14 A typical example of the allegations made in relation to a particular contravention can be gleaned from the statement of claim for the first contravention (omitting particulars) which alleges:
Contravention 1 - 29 November 2012 - dispatch interval ending 15:50:00
18. At 15:07 and 15:12 on 29 November 2012, in expectation of extremely high dispatch prices and an extremely high spot price for TI (trading interval) 16:00, and with the intention of ensuring that all of the available capacity of the Murray Units would be dispatched during TI 16:00, the Respondent submitted two rebids of the available capacity of the Murray Units for TI 16:00, the result of which was that the whole of the available capacity was reallocated to the $53 price band.
19. In each of DI (dispatch interval) 15:35, DI 15:40 and DI 15:45, the Respondent received dispatch instructions providing a target output of 1,348.00 MW for the Murray Units.
20. At 15:45:00, the output of the Murray Units was approximately 1,342.44 MW.
21. At 15:45:04:
21.1 AEMO determined and published a dispatch price of $12,497.76 for DI 15:50; and
21.2 AEMO gave, and the Respondent received by around 15:45:30, a dispatch instruction for DI 15:50, to reduce the output of the Murray Units to 1,164.74 MW by 15:50:00 (the dispatch instruction for DI 15:50).
22. The reduction in target output given in the dispatch instruction for DI 15:50, relative to the target output of 1,348 MW received for the preceding dispatch intervals, occurred because a network constraint was binding to avoid overload on the Murray to Dederang transmission line.
23. The Respondent knew that the reduction in target output had occurred because a network constraint was binding to avoid overload on the Murray to Dederang transmission line.
24. At or around 15:45, the Respondent:
24.1 knew that an extremely high dispatch price had been determined for DI 15:50; and
24.2 expected that an extremely high spot price would be determined for TI 16:00.
…
26. At 15:47:22, the Respondent submitted a rebid (the 15:47 ramp rate rebid) to be effective from DI 15:55, by which it reduced the down ramp rate for the Murray Units from 50 MW per minute to the minimum permitted ramp rate of 3 MW per minute.
27. Between 15:45 and around 15:48, the output of the Murray Units was initially reduced from 1,342.44 MW to approximately 1,294 MW.
…
29. The output from the Murray Units at 15:50:00 was 1,328.47 MW, namely 163.73 MW in excess of the level of output specified in the dispatch instruction for DI 15:50.
30. At no time between 15:45:00 and 15:50:00 did the output of the Murray Units reduce to 1,164.74 MW.
31. By reason of the matters alleged in paragraphs 21.2 and 29 above, alternatively paragraphs 21.2, 29 and 30 above, the Respondent failed to comply with the dispatch instruction for DI 15:50.
32. The Respondent did not hold the reasonable opinion that compliance with the dispatch instruction for DI 15:50 would either be a hazard to public safety, or would materially risk damaging equipment at any time during DI 15:50.
33. By reason of the matters alleged in paragraphs 31 and 32 above, the Respondent contravened clause 4.9.8(a) (Contravention 1).
34. Further, the Respondent deliberately maintained its generation output from the Murray Units above the level of output specified in the dispatch instruction for DI 15:50:
34.1 with the intention of benefiting from maintaining high levels of output during DI 15:50 and the very high spot price expected for TI 16:00; and
34.2 despite knowing that the Murray Units had received a reduced target output for DI 15:50 because a network constraint was binding to avoid overload on the Murray to Dederang transmission line.
…
38. By reason of:
38.1 its non-compliance with the dispatch instruction for DI 15:50 referred to in paragraph 31 above; and
38.2 the effect of its non-compliance with the dispatch instruction for DI 15:50 combined with the 15:47 ramp rate rebid,
the Respondent:
38.3 generated a greater quantity of energy from the Murray Units during DI 15:50, DI 15:55 and DI 16:00 than it would have generated; and
38.4 earned a greater trading amount from the Murray Units for TI 16:00 than it would have earned,
had it complied with the dispatch instruction for DI 15:50.
