a [Local Structure Plan] incorporating the draft provision the subject of the purported agreement, it was not binding on the Shire. The compelling inference from the relevant documents is that, before a draft [Local Structure Plan] was lodged with the Shire for approval, there was nothing more than an incomplete negotiation between Mirvac and [Mr Jake Davidson] with respect to a draft provision which may be included in a [Local Structure Plan] relating to the second access road. [Mr Adam Davidson] did not conclude, with good reason or otherwise, that an agreed outcome with the Shire had been reached. [Mr Adam Davidson] knew that the purported agreed outcome set out in [the email chain between Mr Adam Davidson and Mr Jake Davidson on 9 September 2009] related only to a draft provision. The compelling inferences are, therefore, that [Mr Adam Davidson] knew that Mirvac's strategy was to sell the land englobo after rezoning due to increasing viability concerns, and that [Mr Adam Davidson] was implementing that strategy. In those circumstances, and because (see para 9.4) [Mr Aleksovski] subsequently attempted to do what was put to [Mr Adam Davidson] in a question (quoted at [562] of the [primary decision]), there is a compelling inference that the record of an agreed outcome set out in the handover note was created for the purpose the subject of that question.
9.3 Ground 6.5: Both [Mr Adam Davidson] and [Mr Aleksovski] were experienced land developers holding senior project management positions and knew that, before a [Local Structure Plan] bound the Shire, it had to be adopted by the Council. The compelling inference is therefore that both knew no agreement concerning the draft provision was reached between [Mr Adam Davidson] and [Mr Jake Davidson] that bound the Shire.
9.4 Ground 6.6: At the time [Mr Aleksovski] made the statement to Mr Hall of the Shire that a negotiated position was reached between Mirvac and the Shire as requested by Council, for the above reasons, [Mr Aleksovski] knew that statement was false. Accordingly, his written statement to Mr Hall that an agreement had been made with [Mr Jake Davidson] and other council departments in the form of the draft provision was false.
9.5 Ground 6.7: The compelling inference is that Mirvac acted as detailed in para 9.1 because the viability of the Project had declined since the [Services Agreement] commenced in January 2008, which resulted in Mirvac's strategy then being that, to maximise Mirvac's return, the Land would be sold englobo (with the benefit of the Planning Approval). It was an element of that strategy that, despite clause 6.2, Mirvac would not carry out the Project to Completion.
(emphasis added) (footnotes omitted)
10.1 Ground 7.1: The compelling inference from contemporaneous documents is that the December 2012 Strategy ... was the final version of the document sent to the Shire because reference to a 17 December 2012 Strategy [was] made in the May 2013 Strategy.
10.2 Ground 7.2: The December 2012 Strategy proposed that the Council be responsible for upgrading the temporary fire access road to a public road. That position remained the same in the May 2013 Strategy. Mr Hall responded referring to discussions to the effect that [BN], through Mirvac, would be the responsible party for that work. The response from Mr Pearce to this query was obviously inaccurate. The compelling inference from [Pastoral Co] having no capital gains tax issue was that the explanation to the Shire as to why [BN] (through Mirvac (WA)) was asserting the Shire would be responsible for gazetting and constructing the road was false as (because of cl 3.1 of the [Loan Agreement]) there were no new financial implications that made the acquiring of the relevant land through a private sale no longer feasible, apart from Mirvac's modified strategy at that time (Strategy). At that time, the Strategy had developed from that referred to in para 9.1 above and, as detailed below, had become that:
10.2.1 there be an agreed variation of the [Services Agreement] in Mirvac's favour for [BN] to repay the Initial Advance to secure termination of the [Services Agreement] on terms that [BN] would retain the land unencumbered after termination;
10.2.2 commencing substantial works to carry out the Project would be delayed pending such an agreement being made; and
10.2.3 the threat of an englobo sale after the deadlock provision in cl 15 of the [Services Agreement] was engaged or [BN] defaulted under clause 5.6 of the [Loan Agreement] if the Project were delayed until the Anniversary Date (11 January 2018) be used as a lever to achieve a satisfactory agreed variation of the [Services Agreement] with [BN] resulting in repayment to Mirvac (WA) of the Initial Advance.
10.3 Ground 7.3: As detailed in item 11 of [BN's] Schedule, [Mr Cuthbert] of the Department of Planning ... was included in the email chains relating to the May 2013 Strategy. [Mr Cuthbert] knew there were no financial implications that made a private sale infeasible. Accordingly, the compelling inference is that the WAPC also knew (or would be informed by [Mr Cuthbert]). Further, it is a proper condition of subdivision approval that the subdivider pay the costs of a public road required by the subdivision.[488]
10.4 Ground 7.4: Accordingly, as detailed in item 12 of [BN's] Schedule, the compelling inference is that Mirvac (WA), through [Mr Aleksovski] and others, was attempting to cause [Pastoral Co] to not sell the land required for the second access road, particularly in light of the internal Mirvac documents and matters set out below (which occurred concurrently with the second access road developments).
14.1 Ground 10.1: ... The judge found that a reference [in Mr Crockett's email of 24 May 2012] to the protection of 'our' position ... was, despite it being between Mirvac officers, a reference to the position of both Mirvac and [BN]. The compelling inference from the whole document is that, whilst the [Project Control Group] did endorse a decision to progress the [Local Structure Plan] to approval, each party's representatives on the [Project Control Group] had different reasons for agreeing: [BN] wanted the Project carried out to Completion, but Mirvac was protecting its position by having the [Project Control Group] agree to progress the [Local Structure Plan] to approval because the land could be sold for more by an englobo sale with Planning Approval than without it.
14.2 Ground 10.2: The statement of [Mr Draffen] the subject of ground 10.2 is s [sic] in item 16 of [BN's Schedule]. If [BN's] construction of the Transaction Documents is accepted, [Mr Draffen's] evidence was a material admission by Mirvac. The evidence referred to below leads to a compelling inference that, whilst this admission concerned Mirvac's position in June 2012, that position did not materially change before the [Services Agreement] was terminated in 2014.
