Anderson Formrite Pty Ltd ACN 097 507 652, in the matter of Anderson Formrite Pty Ltd ACN 097 507 652 v CASC Hire Pty Ltd ACN 066 511 680
[2005] FCA 1424
At a glance
Source factsCourt
Federal Court of Australia
Decision date
2005-10-07
Before
Siopis J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
REASONS FOR JUDGMENT 1 This is an application made under ss 459G, 459H and 459J of the Corporations Act 2001 (Cth) ('the Act'). The application is for orders setting aside a statutory demand dated 17 February 2005 and served on the plaintiff by the defendant under cover of a letter dated 18 February 2005. Background 2 The plaintiff was engaged in September 2001 by Baulderstone Hornibrook Limited ('Baulderstone') as the formwork contractor for the construction of a building known as the Woodside Building at St George's Terrace in Perth. At all material times, Mr Warren Anderson, was the sole director and company secretary of the plaintiff. 3 The plaintiff entered into a subcontract with the defendant by which the plaintiff hired and purchased certain items of equipment from the defendant. These items of equipment were needed for the purpose of carrying out the plaintiff's contract with Baulderstone. 4 In May 2002, Baulderstone terminated the contract between the plaintiff and Baulderstone. The termination of that contract with Baulderstone had the consequence that the plaintiff breached several of its contracts with its subcontractors including the subcontract with the defendant. 5 The defendant commenced an action against the plaintiff in the District Court of Western Australia on the hire contracts and obtained default judgment against the plaintiff in the sum of $195 554.13. 6 Mr Anderson, on behalf of the plaintiff, agreed with the defendant to pay the judgment debt by instalments of $50 000. Two payments for $50 000 were made by the plaintiff in March 2003 and May 2003. The evidence suggests that these payments were made by Mr Anderson personally. The plaintiff did not make the next payment due under the agreement between the plaintiff and the defendant. The defendant then issued a statutory demand. When the plaintiff did not comply with the statutory demand, the defendant commenced winding up proceedings against the plaintiff in the Supreme Court of Western Australia. 7 Mr Anderson authorised Mr Joe Passione, the Project Manager of the plaintiff to negotiate a settlement of the outstanding debt with the defendant. Mr Passione had a number of meetings with Mr Cornelis Borsboom, one of six directors of the defendant, in the months of December 2003 and January 2004 for this purpose. 8 Mr Passione says that during those discussions he proposed that the plaintiff would assign to the defendant a debt of $48 884 owed to the plaintiff by Brands Construction Pty Ltd ('Brands') in payment of an equal sum owed by the plaintiff to the defendant and that Mr Borsboom agreed. Mr Passione says that there was no discussion as to what would happen if Brands did not pay the debt. Mr Passione deposed that he said that the plaintiff would deliver to the defendant a FH 2002 Holland Formwork Hoist ('the Hoist') in payment of the balance of the outstanding debt after deducting the amount of the assigned debt, and that Mr Borsboom agreed that the defendant would sell the Hoist. Mr Passione further deposed that the Hoist had a market value of $50 000 to $60 000. He says that it was agreed that if the Hoist was sold for an amount which was more than the outstanding balance the excess amount would be repaid to the plaintiff. 9 Mr Passione says that Mr Borsboom agreed that the defendant would discontinue the winding up application. Mr Borsboom does not dispute the substance of the conversation nor that an agreement was entered into with Mr Passione on behalf of the plaintiff but says that the agreement reached was an agreement in principle and was subject to the agreement being documented by both parties' respective solicitors. Mr Passione says that he participated in discussions with Mr Borsboom in early January 2004 about the preparation of a deed, but he says that the purpose of the deed was to record a concluded oral agreement made between himself and Mr Borsboom for the compromise of the debt. 10 In mid January 2004 notice of the assignment of Brands debt was given. The plaintiff sent a notice to the defendant. The plaintiff also delivered the Hoist to the defendant, which the defendant accepted on 13 January 2004. 11 Mr Passione dealt with the plaintiff's solicitors in relation to the preparation of the deed and says that he instructed the solicitors of the terms of the agreement reached with the defendant. 12 The solicitors acting for the plaintiff prepared a draft deed which was referred to as the 'Deed of Settlement'. 13 The draft deed recorded that the plaintiff would assign to the defendant the Brands debt of $48 884, and that the plaintiff would place on consignment with the defendant one FH 2002 Holland Formwork Hoist which the defendant would be entitled to sell. The parties agreed that the Hoist had an indicative market value of $50 000. There was also provision that insofar as the sale of the Hoist exceeded $46 670.13, the defendant was entitled to hold that excess amount on trust until the balance of all monies had been received from Brands under the assigned debt, at which point the defendant would release the monies held on trust to the plaintiff. The draft deed also provided that the defendant would discontinue the winding up proceedings on execution by the parties of the deed. 14 Significantly, the draft deed also contained the following term: '4. Bar This deed may be pleaded in bar to any claim commenced or taken by any party against any other party in respect of the outstanding debt owed or that may be owed from time to time by [the plaintiff] to [the defendant] or any cause of action or other matter connected with the outstanding debt owed or that may be owed from time to time by [the plaintiff] to [the defendant].' 15 Mr Passione approved this draft deed. On 12 January 2004, Mr Borsboom received a facsimile from Mr Passione that enclosed the draft deed and asked for his comments. 16 Mr Borsboom said that he referred the draft deed to the defendant's solicitors who advised him that there should be amendments made to the draft deed. 17 The defendant's solicitors wrote a letter to the plaintiff's solicitors dated 15 January 2004 wherein they proposed various amendments be made to the draft deed. Significantly, the letter from the defendant's solicitors contained the following paragraphs: '3. Clause 4 Bar Clause 4 should be amended to read as follows: "Until such time as: (a) Brands have completed payment of the remaining instalments to the value of $48,884.00 (excluding GST) and (b) Hoist 1 has been sold by [the defendant] to a value exceeding the outstanding balance of the debt (excluding GST) and (c) seven months have expired after the date of the last payment by Brands or after the receipt of funds on the sale of Hoist 1; (This is to preclude any claim being made against [the defendant] by any liquidator or trustee of [the plaintiff] or Brands for repayment of the funds in the event of a possible liquidation of [the plaintiff] or Brands in the relevant period.)' [The defendant] expressly reserves its right to take any lawful proceedings for the recovery of any outstanding balance including but not limited to the issue of further Winding Up proceedings but thereafter this Deed may be pleaded in bar to any claim commenced or etc…" 4. There shall be a new clause 5 to read as follows: "[The defendant] shall not take any steps to recover the outstanding Judgment Debt whilst Brands duly carries out the terms of its Contract as assigned to [the defendant]."