© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2018] NSWCA 146
Court of Appeal (NSW)
2018-02-23
McColl JA, Payne JA, White JA
Original judgment source is linked above.
Background
Primary Judgment
Grounds of Appeal
Liability Issues
Ground 2 - appellant's submissions
Ground 2 - consideration
Grounds 1 and 5 - appellant's submissions
Grounds 1 and 5 - consideration
Ground 6 - appellant's submissions
Ground 6 - consideration
Ground 3 - appellant's submissions
Ground 3 - consideration
Ground 4 - appellant's submissions
Ground 4 - consideration
Ground 8 - consideration
Ground 7
TOTAL $138,380.70 Past gratuitous domestic and attendant care 11/10/06 to 10/04/07 for 28 hours per week @ $22.50 ph $16,380.00 = $22.50 x 28 x 26 weeks = 11/04/07 to 13/04/15 for 21 hours per week @ $25.46 ph $222,418.56 = $25.46 ph x 21 x 416 weeks = 14/04/15 to 19/04/17 for 21 hours per week @ $25.46 ph $55,604.64 = $25.46 ph x 21 x 104 = TOTAL $294,403.20 Future domestic services and attendant care 21 hours per week during life expectancy at $45.50 ph $778,254.75 = $45.50 x 21 x 814.5 = Future lawn mowing, gardening and home maintenance Lawn mowing and gardening on average 1 hour per week @ $45 $36,652.50 ph during life expectancy = $45 x 814.5 = Handyman assistance on average 6 hours every 3 months or 0.46 $26,226.90 hpw @ $70 ph = $70 x 0.46 x 814.5 = TOTAL $62,879.40 GRAND TOTAL $2,615,605.93
Submissions
Consideration
Appellant's submissions
Consideration
Appellant's submissions
Consideration
Submissions by the parties
Consideration
Appellant's Submissions
Consideration
Submissions
Consideration
Conclusion on damages issues
Costs
Conclusion and orders
Amendments 10 August 2018 - 10/08/18: Typographical error in [169] amended. 27 August 2018 - 27/08/18: Paragraph numbering amended in [165]. 31 August 2018 - table reformatted in [83] 09 May 2019 - Coversheet - corrected paragraph of White JA's judgment from [181] to [182]; added reference to Miller v Galderisi [2009] NSWCA 353 [21] - added pinpoint reference to judgment below, "at [331]" [26], [28], [30], [31], [93], [157], [158] - removed ".00" from numerical figures [36] - corrected case name "United" to "Uniting" and "of" to "in"; added reported citations [37] - corrected case name adding "League"; removed MNC cited prior for Mooney; removed "per" [38], [39] - added section heading for legislation [43] - added reported case citation in Perisher Blue [66], [70] - added reported case citation to Aust Torts Reps [48] - added pinpoint reference to judgment below, "at [283]" [83] - removed "20" from years in dates (i.e. "2019" became "19") [96], [119], [132] - added reported case citation to MVRs [99] - changed "20 June" to "30 June" [115] - removed MNC cited prior in Sampco [120] - removed case citation cited prior in Malec [125] - corrected case name from "Simmons" to "Simmonds"; corrected citation of Babbage v Dungog to "536" from "562"; corrected to "Burchett AJ" from "Einstein J" [130] - corrected pinpoint reference in Kirby P and Meagher JA judgment in Masland from "176-186" to "176-182" [131] - removed MNC cited prior in Amoud and Miller v Galderisi [139] - deleted "the" from "over the Mr Bosevski's life" [145] - removed MNC cited prior in Miller v Galderisi [153] - attributed quote to Miller v Galderisi at [22] [170(2)] - rephrased to "award of damages for loss of future earning" rather than "award of loss for future earning" [178] - corrected "Boveski" to "Bosevski" DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 09 May 2019
Brown v New South Wales Trustee and Guardian [2012] NSWCA 431 Dang v Chea [2013] NSWCA 80; (2013) 63 MVR 240 Doppstadt Australia Pty Ltd v Lovick & Sons Developments Pty Ltd (No 2) [2014] NSWCA 219 Fexuto Pty Ltd v Bosnjak Holdings Pty Ltd (No 3) (1998) 30 ACSR 20 Fox v Wood (1981) 148 CLR 438; [1981] HCA 41 Garzo v Liverpool/Campbelltown Christian School [2012] NSWCA 151 Ghunaim v Bart [2004] NSWCA 28 Henderson v Campbell [2002] NSWSC 1202 James v Surf Road Nominees Pty Ltd ((No 2) [2005] NSWCA 296 Jones v Dunkel (1959) 101 CLR 298; [1959] HCA 8 Joslyn v Berryman (2003) 214 CLR 552; [2003] HCA 34 Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20 Miller v Galderisi [2009] NSWCA 353 Perisher Blue Pty Ltd v Nair-Smith [2015] NSWCA 90 Port Macquarie Hastings Council v Mooney [2014] NSWCA 156 Richard v Mills ((2003) 27 WAR 200; [2003] WASCA 97 Roads and Traffic Authority of NSW v Dederer (2007) 234 CLR 330; [2007] HCA 42 Sampco Pty Ltd v Wurth [2015] NSWCA 117 Sharman v Evans (1977-1978) 138 CLR 563; [1977] HCA 8 Shaw v Thomas [2010] NSWCA 169 Shoalhaven City Council v Humphries [2013] NSWCA 390 United Church of Australia Property Trust ((NSW) v Miller [2015] NSWCA 320 Van Gervan v Fenton (1992) 175 CLR 327; [1992] HCA 54 White v Benjamin [2015] NSWCA 75 Category: Principal judgment Parties: 2017/117390