14.3 Ground 10.3: As at July 2012, Mirvac's position was that, because Completion in accordance with the [Services Agreement] would not give a viable economic outcome for Mirvac, it was not in Mirvac's interest to proceed with the Project. The compelling inference is that Mirvac's stated assumption to move towards an englobo sale at the time was not only adopted for the purposes [of adopting a value for the carrying value of inventory], but also because Mirvac at the time knew that the Strategy was required because Mirvac could not lawfully terminate the [Services Agreement] merely for its financial convenience.
14.4 Ground 10.4: As detailed in item 18 of [BN's] Schedule, the compelling inferences are that Mirvac acted on the basis that it was bound to carry out the Project to Completion and, based on the evidence that Mirvac would not have considered how to engage the deadlock provision in the [Services Agreement] unless it knew that was the only way, in the absence of agreement by [BN], to lawfully exit the [Services Agreement] before the Anniversary Date without carrying out the Project. As detailed below, investigations were carried out by Mirvac into how the deadlock provision could be engaged.
14.5 Ground 10.5: [Mirvac's emails dated 22 and 23 January 2013] state that legal advice was being sought as to how best to enact the deadlock provisions to ensure Mirvac's actions were supported by the [Services Agreement]. However, the compelling inference from all the evidence discussed in this para 14, is that a decision to exit via deadlock had been made, and Mirvac was only obtaining further legal advice on how to lawfully implement the decision.
14.6 Ground 10.6: As detailed in item 20 of [BN's] Schedule, in February 2013 Mirvac was considering the best way to exit the [Services Agreement]. Mirvac's considered that [BN] was likely to release Mirvac from its obligations under the [Services Agreement] and repay the Initial Advance ($25m) in exchange for retaining the land unencumbered. Accordingly, a provision of $18m against the then value of the [Outstanding Loan Amount] ($43m approx.) was made in February 2013, rather than a provision of $28m recommended by Mirvac's auditors based on the then market value of the land being $15m if sold englobo. The compelling inferences from the basis on which the $18m provision was made and the other evidence in Item 20 [of BN's Schedule] are that Mirvac had, at February 2013, adopted the Strategy, and was considering only how (and not whether) to implement the Strategy.
14.7 Ground 10.7: The compelling inference from the documents detailed in item 21 of [BN's] Schedule is that Mirvac knew that renegotiation of the [Services Agreement] on terms acceptable to Mirvac would not occur as [BN] was unwilling to materially amend the [Services Agreement] in Mirvac's favour. That Mirvac began valuing the land based on an englobo sale leads to a compelling inference that Mirvac had decided it would not carry out the [Services Agreement] to Completion of the Project because it knew the [Services Agreement] could not be renegotiated to Mirvac's satisfaction.
14.8 Ground 10.8: The evidence detailed in item 22 of [BN's] Schedule, relating to the PWC Report (a Book), clearly details that Mirvac's decision up to the date of the PWC Report was that Mirvac would exit the [Services Agreement] via deadlock, but further legal advice was being sought as to how the use of the deadlock provisions could best be achieved. It was because that legal advice had not been obtained that the PWC Report recommended a provision of $28m rather than $18m.
14.9 Ground 10.9: The evidence detailed in item 23 of [BN's] Schedule is also consistent with the evidence and the compelling inferences detailed above. The provision of $18m was made on the basis that, although [BN] was no longer willing to renegotiate the [Services Agreement] favourably to Mirvac, Mirvac management assumed that [BN] would agree to repay the Initial Advance in full to prevent the land being sold englobo following a deadlock. The compelling inference from that evidence was that Mirvac had made, or had manifested an intention to make, the [alleged Refusal to Proceed decision].
14.10 Ground 10.10: By September 2013, Mirvac had received legal advice as to how best to use the deadlock provision in the [Services Agreement]. Mirvac knew by that time that it could not bring about a deadlock by having Mirvac Ltd refuse to give an ACC to commence work on the Project, and that a rejection of a Budget or Programme at a [Project Control Group] meeting leading to deadlock was required. The evidence in item 24 of [BN's Schedule] shows that three options were considered by Mirvac in September 2013 as to how to proceed. All three options, if [BN's] construction of the Transaction Documents is accepted, were repudiatory, or would constitute a [Non Monetary Event of Default] under the [Services Agreement] if implemented. The financial model of how much Mirvac would lose if the option of carrying out the Project to Completion in accordance with the [Services Agreement] was adopted shows why that option had been, and continued to be, rejected by Mirvac.
(emphasis added) (footnotes omitted)
Ground 8 - second access road and viability concerns
15.1 delay the commencement of works on the Project because no ACC had been, or would be, issued by Mirvac Ltd to commence substantial Project work; and
15.2 put pressure on [BN] (due to the risk of the [Outstanding Loan Amount] not being repaid under cl 11 before the Anniversary Date) to either renegotiate the [Services Agreement] in Mirvac's favour or repay the Initial Advance as contemplated by the Strategy. (footnotes omitted)
(a) the Programme would take 18 months and would achieve delays, intended by Mirvac, up to the point where the Initial Advance was due for repayment; and
(b) because Mirvac contemplated a loss of $80 million even if the golf course were incorporated, Mirvac had no intention of carrying out the Project to Completion after the 18‑month planning period.
3. As including the golf course land was inconsistent with the definition of Project, in submitting the Budget and Programme, Mirvac did not have the intention of carrying out the Project to completion properly, timeously and in good faith.
It was intended to cause material delay in commencing work on the first stage of the Project so as to result in [Mirvac (WA)] not incurring expenditure in carrying out the Project prior to Mirvac (WA) becoming entitled on 11 January 2018 to repayment of any unrepaid part of the Advances.
Ground 12 - recording of Project Control Group meetings
Further, the proposition was inherently improbable. It would have first required [Mr] Adam Davidson, a planning manager, to determine that there could be some value in creating a document in 2010 falsely asserting an agreement. This would require quite some foresight. It would have also required him to be dishonest and willing to be dishonest despite the fact that he was leaving Mirvac WA for a job elsewhere. Further, if he wanted to create a document alleging an agreement that went beyond documents common to the Shire and Mirvac WA, one might expect he would refer to fictitious oral conversations. He did not. He reproduced in the handover notes the 2009 Trigger Provisions.