39. By reason of the effect of the Respondent's non-compliance with the dispatch instruction for DI 15:50 referred to in paragraph 31 above combined with the 15:47 ramp rate rebid:
39.1 a lower quantity of electricity was able to be imported from the New South Wales region into the Victorian region of the NEM during DI 15:55 and DI 16:00 than would have been imported had the Respondent complied with the dispatch instruction for DI 15:50;
39.2 generating units in the New South Wales and Queensland regions of the NEM were dispatched at lower levels during DI 15:55 and DI 16:00 than they would have been had the Respondent complied with the dispatch instruction for DI 15:50;
39.3 the dispatch price for DI 15:55 was higher than it would have been had the Respondent complied with the dispatch instruction for DI 15:50; and
39.4 the spot price for TI 16:00 was higher than it would have been had the Respondent complied with the dispatch instruction for DI 15:50.
15 As for the defence to such allegations, many of the objective framework facts are not in dispute. But pleas of knowledge, expectation or other states of mind of Snowy Hydro are denied.
16 In terms of Snowy Hydro's defence to the alleged first contravention, it is pleaded:
33. The respondent denies paragraph 33. In further answer to paragraphs 18 to 33 of the statement of claim, the respondent relies upon the following matters:
(a) the respondent's failure to meet the output target in the dispatch instruction for DI 15:50 occurred in the following circumstances:
(i) in each of DI 15:35, DI 15:40 and DI 15:45, Mr Whish had targeted output of 1,348.00 MW, in accordance with the dispatch instructions received for each of those dispatch intervals;
(ii) Mr Whish received a target output for DI 15:50 of 1,164.74MW;
(iii) although Mr Bradburn knew that there was a network constraint binding for DI 15:50, Mr Bradburn believed that this constraint was only transitory, and thus was unlikely to constrain the output of the Murray units in DI 15:55;
(iv) furthermore, Mr Bradburn understood that the capacity of the Murray units had been, or would be, bid into the market in price band 1 (minus $1,000), that being the appropriate bid to make in the circumstances, thus making it very likely that the respondent would receive an instruction to dispatch for DI 15:55 1,348.00 MW, that is, all of its available capacity;
(v) as a result of (iii) and (iv) above, at approximately 15:46, Mr Bradburn telephoned Mr Whish and informed him that the target output for DI 15:55 was likely to be close to 1,348.00 MW;
(vi) having been informed by Mr Bradburn of the likely target output for DI 15:55, Mr Whish concluded that it would potentially jeopardise the safe operation of the plant if he tried to reduce the output of the unit from 1348.00 MW to 1,164.74 MW in one interval, and then increase it back to 1348.00 MW in the next, in order to comply with output targets in successive dispatch instructions. In particular, Mr Whish was concerned that a rapid decrease and increase of this sort would create a risk of 'air entrainment', which had the potential to (a) cause damage to the Murray Units including catastrophic destruction to the Murray Units and surrounding infrastructure, and (b) imperil the personal safety and even the lives of personnel and the public in the vicinity of the Murray Units;
(vii) accordingly, Mr Whish decided to maintain the output of the Murray units during DI 15:50 at approximately 1,348.00 MW.
(b) the respondent was not required to comply with the dispatch instruction for Dl 15:50 because:
(i) for the reasons pleaded in the respondent's cross claim, clause 4.9.8(a) is invalid;
(ii) alternatively, (if clause 4.9.8(a) is valid), in the circumstances pleaded in paragraph (a) above, the respondent held a reasonable belief that compliance with the dispatch instruction for Dl 15:50 would have been a hazard to public safety;
(iii) further or alternatively, in the circumstances pleaded in paragraph (a) above, the respondent held a reasonable belief that compliance with the dispatch instruction for Dl 15:50 materially risked damaging equipment;
(iv) further or alternatively, in the circumstances pleaded in paragraph (a) above, the respondent took reasonable steps to comply with the dispatch instruction for Dl 15:50;
(v) further or alternatively, in the circumstances pleaded in paragraph (a) above, compliance with the dispatch instruction for Dl 15:50 was impracticable;
(vi) further or alternatively, in the circumstances pleaded in paragraph (a) above, the respondent's failure to meet the output target in the dispatch instruction for Dl 15:50 was the result of a reasonable assumption, or alternatively reasonable mistake, being that the constraint would be temporary and the full output of the Murray Units would be requested to be dispatched in Dl 15.55.
