Preliminary consideration of the basis for disputing the debt
10 Scotia Downs and Flosprings have consistently and strenuously denied their indebtedness to the bank. They sought a finding under s 459G that there was a genuine dispute or offsetting claim, and applied to review the finding when their application was dismissed. They also filed a Supreme Court action shortly after the bank commenced its proceedings, and have prosecuted it by way of defence and counterclaim.
11 The evidence of Scotia Downs and Flosprings disputing the debt is set out in the affidavits Mr Enzo Floreani sworn 27 October 2010, 25 March 2011 and 11 August 2011. Mr Floreani is the sole director of Scotia Downs, and is also authorised by Flosprings to swear an affidavit on its behalf. These claims of the defendants and accounts of representations allegedly made by the bank and agreements allegedly reached between the parties are also particularised in the Supreme Court proceedings. Mr Floreani deposes, and the Supreme Court proceedings allege, that:
(a) The nature of the finance sought and agreed to be provided was to purchase and subdivide land to develop a retirement village and aged care facility on a staged basis. The bank represented that it was experienced in the funding requirements of such developments. Stage one of the project was the construction of 54 independent living units. It was agreed that the loan facilities were like an overdraft, pursuant to which money could be drawn down as necessary to fund the construction of units. As the settlement of units sold took place, the monies received would be remitted to the account and credited accordingly. The facility limit was $5.2 million.
(b) Sweetwater commenced construction in early 2007. By March 2007 it had signed contracts for the sale of 24 of 50 units. In the period prior to August 2007, it had completed all of the work associated with the subdivision for the development, and had completed at least half of the work necessary to complete the units that had been pre-sold. It did not reach the funding limits under the loan facilities.
(c) On or about 27 August 2007 Mr Floreani met with the bank as Sweetwater was experiencing cash flow difficulties by reason of price escalations and increased supplier and subcontractor costs. He advised the bank that the first five units were nearing completion and that approximately $1.1 million would then be remitted to the account, which would cover the existing cash shortfall and provide a significant buffer against the need for further draw-downs. The bank's representative then indicated that the bank required that the loan facility limit be reduced as it appeared the full facility would not be utilised in the development.
(d) The bank then advised in September 2007 that it intended to reduce the loan facility limit from $5.2 million, to approximately $3.15 million. At that time the monies drawn down totalled approximately $2.36 million. Sweetwater was operating within the loan facility limit and was on track to pay out the anticipated debt with the settlement of pre-sold units that were then midway through construction. It was agreed by the bank's representative that the new facility limit could be moved up or down as required, provided the original $5.2 million limit was not reached.
(e) Although some further draw-downs were made after September 2007, the bank either responded very slowly or rejected requests for the draw-down of monies after this date. The delay in varying, or the refusal to vary, the facility limit upwards was a breach of the agreement, and contrary to the representations made by the bank.
(f) In the period from about August 2007 to mid 2008 a number of contractors and other creditors involved in the construction of units were either not paid or not paid in a timely way. The work on the units slowly ground to a halt, and local tradespeople lost interest in working on the development. Potential local purchasers of units also lost confidence in the development. The work on the development, and sales of units, never regained momentum.
(g) The bank's delay or refusal to allow draw-downs resulted in lost sales, an inability to achieve further sales and an inability to construct the remaining units or the proposed nursing home. It also significantly increased Sweetwater's holding costs. In total 26 units were sold, and 10 unit sales were lost because of the delay. The 10 lost sales would have provided the project with approximately $2.3 million.
(h) Sweetwater's indebtedness to the bank never reached the $5.2 million limit of the loan facility agreed at the commencement of the project.
12 In summary Mr Floreani deposes that Sweetwater was misled in entering into the loans with the bank, and that the bank's alteration of the nature and limit of the loan facility was a breach of the initial agreement. Further, by significantly delaying or refusing to allow the draw-down of funds under the loan facilities the bank breached the initial agreement, and the variation of it in September 2007. The same conduct was also a breach of representations made by the bank. He asserts a substantial offsetting claim, which is unquantified.
13 The bank relies on affidavits sworn by a manager, Ms Sonya Causovski, on 1 October 2010 and 15 February 2011. Scotia Downs and Flosprings do not contest the evidence of Ms Causovski insofar as it sets out the documents reflecting the loan facility and the variations to it. Ms Causovski deposes that:
(a) The aggregate facility limit of the loan facility initially provided to fund the development was $5.07 million, although by 18 September 2007 the limit had been increased to $5.7 million.
(b) There was no relevant delay in the provision of funding as the bank continued to provide to Sweetwater all requested draw-downs from August 2007 until March 2008. Draw-downs against the new facility limit agreed in September 2007 were allowed in that month, and in October 2007, November 2007, December 2007, February 2008 and March 2008.
(c) In September 2007 Sweetwater owed the bank $2.35 million and the aggregate facility limit was $5.7 million. Sweetwater requested a variation to the facility agreement to provide an additional line of overdraft funding of $350,000 and to reduce the facility limit by consolidating the various accounts to take into account expected debt reduction through completion and sale of units in stages. The loan facility limit was reduced to $2.55 million plus a new overdraft facility of $350,000 and funding of the GST payments of $250,000. The aggregate facility limit was therefore $3.15 million.
(d) However, by 17 December 2007 Sweetwater owed the bank $3.77 million, which exceeded the new aggregate facility limit.
(e) In March 2008 Sweetwater requested an increase in the facility limit of $650,000. At that time only four units had been completed and cost overruns of approximately $1.35 million had been identified by Sweetwater. The bank declined to increase the facility limit as requested.
14 There are shortcomings in both the evidence of Mr Floreani and that of Ms Causovski. Mr Floreani does not fully contradict the evidence of Ms Causovski, even in his affidavit filed in reply. Amongst other things, he does not properly explain the inconsistency between his allegations of delay in funding, and the bank's evidence that until March 2008 it met each funding request, and he does not respond to the bank's evidence as to the reasons for its refusal of funding requests. Further, in my view it is likely to be difficult for Mr Floreani to make out the case that it was an oral term of the agreement in September 2007 that although the new loan facility limit was reduced to $3.15 million, the total borrowings could be varied upward within the original $5.2 million facility limit.
15 The bank's evidence is deficient in that it does not address Mr Floreani's allegations as to statements and representations made to him by identified representatives of the bank. These allegations found the defendants' offsetting claims of breach of agreement and misleading and deceptive conduct. The bank also fails to explain the reasons for the reduction in the loan facility limit from $5.7 million to $3.15 million in September 2007, other than to suggest that it was at Sweetwater's request. It would be surprising if this was correct.
16 It is impossible on the basis of the material to determine the dispute on the facts or decide the merits of the dispute, and the Court is not required to do so. On hearing an application for leave under s 459S the Court is only required to give preliminary consideration to the basis for disputing the debt. It does not resolve questions of fact nor determine where the merits lie.
17 In considering the grant of leave the Court is not required to determine whether there is a genuine dispute as to the debt. The defendants are seeking a statutory indulgence to raise grounds they have already raised, or could have raised. They must establish that the grounds they propose to rely on in opposing the winding up application are arguable: Master Paving Pty Ltd v Heading Contractors Pty Ltd (1997) 15 ACLC 1025 at 1033 ("Master Paving"). In my view sufficient evidence is before the Court, containing sufficient particularity, to distinguish the evidence from mere claim or assertion, and it is arguable. The evidence is sufficient to grant the defendants leave to rely on the grounds set out in the affidavits and exhibited pleadings in opposing the winding up. I have not determined that the defendants' evidence disputing the debt is sufficient to successfully oppose the winding up applications, only that it can be advanced.