[Counsel for BN]: But in your dealings whilst you were there with the Shire of Harvey, the [S]hire was generally supportive of the Binningup [P]roject proceeding in your understanding, wasn't it? - Conditionally supportive, yes.
[Counsel for BN]: And in your experience do large property developers such as Mirvac sometimes acquire land with a view to carrying out a subdivision development, but then after doing a detailed feasibility analysis sell the land without actually proceeding to carry out the development? - Yes, I've seen it happen.
[Counsel for BN]: Has it been done by Mirvac to your knowledge? - I can't recall any projects that I was involved in where that occurred.
[Counsel for BN]: I see. And where that type of situation applies, is it your experience that it's common for a large property developer to take all possible steps to maximise the sale price before marketing the land? - Yes.
[Counsel for BN]: And in your experience, can those steps to maximise the sale price include obtaining planning approval for a proposed development and then selling the land with the benefit of a current development approval? - Yes.
In closing submissions, [BN] submitted that Mr Aleksovski's statement in his 5 September 2011 email that 'a negotiated position was agreed with your predecessor Jake and other council departments concerned' was false. I do not accept this. The documentary evidence shows that the Shire officers and Mirvac WA's development manager had reached an agreement about trigger points as to the time at which the route would need to be identified (on the issue of titles to facilitate the development of 750 dwellings) and the time at which the road would be constructed (on the issue of titles for 1,000). (footnote omitted)
In any event, for the same reasons as rejecting [BN's] primary contention on [Mr] Adam Davidson's conduct, I do not accept that his conduct supports any intention other than a desire to save unnecessary or premature costs. [Mr] Adam Davidson was seeking to avoid having to construct a second access road earlier than required (if indeed it was required at all), for the benefit of both Mirvac WA and [BN]. As Mr Waller spontaneously noted, that was 'just prudent'. (footnote omitted)
In evaluating the evidence in relation to the second access road, I have taken into account the other evidence that shows what else was happening at particular times. Much of this evidence is summarised later.
In particular, Mr Aleksovski first asked Mr Payton about possible tax issues on 21 March 2013. This was less than two months after a Mirvac Board paper and a report from PricewaterhouseCoopers that indicated, among other things, that Mirvac was contemplating using the deadlock provisions to persuade [BN] to agree to vary the Services Agreement, but was first going to obtain legal advice to ensure that whatever it did was contractually permissible. It was just over a month after an email exchange which was to similar effect. However, as I will later explain, these, and other similar documents, do not show that Mirvac WA intended to act contrary to its contractual obligations or to delay or stop work on the Project pending the anticipated negotiated outcome.
I do not accept Mr Aleksovski's explanation as to why he raised tax issues with Mr Payton. His explanation was implausible. However, I also do not accept that Mr Aleksovski raised tax issues to try to convince Mr Payton that [Pastoral Co] should refuse to sell the land for the second access road. Rather, I infer (despite Mr Aleksovski's evidence) that he raised tax issues with Mr Payton as part of his attempt to manoeuvre the Shire into compulsorily acquiring the land. Had the Shire acquired the land, this would have been of significant benefit to the Project, and [Pastoral Co] could not have held Mirvac WA and [BN] to ransom.
I do not accept that Mr Aleksovski was seeking to delay progress. Mr Aleksovski denied he was seeking to delay. His denial was supported by the documentary evidence:
(1) In June 2012, Mr Pearce, on behalf of Mirvac, was pressing the Shire.
(2) The June 2012 Strategy was provided promptly and addressed Mr Hall's requests.
(3) After the meeting on 13 August 2012, Mr Aleksovski promptly sought to meet with Mr Waller, and a further meeting was held with the Shire at which Mr Waller was present. In that meeting, the trigger point for the construction of the road, left open by the 13 August meeting, was agreed.
(4) In May 2013, Mr Aleksovski wanted to press the Shire to respond. The email sent to the Shire on 10 May 2013 foreshadowed that Mirvac WA would rely on a deemed refusal if a decision was not forthcoming. However, it also advised that further discussion may resolve the issue. Its aim was clearly to prompt a response from the Shire and to encourage the Shire to be willing to negotiate.
(5) In numerous documents, including the Deemed Refusal Notice itself, Mirvac Ltd reiterated its commitment to make a contribution per lot for the construction of the road.
(6) Mr Pearce responded to Mr Hall's email of 27 May 2013, on 30 May 2013. In that email, Mr Pearce was pressing for 'the June spot' at the Planning Committee.
These documents are inconsistent with a desire to delay. They support a desire to persuade the Shire to agree with Mirvac WA's proposal and to persuade it to compulsorily acquire the land.
Further, the fact of utilising the deemed refusal process is itself inconsistent with a desire to delay. By using this process, Mr Aleksovski sought to have the WAPC resolve the impasse between the Shire and Mirvac WA, rather than the impasse continuing (unless Mirvac WA capitulated). Mr Aleksovski also chose the WAPC rather than the State Administrative Tribunal as he thought it would be faster.
I do accept that the May 2013 Strategy inaccurately stated that investigation by [Pastoral Co] had revealed significant tax implications. This was not an innocent mistake. The inaccuracy is too detailed, and is, in effect, repeated in Mr Pearce's email to Mr Hall on 30 May 2013. The inaccuracy troubled me. However, in all of the circumstances, I am not satisfied that the misstatement was made as part of a larger plan to delay or impede implementation of the Project. Nor am I satisfied that it was made because the [alleged Refusal to Proceed decision] had been made. While I accept that Mr Aleksovski was trying to avoid incurring costs, I do not accept that this was because the [alleged Refusal to Proceed decision] had been made. It is much more likely to have been written as part of Mirvac WA's ongoing efforts to try to reduce unnecessary expenditure, by seeking to secure the Shire's agreement to acquire the land itself.
