[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE
[This headnote is not to be read as part of the judgment]
The respondent (YTO) was the principal contractor for a commercial and residential development in Ashfield, Sydney. In July 2017, YTO entered into a subcontract with Innovative Civil Pty Ltd (Innovative), of which the appellant was the sole director. Pursuant to the subcontract, Innovative agreed to carry out certain civil works on the Ashfield site, including the excavation and removal of organic material.
On 11 January 2018, Innovative issued a payment claim to YTO pursuant to s 13 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the SOP Act), which relevantly included a variation amount of $490,000 (plus GST) for the removal of 70 loads (later reviewed to be 66 loads) of excavated general solid waste (GSW) material at a rate of $7,000 per load. On 7 February 2018, after YTO served a payment schedule disputing Innovative's payment claim, Innovative lodged an adjudication application pursuant to s 17 of the SOP Act. On 22 February 2018, an adjudicator determined that YTO was to pay Innovative a total of $1,535,377.51 (inclusive of GST), which included an amount of $462,000 (plus GST) for the removal of 66 loads of GSW.
On 28 March 2018, YTO commenced proceedings against Innovative in the Supreme Court to set aside the adjudicator's determination on the basis of fraud. On 10 August 2018, Rein J held that YTO's claim for fraud could not be established and found that YTO was precluded from relying on assertions made in closing submissions where they departed from the claim as articulated in the Second Further Amended Technology & Construction List Statement. On 15 May 2019, the Court of Appeal allowed YTO's appeal in part, concluding that Rein J had not addressed YTO's claim dealing with Innovative's representation on the number of loads of GSW, nor did his Honour address the respondent's allegation that Innovative knew the representation was false. The Court ordered Innovative pay into the Court an amount of $399,000 (plus GST and interest). Innovative did not pay this amount and on 14 October 2019, Innovative was placed into external administration.
On 24 May 2020, YTO commenced proceedings in the District Court against the appellant. Russell SC DCJ held that representations made by the appellant were made in trade or commerce and were misleading or deceptive. His Honour further found that the adjudicator relied on the misleading and deceptive conduct in coming to the view that Innovative was entitled to its entire claim in relation to the carting and tipping of GSW. His Honour held that YTO suffered loss and damage and awarded damages of $306,763.10 (including interest).
The appeal involved two main issues. The first issue was whether the primary judge erred by finding that representations made by the appellant to the adjudicator constituted conduct "in trade or commerce" for the purposes of s 18 of the Australian Consumer Law (ACL) (Ground 1). The second issue was whether the primary judge should have found that the respondent was precluded from bringing its claim in the District Court on the application of one or more of the principle in Port of Melbourne Authority v Anshun Pty Ltd (1981) 147 CLR 589; [1981] HCA 45, abuse of process and issue estoppel (Grounds 2-4). The appellant also raised a denial of procedural fairness (Ground 7) and an alternative argument contending that the primary judge erred in the assessment of damages under the ACL (Ground 8).
The Court (Mitchelmore JA, Kirk JA and Adamson JA agreeing) held:
(1) The making of the representations to the adjudicator was not conduct in trade or commerce. Although an adjudication application is the means by which a claimant may seek to enforce their entitlement to a progress payment under the SOP Act in the event of a dispute, and the process may be prevalent in the construction industry, it does not follow that all conduct associated with the process is conduct in trade or commerce. The relationship between the adjudicator and the parties is not a trading or commercial relationship; and the adjudicator has the statutory function of determining the dispute. Although the dispute may arise from a commercial transaction, the making of the representations to the adjudicator was not conduct which in itself was an aspect or element of activities or transactions which, of its nature, bore a trading or commercial character: [84]-[85].
Concrete Constructions (NSW) Pty Ltd v Nelson (1990) 169 CLR 594; [1990] HCA 17 applied; Bitannia Pty Ltd v Parkline Constructions Pty Ltd (2006) 67 NSWLR 9; [2006] NSWCA 238; Energetech Australia Pty Ltd v Sides Engineering Pty Ltd [2005] NSWSC 1143; 226 ALR 362; Little v Law Institute of Victoria (No 3) [1990] VR 257; Pertzel v QLD Paulownia Forests Ltd [2008] 2 Qd R 526; [2008] QCA 287; Probuild Constructions (Aust) Pty Limited v Shade Systems Limited [2018] NSWSC 540 considered.
(2) In light of the determination on Ground 1, it was not necessary to reach a concluded view on the second main issue, regarding Anshun estoppel, abuse of process and issue estoppel. However, the raising of these issues gave rise to a number of difficulties in the oral submissions that would have led to declining to entertain these grounds on the appeal, in circumstances where they were not raised below: [98]. It was also unnecessary to determine Grounds 7 and 8: [101]-[102].