Moray & Agnew (Appellant in both matters) Villari Lawyers (Respondent in 2017/117390) HWL Ebsworth (Respondent in 2017/117381) File Number(s): 2017/117390; 2017/117381 Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Common Law Division Citation: [2016] NSWSC 1893 Date of Decision: 29 March 2017 Before: Rothman J File Number(s): 2009/337219; 2011/70381
Headnote [This headnote is not to be read as part of the judgment] In 2006 Mr Riste Bosevski, a labourer employed by Professional Contracting Pty Ltd, was injured at a work site in regional New South Wales operated by Avopiling Pty Ltd. Two employees of Avopiling Pty Ltd were erecting a mast on a pile driving rig at the site when an auxiliary cable on the mast snapped, causing metal objects to fall and strike Mr Bosevski, who was standing with his supervisor in the vicinity of the pile driving rig. Mr Bosevski suffered injuries to his head, neck and chest. In 2009 Mr Bosevski commenced proceedings in negligence against Avopiling Pty Ltd. In 2011 Avopiling Pty Ltd filed a defence claiming, inter alia, contributory negligence by Mr Bosevski. In its defence, Avopiling Pty Ltd also alleged that any liability it had to Mr Bosevski ought to be reduced under s 151Z(2) of the Workers Compensation Act 1987 (NSW) by reason of the negligence of Professional Contracting Pty Ltd. Later in 2011 the Workers Compensation Nominal Insurer, which by that time was responsible for Professional Contracting Pty Ltd's obligations to pay workers compensation, commenced proceedings against Avopiling Pty Ltd seeking indemnity pursuant to s 151Z(1)(d) of the Workers Compensation Act 1987 (NSW) for payments it had made to Mr Bosevski. In its defence, Avopiling Pty Ltd repeated the allegation that any liability it had to Mr Bosevski ought to be reduced under s 151Z(2) of the Workers Compensation Act 1987 (NSW) by reason of the negligence of Professional Contracting Pty Ltd. Both sets of proceedings were heard together. In the negligence proceedings, the primary judge found that Avopiling Pty Ltd had been negligent. The primary judge awarded Mr Bosevski damages in the sum of $2,632,390.93. The primary judge found that Professional Contracting Pty Ltd had not been negligent and Mr Bosevski had not been guilty of contributory negligence. In the indemnity proceedings, the primary judge found in favour of the Workers Compensation Nominal Insurer in the sum of $919,225.23. The primary judge rejected Avopiling Pty Ltd's defence that Professional Contracting Pty Ltd had also been negligent. On appeal the issues were: (i) Whether the primary judge formulated the risk of harm for the purposes of the negligence of Professional Contracting Pty Ltd and the contributory negligence of Mr Bosevski in a way that was impermissible; (ii) Whether the primary judge erred in finding that Professional Contracting Pty Ltd was not negligent; (iii) Whether the primary judge erred in not making a finding of contributory negligence by Mr Bosevski; (iv) Whether the primary judge erred in his Honour's award of damages. The Court (Payne JA, McColl and White JJA agreeing) held, allowing the appeal in part: In relation to issue (i), per Payne JA (McColl JA agreeing and White JA agreeing in part and not deciding if the formulation of the risk of harm was too narrow): Avopiling Pty Ltd bore the onus of proof, including the identification of the correct risk of harm, to establish negligence in relation to Professional Contracting Pty Ltd and contributory negligence in relation to Mr Bosevski. It failed to frame its pleadings in respect of the risk of harm by specific reference to relevant provisions of the Civil Liability Act 2005 (NSW) or identify the correct risk of harm in its pleadings: [40]-[42] Garzo v Liverpool/Campbelltown Christian School [2012] NSWCA 151, applied. The primary judge's formulation of the risk of harm was not in error. It identified the source and general causal mechanism of the injury: [43] Civil Liability Act 2005 (NSW), s 5B; Roads and Traffic Authority of NSW v Dederer (2007) 234 CLR 330; [2007] HCA 42; Perisher Blue Pty Ltd v Nair-Smith [2015] NSWCA 90, applied. In relation to issue (ii), per Payne JA (McColl and White JJA agreeing): The primary judge was correct to find that Professional Contracting Pty Ltd was not negligent. The evidence established that Mr Bosevski and his supervisor were acting in the scope of their duties by being in the vicinity of the pile driving rig: [50]-[52], [59], [62], [79]-[81] It was not demonstrated that Professional Contracting Pty Ltd knew, or had any reason to know, of the risk of harm, or that Mr Bosevski or his supervisor could appreciate the risk of harm: [55]-[58] In