Mr Aleksovski believed that the Project should not have been 'held to ransom by the Shire of Harvey to acquire land from a private third party individual for a public road'. Mr Aleksovski was also clearly unhappy that the Shire had changed its position, after agreeing what the triggers would be for the road construction. Neither matter would justify misstating the position to the Shire. However, I do not accept that he did it to delay the Project or because the [alleged Refusal to Proceed decision] had been made. In my view, it is more likely that Mr Aleksovski was simply trying to persuade the Shire to acquire the land itself, in an effort to save costs. (emphasis added) (footnotes omitted)
From the overall context, it appears that [Mr Crockett] believed that Mirvac would consider a budget for subdivision works to be infeasible, given the then market conditions and forecast, and that therefore Mirvac would not approve such a budget, which could lead to a deadlock. As later explained, Mirvac had the right under the Services Agreement to disapprove a budget it considered to be infeasible. (emphasis added)
In cross‑examination, Mr Aleksovski was asked if he was aware that the position was to progress the [Local Structure Plan] approval 'to protect Mirvac's position'. He said he was not aware of that. He said his role was to perform the role of contractor and to get the [Local Structure Plan] approved and that is what he did. (footnote omitted)
[T]he position is that you knew in June 2012 that Mirvac had made a decision - and you in particular on its behalf had made a decision - that Mirvac would not be proceeding to carry out the subdivision project at Binningup. (emphasis added)
That's incorrect. We - the position - we had never taken a position not to proceed with the project. Sure that it was - absolutely the project was - was financially challenging and we were attempting to find a pathway to at least come up with a viable [S]tage 1 to at least allow the project to proceed in some shape or form. Now, to proceed further, you know, our view at the time was that some form of renegotiation would be required for that to happen. But, no, we hadn't made we had absolutely not made a decision not to proceed. (emphasis added)
[M]r Draffen's evidence must be considered as a whole. As noted earlier, Mr Draffen spoke of renegotiation as being probable and ideal. He said that the options under consideration in September 2013 were not limited to requiring a renegotiation of the Services Agreement. After that time, he had had discussions with Mr Waller about the options and those options may or may not have involved a variation to the Services Agreement. He said that, when he met with Mr Waller on 3 April 2014, more work was required before a view as to that could be reached. (emphasis added) (footnote omitted)
[M]ore directly concern[ed] the internal position of Mirvac being inconsistent with carrying out the project to completion properly and timeously as required by cl 6.2 [of the Services Agreement][533] and - or conduct of Mirvac (WA) which didn't comply with the obligations of Mirvac (WA) under the [Services Agreement] led to there being repudiation in the second sense referred to in Koompahtoo or a breach of a [N]on [M]onetary [E]vent of [D]efault which we have also relied on'.
So HY13 refers to the first half of the 2013 financial year from 1 July 2012 to the end of that calendar year, doesn't it?---Yes.
In other words, the six months ending 31 December 2012?---Correct.
Okay. And could you please look at the summary on page - yes, page 11523?---Yes.
It's under the project categorisation; everything is redacted except Binningup. It's referred to there under the product line MPC, so it's master‑planned communities product line. State: WA. And it's recorded as, 'Action: englobo/super lot' with a tick. So your understanding of sale of a super lot or englobo, as referred to there, is to sell the land un‑subdivided, isn't it?---In general terms, yes.
Thank you. And what's there recorded - that is, 'Action: englobo/super lot sale' - was consistent with what was in the managing director's report that we just reviewed, wasn't it?---It was consistent with the assumption adopted for provision purposes, which was the negotiated exit which we just discussed.
Yes. And that was a strategy to move towards an englobo sale - - -?---It was the assumption for the purposes of carrying - of adopting a value for the carrying value of inventory, which was the subject of this report.
This requires [BN] agreeing to release Mirvac from its obligations under the [Services Agreement] and refund the initial $25m Land costs.
Currently, this is considered the most likely scenario as [BN] is unlikely to proceed through the deadlock provision ... [BN] would receive all the planning and other associated intellectual property for free and would be simply returning the initial land advance.
...
We will need to receive further detailed legal advice in relation to how best to enact the deadlock provisions to ensure our actions are fully supported by the [Services Agreement].
The deadlock provision sets out a procedure for dispute resolution which eventuates in the land being sold for an agreed sum if the disagreement cannot be resolved. ... Based on discussions with [BN] and based on our knowledge of [its] intentions, it is not envisaged that [BN] would allow the deadlock to escalate to this level. (emphasis added)
In December 2012, Mirvac and [BN] discussed the current status of the project and its long‑term future project returns based on the current structure of the [Services Agreement].
The outcome of this discussion was that under the current structure of the [Services Agreement], Mirvac's long‑term future returns generated by the project were of concern and that a renegotiation of the [Services Agreement] and/or the ongoing arrangement between both parties would need to be considered. [BN] indicated a willingness to provide assistance with regards to the renegotiations of the [Services Agreement] in order to advance the project to the delivery phase during those discussions.
A subsequent site tour was held in June 2013 which was attended by John Carfi, Toby Long, Kim Lawrance, [BN] and [Mr Aleksovski].
At that site meeting it was agreed that development was to commence along the foreshore where a mix of both residential, retail and commercial product would be delivered as part of Stage 1 and that the relevant feasibility analysis would be undertaken to reflect the changes/impact to the project.
[BN] reiterated its willingness to achieve a suitable outcome for both parties at the [Project Control Group] meeting held in July 2013. It also tabled the future of the existing Binningup Golf Course was at risk from their prospective due to its ongoing financial strain on the project (it currently has a net loss of $300k - 360k per annum) and that incorporating the golf course into the development was an option and put forward as their preferred option. (emphasis added)
Now, when you received this memorandum, is that how you understood the position to be as recorded there?---Certainly the understanding was that there was no ability to exit the [Services Agreement] for - just because we wanted to exit; we would have to follow the provisions of the [Services Agreement]. (emphasis added)
Based on the discussions held to date, the advice obtained from Mirvac Legal, Colliers International Market Research & Feasibility Analysis and the recently released Mirvac New Business Strategy, the following scenarios/options are determined as being most suitable for consideration by senior management in assessing the future of the project:
In conclusion, based on the feasibility analysis undertaken, the market research undertaken by Colliers and the future release of urban land within the South West market in the next 5 to 10 years ... it is advised that consideration be given to holding discussions with [BN] outside of the current [Services Agreement] framework in order to negotiate a suitable position for both Mirvac and [BN] and facilitate an outcome suitable to both parties.