17 For present purposes, although nine contraventions are pleaded, the allegations and defences are in similar form. It is not necessary to refer to the AER's reply for present purposes.
18 Snowy Hydro's cross-claim pleads various matters in support of its invalidity contention. The plea of invalidity of cl 4.9.8(a) (at [46] et seq) is based upon many factual allegations that are said to lead to the conclusion that cl 4.9.8(a) is unreasonable, lacks proportionality and is uncertain.
19 First, "(e)xact compliance with dispatch instructions in every dispatch interval is a physical impossibility" (at [17]) (the impossibility scenario). Various factual matters are then listed (at [18]).
20 Second, most of the scheduled generating units in Australia operate by burning fossil fuel (at [19]), that there is variability as to the precise MW quantity of electricity produced by such a unit at any point in time due to various factual matters (at [20]), and that accordingly it is difficult for an operator to control the precise MW quantity of electricity produced (at [21]). There were also variability factors for hydro-electric generating plant that gave rise to similar problems (at [22]-[24]).
21 Third, because of the use of governor control systems that automatically adjust the output of a unit in response to frequency fluctuations, that a Scheduled Generator's output necessarily deviates from the target specified in a dispatch instruction (at [25]-[28]).
22 Fourth, the failure of scheduled generating units, and associated control systems, a common occurrence apparently, results in such units not complying with dispatch instructions (at [29]).
23 Fifth, because the metering equipment for scheduled generating units has an error accuracy tolerance of between 0.5% and 3%, this may lead to non-compliance with a dispatch instruction (at [30]).
24 Sixth, because dispatch instructions may change the required output from one five minute dispatch interval to the next, that when moving from one level of output to another, it is often impossible to reach the precise output level in the short time available (at [31]-[32]).
25 Seventh, because the AEMO may at any time issue a dispatch instruction to provide frequency control ancillary services (to help maintain frequency within the power system), it may then be simultaneously impossible to implement exactly a dispatch instruction (at [33]-[35]).
26 It is then said that "(m)ost scheduled generators fail to comply with dispatch instructions every day that they are generating" (at [36]). But as I put to Mr Cameron Moore SC, senior counsel for Snowy Hydro, this de facto position is only a jury point in the absence of a forensic causal analysis regarding each specific non-compliance.
27 It is then said that the design and operation of the NEM contemplates non-compliance (at [37]-[45]). First, the system of the use and procurement of frequency control ancillary services implies that the National Electricity Rules contemplate discrepancies between dispatch instructions and the electricity generated by generators; discrepancies are managed using such services (at [38]-[40]). Second, because of the power to declare units as non-conforming, with the AEMO permitted to publish non-conformance thresholds, that such power suggests that strict conformance with dispatch instructions is not necessary (at [41]-[42]). Third, because of the AEMO's power to give directions generally "if AEMO is satisfied that it is necessary to maintain system security" that this power is somehow inconsistent with strict compliance because such directions could override (at [43]-[45]).
28 Snowy Hydro then draws together these factual threads and pleads:
Invalidity of clause 4.9.8(a)
46. By reason of the matters pleaded in paragraphs 17 to 34, all Scheduled Generators will:
(a) regularly fail to achieve the particular output specified in their dispatch instructions; and
(b) as a result, if clause 4.9.8(a) applies in accordance with its stated terms, regularly contravene a civil penalty provision in their ordinary day-to-day operations.