relation to issue (iii), per Payne JA (McColl and White JJA agreeing): The primary judge was correct not to make a finding of contributory negligence by Mr Bosevski. The evidence established that Mr Bosevski had a legitimate reason for being in the vicinity of the pile driving rig when he was injured, and Avopiling Pty Ltd did not prove that Mr Bosevski knew or ought to have known of the risk of harm: [66]-[69], [79]-[81] Joslyn v Berryman (2003) 214 CLR 552; [2003] HCA 34; Ghunaim v Bart [2004] NSWCA 28, applied. In relation to issue (iv), per Payne JA (McColl and White JJA agreeing): The primary judge's award of damages should be varied in respect of some heads of damage and left undisturbed in respect of other heads. Save for certain agreed adjustments, Avopiling Pty Ltd failed to show error in the award of damages for past economic loss, loss of future earning capacity and past gratuitous care: [94]-[95], [101]-[103], [111]-[117], [169] Civil Liability Act 2002 (NSW), s 15; Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20, applied. Sampco v Wurth [2015] NSWCA 117, distinguished. Section 13 of the Civil Liability Act 2002 (NSW) applies to damages for future economic loss both in respect of "future earning capacity" and "other events on which the award is to be based". The latter category includes damages for future attendant care, lawn mowing, gardening and handyman services, and future medical expenses. Sub-section (2) requires an approach to the assessment of damages which is consistent with the approach in Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20. This extends to the assessment of damages for future attendant care, lawn mowing, gardening and handyman services, and future medical expenses, consistent with principle and the weight of authority in this Court. This involves calculating the percentage possibility of a future event occurring but for the injury and then adjusting the award of damages according to that calculation: [128]-[137] Civil Liability Act 2002 (NSW), Part 2, ss 11A, 12, 13; Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20; Marsland v Andjelic (1993) 31 NSWLR 162; Amoud v Al Batat [2009] NSWCA 333; Miller v Galderisi [2009] NSWCA 353; White v Benjamin [2015] NSWCA 75; Metaxoulis v McDonald's Australia Ltd [2015] NSWCA 95, applied. Sampco Pty Ltd v Wurth [2015] NSWCA 117, considered. Gordon v Truong [2014] NSWCA 97, not applied. It does not follow from the use of the life expectancy tables that no further allowance for vicissitudes is warranted for future attendant care: [138], [153] Bresatz v Przibilla (1962) 108 CLR 541; [1962] HCA 54; Sharman v Evans (1977-1978) 138 CLR 563; [1977] HCA 8; Simmons v Hillsdon (No 2) [1965] NSWR 837; Henderson v Campbell [2002] NSWSC 1202; Babbage v Dungog Shire Council [2003] NSWSC 562; Richard v Mills (2003) 27 WAR 200; [2003] WASCA 97, distinguished. The primary judge did not approach the assessment of damages for future attendant care, lawn mowing, gardening and handyman services, and future medical expenses in the manner required by section 13 of the Civil Liability Act 2002 (NSW): [139], [141], [159], [165] In reassessing the award of damages for future attendant care, an award of damages for future attendant care on a commercial basis is warranted because the required services are readily available and likely to be availed of by Mr Bosevski. A discount of 25 per cent should be made to that award to reflect the various risks in Mr Bosevski's circumstances and the chance that commercial assistance will not be obtained: [139], [142], [147], [149]-[152] Uniform Civil Procedure Rules 2005 (NSW), r 51.53; Civil Liability Act 2002 (NSW), s 13; Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20; Van Gervan v Fenton (1992) 175 CLR 327; [1992] HCA 54; Australia and New Zealand Banking Group Ltd v Haq [2016] NSWCA 93; White v Benjamin [2015] NSWCA 75, applied. In reassessing the award of damages for lawn mowing, gardening and handyman services, a discount of 25 per cent is appropriate: [159], [169] Civil Liability Act 2002 (NSW), s 13; Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20, applied. In reassessing the award of damages for future treatment expenses, a discount of 10 per cent is appropriate: [166], [168], [169] Civil Liability Act 2002 (NSW), s 13; Malec v JC Hutton Pty Ltd (1990) 169 CLR 638; [1990] HCA 20, applied.
[2003] WASCA 97
(1990) 169 CLR 638
(2009) 239 CLR 175
(1968) 122 CLR 649
(2012) 247 CLR 345
(2013) 63 MVR 240
(1981) 148 CLR 438
(1959) 101 CLR 298
(2003) 214 CLR 552
(2003) 27 WAR 200
(2007) 234 CLR 330
(1992) 175 CLR 327
(1993) 31 NSWLR 162
(1962) 108 CLR 541
(2015) 91 NSWLR 752
(2014) 201 LGERA 314
(2015) 90 NSWLR 1
(2009) 54 MVR 167
(2015) 70 MVR 188
(1993) 26 IPR 261
[2009] HCA 27