So the recommendation in that paragraph - was that something that you adopted?---I think it was a - we ... continued to discuss and review options and have further conversations with Mr Waller about potential options. All ... that was recommending is that we ... continue to do so and that - and that those discussions - because they were - they were outside of the current approved [Services Agreement].
And you subsequently participated in the process of having a - of negotiating with Mr Waller outside the current [Services Agreement] as there [sic] recommended didn't you?---I was involved in discussions with Mr Waller, yes, post then.
A 'Project Risk Assessment' was attached to the agenda for a meeting of the 'MPC WA Monthly Project Review' on 25 October 2012. It included a risk said to arise from the fact that the current feasibility assumptions were based on the perceived outcome of the 'renegotiations currently underway' with [BN]. The 'Plan Description' associated with this risk said:
'Project partner is aware of the issue and has expressed a willingness to work with Mirvac to achieve a suitable outcome for both parties however has indicated that certain terms and parameters of the original agreement are not negotiable. The impact amount is based on the current WIP of the project is [sic: if] an agreement cannot be reached.'
A Mirvac spreadsheet titled 'Summary of Forecasts Q2FY13', and dated 17 December 2012 stated in the 'Risks' worksheet that the cash flow profile is 'affected by environmental and planning approvals which has caused delays in commencement on site. Demand for the anticipated product will need to be carefully assessed'. In the 'Other Threats and Opportunities' worksheet it stated:
'Further to the environmental approval process, the project yield has been reduced. However, there has been an unwillingness from [BN] to review the [Services Agreement]. Therefore, putting the viability of the project at threat. This may trigger an impairment to the loan balance currently carried.
The recoverability of the [Services Agreement] loan does not appear to be supported by the value of the land. ... The loan is secured against the development site but based on current assumed englobo valuation the security value is not sufficient to pay out the loan.'
These documents show nothing more than that Mirvac recognised that, if the Services Agreement was not varied, it may need to make a provision to reflect the risk the loan would not be fully repaid. (footnotes omitted)
[A]ll works which are desirable or necessary as a preliminary step to Subdivision Works or Construction Works including preparing designs, obtaining Approvals and conducting market investigations.
And you prepared the September 2014 [R]eport for the [Project Control Group] meeting which was scheduled for 25 September 2014, didn't you?‑‑‑Yes, I did.
Can I take you to that document; tab 749. And could I ask you, please, to look at the first three dot points in section 2 of the report on page 11162 under the heading Design. The first dot point says:
'[BN] requested Mirvac to review options for developing the golf course land to understand the impact.'
'The likely increase in yield is some 200-plus lots.'
'The conversion of the golf course land into residential lots is significantly different from the current approved [Local Structure Plan] and is therefore deemed to be a major amendment to the [Local Structure Plan]. Therefore, a full amendment to the approved [Local Structure Plan] will be required, including a complete reconsideration of the amended [Local Structure Plan] inclusive of public advertising, Shire of Harvey approval and WAPC approval. This is anticipated to take some 12 to 15 months of additional planning works. Commencement of the [Local Structure Plan] amendment will commence in October 2014. Initial discussions will be held with both WAPC and the Shire of Harvey to gauge their thought on the amendment and to determine the most effective and time-conscious way forward to alleviate any potential time delays and constraints. Pursuant to clause 6.5B(2)(a) -'
'a programme in advance of the commencement of the preliminary works for a stage outlining the [Local Structure Plan] amendment process is annexed to this report for the [Project Control Group] as attachment 5.'
'The removal and subsequent development of the golf course into residential land will be a contentious issue. Existing residents of Lakewood Shores will be seeking clarification and an explanation from [BN], along with the Shire of Harvey. Immediate consultation must therefore be undertaken with the Shire of Harvey to address any potential concerns and adverse impacts of the decision.'
See all of that?‑‑‑Yes.
So the first dot point was not correct, was it, because it was you who suggested considering closing the golf course, wasn't it?‑‑‑No. I don't agree with that.
All right. In the second dot point you said there would be 12 to 15 months of additional planning work to amend the [Local Structure Plan] and that work would commence in October 2014, didn't you?‑‑‑Yes, I did, and that was based on - on advice that I had from our planning consultant.
All right. And you knew when you prepared this document that amendment of the [Local Structure Plan] in that way could only proceed if the definition of 'project' in the [Services Agreement] was first amended by mutual agreement of Mirvac and [BN], didn't you?‑‑‑No. I wasn't aware of that.
Well, you were aware of it when you prepared the minutes of the previous [Project Control Group] meeting, that project - the golf course is an element of the [Services Agreement] - weren't you?‑‑‑Yes, and - and it would have required an amendment to the - to the structure plan that was just approved.
But it also would have required mutual agreement to an amendment of the [Services Agreement] to change the definition of 'project', wouldn't it?‑‑‑I - I - I don't understand what - what you're ‑ ‑ ‑
Well, you knew that, didn't you?‑‑‑I wasn't aware that it required an amendment to the [Services Agreement].
Well, why are you recorded, in the minutes you prepared in July, saying that the golf course is a part of the [Services Agreement], then, Mr Aleksovski? You knew about it?‑‑‑Sorry, I'm - I'm - I don't understand. Knew about what, exactly?
Well, you knew that it wasn't a function of the [Project Control Group] to start approving things which were not even part of the project as defined, didn't you?‑‑‑No. I - I wasn't aware of that.
Weren't you?‑‑‑No.
Did you discuss this document that you prepared and sent out with anyone else within Mirvac before it was sent?‑‑‑There would have been discussions with - with - with my - my immediate manager. So, yes, it would have been with - with [Mr] Lawrance.