47. By reason of the matters pleaded in paragraphs 17 to 45, clause 4.9.8(a) is invalid on one or more of the following grounds:
(a) unreasonableness; and/or
(b) lack of reasonable proportionality to the subject matter the grant of the rule making power under the National Electricity Law.
48. In the alternative, if clause 4.9.8(a) does not require a registered participant to achieve the exact output specified in a dispatch instruction, it fails to communicate the obligation actually imposed by clause 4.9.8(a), and is accordingly invalid on the ground that it is uncertain.
49. As clause 4.9.8(a) is invalid, it is not picked up and applied as part of the law of Victoria or of New South Wales pursuant to the National Electricity (Victoria) Act 2005 or the National Electricity (New South Wales) Act 1997.
Alternative construction of clause 4.9.8(a)
50. In the alternative, if clause 4.9.8(a) of the Rules is valid, on its proper construction it does not require strict compliance with a dispatch instruction or compliance in all circumstances, including but not limited to:
(a) circumstances in which the Registered Participant has taken reasonable steps to comply;
(b) further or alternatively, circumstances in which compliance is not practicable; and
(c) further or alternatively, circumstances of inadvertence or misunderstanding;
Relief claimed
51. The Cross-Claimant seeks:
(a) A declaration that clause 4.9.8(a) of the National Electricity Rules is invalid, on the basis that the rule is not authorised by the rule making power in s 90 of the National Electricity Law…
29 In substance, it is said that cl 4.9.8(a) is invalid for unreasonableness. Second, it is said that it is invalid due to a lack of reasonable proportionality. Third, it is said that it is invalid for uncertainty. Now just stopping there, it is apparent that detailed evidence addressing how the NEM works in practice and addressing each of the matters referred to in [19]-[27] above will need to be led and assessed in order to address these conclusions. A significant number of these factual allegations are in contest - see [17]-[45A] of the AER's defence to cross-claim. As is summarised in the affidavit of Leanne Hanna, solicitor for the AER, affirmed on 9 September 2014, responding to the affidavit of Justin Oliver, solicitor for Snowy Hydro, sworn on 25 August 2014, which I have also considered, contentious factual issues will need to be explored concerning:
whether the technical matters listed at [20] and [23] of the cross-claim make it impossible for the operator of a fossil-fuel burning generating unit or a hydro-electric generating unit to comply with a dispatch instruction ([18(a)] of the cross-claim which is denied, at least in part);
the implications of the operation of a governor control system attached to a generating unit ([28] of the cross-claim which is denied, at least in part);
the regularity with which scheduled generating units or their associated control systems in the NEM fail, resulting in those generating units being unable to comply with a dispatch instruction ([29] of the cross-claim which is denied, at least in part);
the significance of the error accuracy tolerance of metering equipment ([30] of the cross-claim which is denied, at least in part);
whether it is impossible to reach the precise output level specified in the dispatch instruction within the time period between the giving of the dispatch instruction and the end of the dispatch interval ([32] of the cross-claim which is denied, at least in part);
the implications of a Scheduled Generator receiving a dispatch instruction in relation to frequency control ancillary services ([34] of the cross-claim which is denied, at least in part);
whether the National Electricity Rules contemplate regular non-compliance with dispatch instructions ([37] of the cross-claim which is denied, at least in part); and
whether cl 4.9.8(a) is a disproportionate exercise of the rule-making power under s 90(1) of the National Electricity Law ([47(b)] of the cross-claim which is denied); to this may be added reference to s 34.
30 In the alternative to its invalidity arguments, Snowy Hydro asserts that cl 4.9.8(a), if valid, on its proper construction does not require strict compliance with a dispatch instruction where a registered participant has taken reasonable steps to comply, compliance is not practicable or where there is inadvertence or a misunderstanding. But these alternative arguments, if directly or indirectly dealt with as part of any separate determination, move into the offending territory of potentially hypothetical questions and interlocutory declarations which I will explain later.