Mirvac were appointing senior personnel from Sydney as the [Project Control Group] representatives at this time, weren't they?‑‑‑Yes. I - I believe it was ‑ ‑ ‑
Cooper and Long?‑‑‑Yes, [Mr] Cooper was a [Project Control Group] member, and [Mr] Long, yes.
Yes. Well, you discuss this document with them as the representatives that were going to attend this meeting?‑‑‑I - I - I may have.
And did you discuss with them the fact that what you were proposing was to do something which couldn't be forced on anyone at a [Project Control Group] meeting unless there was mutual agreement to change the definition of 'project'?‑‑‑No. I wasn't aware of that.
Nor did [Mr] Cooper tell you that?‑‑‑No one told me that. No.
Nor [Mr] Long?‑‑‑No one told me that.
No one?‑‑‑No.
Nor Ms Pini?‑‑‑No one told me that. No.
No one? All right. Thank you. And the reason you suggested this work would commence in October 2014, even though there was no mutual agreement made to change the [Services Agreement], was because you thought that this major [Local Structure Plan] amendment was a good method to further delay commencement of infrastructure works for a long period, didn't you?‑‑‑No. I don't agree with that at all.
All right. You knew, in September 2014, that Mirvac wished to ensure that the 10-year period specified in clause 5.6 of the [Loan Agreement] would expire in respect of the $25 million advance before Mirvac carried out any infrastructure works on the project, didn't it?‑‑‑No.
You understood that, in - you - start again. You understood, in 2014, that Mirvac could, after those 10 years, sell the project land as mortgagee unless [BN] repaid the $25 million advanced or agreed to vary the [Services Agreement] in some way favourable to Mirvac, didn't you?‑‑‑No. I don't agree with that.
And in truth, you were well aware of those matters a year earlier when you wrote the memorandum to Mr Draffen, dated 5 September 2013, at tab 583 [the September 2013 Options Memo] that we've looked at earlier, didn't you? You were aware of it then?‑‑‑Sorry. Are you asking - I was aware of ‑ ‑ ‑
You were aware of those matters that, after 10 years, there could be pressure put on [BN] to either repay the 25 million additional advance pursuant to the [Loan Agreement] or agree to vary the [Services Agreement] to give Mirvac a far better outcome; you were aware of that a year before this time, weren't you?‑‑‑No. I don't agree with that.
Well, we've looked carefully at your report at tab 583 today [the September 2013 Options Memo]; I won't take you back to it now but it records that - your awareness of a proposal that the $25 million would be converted to equity in December 2017, doesn't it?‑‑‑That was a scenario that was - that I was asked to model. Yes.
That's right. And that was because December 2017 was the month before the 10 years expired, wasn't it?‑‑‑That's what I was instructed to model and that's what I modelled.
And you understood why you were instructed the model it, didn't you?‑‑‑No. As I - as stated, that's what I was instructed to model and that's what I modelled.
Right. And do you recall, in option 2 in your model, that it included incorporating the golf course into the development, didn't it?‑‑‑Yes, it did, from memory. Yes.
All right. Yes. Okay. And the sales rates in option 1 and option 2 in that document, which we went through earlier, had sales commencing at different times, didn't they?‑‑‑I can't confirm that without looking at the document. I'm happy ‑ ‑ ‑
All right. Well ‑ ‑ ‑?‑‑‑I'm - yes.
You can look at it if you wish but I can tell you that option 1 has sales commencing in April 2015 but option 2 has sales commencing in June 2017 but if you want to check it, I will take you to the pages?‑‑‑Yes. If you don't mind, if I could check that, please.
Yes. That's fine?‑‑‑That would be appreciated.
That's volume 16, tab 583. And for option 1, it's at page 8438. You see, under Sales Rate, the sales in option 1, the first four per month from April 2015?‑‑‑Yes.
See that there?‑‑‑Yes.
And if you turn over to page 8439, option 2, sales rate: six per month from June 2017?‑‑‑Yes. Correct.
Right. And ‑ ‑ ‑?‑‑‑Your Honour, just to clarify, the sales rates, that six per month actually means settlements. So that's when first settlements would actually start occurring. I just wanted to clarify that because there's sales and there's settlements but what that means is that we would be settling from that particular date.
And if you look at - seeing you've got the document there, if you turn back to page 8437, and the last item on page 8437 where option 2 is described:
Undertake a feasibility analysis based on the development commencing on foreshore and incorporating the existing Binningup golf course into the development.
See that?‑‑‑On page 8437, was it?
Yes. Where there's option 2 in ‑ ‑ ‑?‑‑‑Yes.
‑ ‑ ‑ the last dot point, the first two lines?‑‑‑Yes, that's correct.
That was - I asked you a few moments ago that option 2 proposed incorporating the existing Binningup golf course into the development, and that's where you said that, didn't you?‑‑‑Yes.
Basis of that, I'm suggesting to you, that it was your proposal to Mr Waller that that be done?‑‑‑No, I don't agree with that.
No. So isn't it the case that this project [Project Control Group] report for the September 2014 meeting scheduled for 25 September 2014 was simply a continuation of Mirvac's attempts to delay any infrastructure works commencing on this project before the 10 years from the date of the initial [Services Agreement] - that is, before 10 years from 11 January 2008 - had expired?‑‑‑No, I don't agree with that.
No. All right. Thank you, your Honour. (emphasis added)
In [BN's] written submissions, it summarised the matters which it said manifested the [alleged Refusal to Proceed decision].
... Mr Lawrance was the Development Director of Mirvac Ltd at the time. In its closing submissions, [BN] modified (or clarified) what it had pleaded:
...
(2) [BN] asserted that the effect of Mr Lawrance's statements was that, in addition to [Project Control Group] approval, Mirvac would need internal Mirvac approval prior to commencing Stage 1.
...
[BN] asserted that statements made by ... Mr Lawrance in 2014 showed that the [alleged Refusal to Proceed decision] had been made. ...
...
[BN] alleged that, at the [Project Control Group] meeting on 13 June 2014, Mr Lawrance made a statement 'to the effect, in addition to the [Project Control Group] approval, that Mirvac would need internal Mirvac approval prior to commencing Stage 1 works on the Project'. (emphasis added) (footnotes omitted)
Mirvac had internal approval processes and that Mirvac would not be able to commence Stage 1 without having internal approval.
I accept that evidence. However, I do not consider Mr Lawrance's statement was repudiatory or one which manifested the intention alleged by [BN]. As will be seen, Mirvac WA had the right to disapprove a budget as a member of the [Project Control Group]. Before a [Project Control Group] meeting at which a budget was to be approved or disapproved by the [Project Control Group], it is to be expected that Mirvac would go through an internal approval process to enable their representatives on the [Project Control Group] to be in a position to vote appropriately, as explained by Mr Draffen in a passage extracted above. There is nothing repudiatory or sinister about this. Indeed, Mr Waller said he would think that would be logical. (emphasis added) (footnotes omitted)
In his oral evidence, Mr Draffen said, consistently with what he wrote at the time, that the purported minutes were not an accurate record of their meeting. He said:
'[T]here's references in there to comments that I made around the Mirvac [B]oard approval process which I don't agree are correct. Certainly, from a Mirvac perspective, we would have gone through an internal approval process to be in a position at the formal [Project Control Group] to approve - or our - or, you know, basically in - in a position for our attendees at the [Project Control Group] to vote appropriately. That is a process that would have been an internal process that may or may not have required Mirvac [B]oard approval, depending on the size of - the scope of the approval sought. ... Certainly we would have gone through a process prior to any formal consideration, for example, of a budget or programme at the [Project Control Group] to get the necessary approvals that we would need.'
In cross examination, Mr Waller was asked if Mr Draffen said words to the effect that Mirvac will need to go through its internal approval processes before it could agree at [Project Control Group] level to a construction of Stage 1. He replied 'That's - well, I would think that would be logical'. (footnotes omitted)
The judge accepted, at [478] of the [primary decision], that the statement that 'Mirvac had internal approval processes and that Mirvac would not be able to commence Stage 1 without having internal approval' was made by [Mr Lawrance] at the 3 June 2014 [Project Control Group meeting] [(Mr Lawrance's Statement)]. The judge found that [Mr Lawrance's Statement] was not repudiatory or one that manifested the intention alleged by [BN]. If [BN's] construction of the Transaction Documents is accepted, [Mr Lawrance's Statement] was clearly repudiatory and one that manifested the intention alleged and was a further [d]efault by Mirvac (WA). (emphasis added)
I am not satisfied that the reason why Mirvac WA did not submit a programme and budget in relation to subdivision works or construction works was because Mirvac Ltd's directors had not approved the Project being implemented by carrying out subdivision works or construction works and creating Sale Lots. Indeed, I find that was not the reason.
A budget for Stage 1 could not be prepared until after the [Local Structure Plan] had been approved, which occurred in February 2014. In April 2014, Mr Draffen and Mr Waller agreed that Mirvac WA would do some more work around the potential for Stage 1 that would present the Project in its best light. This is what Mirvac WA sought to do in the September 2014 Report.
The September [2014] Budget included the cost of detailed design and documentation of the second access road, the bulk entry works and the subdivision application for Stage 1. Until these expenses were approved, and the work done, it was not possible to create a realistic budget for subdivision works or construction works.
Mirvac WA's refusal to agree to meetings being recorded was not a breach of its obligations, good faith or otherwise. I am also not satisfied it refused in order to delay or stop the Project. The documentary evidence showed that, by September 2014, the relationship between the parties was combative. Mirvac WA had said it was willing to attend a meeting if it was not recorded, and was willing to pay for an independent minute taker. This was not an unreasonable stance, in all of the circumstances. Mirvac WA's Good Faith Obligation did not require it to agree to the meeting being recorded.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
Research Associate to the Honourable Justice Murphy and the Honourable Justice Mazza
[1] Mirvac (WA) Pty Ltd v Binningup Nominees Pty Ltd [2020] WASC 28.
[3] This overview is largely drawn from the findings in the primary decision.
[11] There is an issue in the appeal as to whether (as the judge found) Mirvac (WA) had the right to disapprove a Budget or whether (as BN contends) only BN had the right to disapprove a Budget.
[14] See primary decision [62] - [90].
[42] Primary decision [23]. The term 'Non Monetary Event of Default' was defined in cl 1.1 of the Services Agreement, in respect of a party, to include:
[T]hat party fails to carry out its obligations under this document (except any obligation which if not complied with would constitute a Monetary Event of Default) in a proper, timely, professional and workmanlike manner such that in the opinion, acting reasonably, of the party not in default such failure will have a material and adverse effect on the Project.
[47] Primary decision [40], [99] - [100].
[53] Primary decision [448] - [449]. (The minutes (exhibit 17.644) are not in the GB.)
[62] Primary decision [313], [322], [375], [408], [485], [555], [790].
[63] Primary decision [539] - [543].
[64] Primary decision [547] - [549].
[65] Primary decision [551] - [552].
[66] Primary decision [553] - [555]. The judge considered criticisms of Mr Draffen's evidence by counsel for BN at primary decision [479] - [485].
[71] Primary decision [403] - [404].
[72] Primary decision [556] - [568].
[73] Primary decision [569] - [571].
[75] Primary decision [583] - [584].
[76] Primary decision [585] - [618].
[79] Primary decision [103], [178].
[80] Primary decision [263] - [270].
[81] Primary decision [707] - [722].
[83] Primary decision [511] - [515].
[84] Primary decision [438] - [445].
[86] Primary decision [472] - [473].
[88] Primary decision [477] - [478].
[91] Primary decision [527] - [528].
[92] Primary decision [746] - [751], [754] - [756].
[93] Primary decision [778], [790].
[100] Lee v Lee [2019] HCA 28; (2019) 266 CLR 129.
[101] Lee [55]. See also Fox v Percy [2003] HCA 22; (2003) 214 CLR 118 [25]; Robinson Helicopter Co Inc v McDermott [2016] HCA 22; (2016) 90 ALJR 679 [43]; Smart v Power [2019] WASCA 106 [100] ‑ [106]; Child and Adolescent Health Service v Mabior [2019] WASCA 151; (2019) 55 WAR 208 [93]; Joyce v Anderson [2020] WASCA 48 [105] ‑ [106], [204] ‑ [213].
[103] Nocton v Lord Ashburton [1914] UKLawRpAC 31; [1914] AC 932, 957; Clarke Boyce v Mouat [1994] 1 AC 428, 436 - 437.
[104] Voulis v Kozary [1975] HCA 44; (1975) 180 CLR 177, 193; Commissioner of the Australian Federal Police v Kalimuthu [No 2] [2018] WASCA 192 [490] ‑ [491].
[105] BN's written submissions filed 13 May 2021, par 4.2.
[107] Primary decision [66]; Agreed chronology WB 123.
[108] Primary decision [66]; Agreed chronology WB 123.
[113] Primary decision [116]; GB 316 - 353, particularly GB 331 - 332.
[116] Primary decision [121] - [122]. See also primary decision [128].
[118] Primary decision [71]; Agreed chronology WB 123.
[120] Primary decision [118], [123].
[121] Primary decision [123]; GB 354 - 397, particularly GB 377, 394.
[125] GB 429 - 432; Agreed chronology WB 123.
[127] Mr Jake Davidson and the witness Mr Adam Davidson are not related. To avoid confusion, the judge referred to each man by his full name: primary decision [124].
[128] Primary decision [124] - [125].
[130] Primary decision [127] - [128].
[135] Primary decision [132] - [133].
[141] Primary decision [138] - [140].
[148] Primary decision [145] - [147].
[152] Primary decision [150], [158], [161].
[158] Primary decision [75]; agreed chronology WB 124.
[164] Primary decision [75]; agreed chronology WB 124.
[172] Primary decision [156] - [157].
[174] Primary decision [161] - [163].
[190] Primary decision [164] - [165]; GB 585 - 586.
[191] Primary decision [165] - [166]; GB 587 - 590.
[192] Primary decision [167] - [171].
[200] Primary decision [328]. (The document is not in the GB.)
[204] Primary decision [332]. (The document is not in the GB.)
[206] Primary decision [334]. (The document is not in the GB.)
[207] Primary decision [337] - [338].
[208] Primary decision [335]. (The document is not in the GB.)
[212] Primary decision [340]; GB 591 - 592.
[214] Primary decision [344]; GB 593 - 598.
[215] Primary decision [349] - [350].
[216] Primary decision [351]; GB 599 - 603.
[219] Primary decision [354]; GB 604 - 606.
[222] Primary decision [187]; GB 864 - 869.
[223] Primary decision [188]; GB 870 - 879. (The index to the GB wrongly refers to this as exhibit 24.08, whereas it is exhibit 24.8.)
[224] Primary decision [189] - [190].
[226] Primary decision [356]; GB 857 - 863.
[230] Primary decision [193]; GB 607 - 608.
[233] Primary decision [357]. (This document is not in the GB.)
[234] Primary decision [358] - [359].
[235] Primary decision [360]. (This document is not in the GB.)
[238] Primary decision [365] - [368]. (These spreadsheets were not in the GB.)
[239] Primary decision [363] - [364], [369] - [372].
[240] Primary decision [373] - [374].
[243] Primary decision [196] - [197]; GB 647 - 649.
[246] Primary decision [200] - [201].
[247] Primary decision [196] - [197]; GB 647 - 649.
[248] Primary decision [377]; GB 650 - 655.
[252] Primary decision [380]; GB 656.
[253] Primary decision [381] - [382].
[254] Primary decision [383] - [384]; GB 659 - 669, particularly GB 666.
[255] Primary decision [386]; GB 668.
[256] Primary decision [387] - [389].
[266] Primary decision [399] - [405].
[267] Primary decision [406] - [408].
[269] Primary decision [409]; GB 670 - 678.
[270] Primary decision [411]; GB 676 - 677.
[271] Primary decision [412] - [418].
[273] Primary decision [420]; GB 679 - 681.
[275] Primary decision [422]; GB 680.
[279] Primary decision [426] - [431].
[280] Primary decision [203] - [204].
[282] Primary decision [206] - [207].
[283] Primary decision [209] - [210].
[285] Primary decision [88]; agreed chronology WB 126.
[286] Primary decision [212]; GB 683 - 684.
[287] Primary decision [214]; GB 697 - 700.
[288] Primary decision [214] - [215]; GB 697 - 698.
[307] Primary decision [229] - [231].
[309] Primary decision [432]; GB 695.
[310] Primary decision [433] - [437].
[312] Primary decision [286] - [287].
[313] Primary decision [234]; YB 131 - 137.
[314] Primary decision [235] - [238].
[315] Primary decision [239] - [240].
[317] Primary decision [243] - [245].
[319] Primary decision [242], [247].
[321] Primary decision [89]; agreed chronology WB 126; GB 703 - 744.
[325] Primary decision [438]; GB 747 - 753.
[326] Primary decision [440]; GB 748.
[330] Primary decision [441] - [442].
[333] Primary decision [290] - [291].
[334] Primary decision [293] - [294].
[336] Primary decision [249] - [250].
[338] Primary decision [252] - [253].
[339] Primary decision [254] - [255].
[341] Primary decision [261] - [262].
[342] Primary decision [89]; agreed chronology WB 127.
[349] Primary decision [90]; agreed chronology WB 127.
[352] Primary decision [451] - [464].
[353] Primary decision [472] - [473].
[356] Primary decision [297] - [298].
[360] Primary decision [477] - [478].
[366] Primary decision [302], [538].
[367] Primary decision [303] - [305].
[368] Primary decision [306] - [313].
[369] Primary decision [516] - [521].
[370] Primary decision [526] - [528].
[372] By cl 5.12(b), each of BN and Mirvac (WA) 'must ensure that at least one of the Project Control Group members appointed by it attends meetings of the Project Control Group'.
(1998) 43 NSWLR 104
(2003) 214 CLR 118
(2016) 90 ALJR 679
(2019) 55 WAR 208
(2019) 266 CLR 129
(1975) 180 CLR 177