Abigroup Contractors Pty Limited v Sydney Catchment Authority
[2006] NSWCA 282
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2006-03-09
Before
Beazley JA, Ipp JA, Tobias JA, McDougall J
Source
Original judgment source is linked above.
Judgment (52 paragraphs)
Introduction 2 The appellant was the successful contractor for the construction of a spillway at Warragamba Dam. The contract was a lump sum contract under which the appellant bore all risks, including the cost of work not included in the contract but which was necessary to be done to bring the project to completion. It was within the scope of the contract 'risk' clause that additional work might need to be carried out because of site conditions. 3 As it turned out, the appellant was required to undertake additional excavation and refilling work because the rock level, in one area of the site known as Folly Creek, was substantially lower than indicated in the respondent's Concept Design Drawings and detailed specifications. The appellant claimed that it suffered a loss as a result of having to do the extra work and that that loss was caused by the respondent making a representation that it had no plans of an outlet pipe that drained water through an embankment over Folly Creek. There was in fact such a plan. The appellant contended that if it had known of the existence of the plan, further enquiries would have revealed the rock levels, shown in the Concept Design Drawings and detailed specifications, to be seriously flawed. 4 The appellant brought proceedings claiming that the respondent had engaged in misleading and deceptive conduct contrary to s 52 of the Trade Practices Act. The appellant contended that having been induced to enter into the contract by the respondent's misrepresentation which committed it to do significantly more work than was allowed in the lump sum contract, it was entitled to damages, being the cost of doing the additional work, pursuant to s 82 of the Trade Practices Act. Claims for relief were also pleaded under s 87 of the Trade Practices Act and for damages for breach of contract. 5 The proceedings were referred out to a Referee pursuant to Pt 72 r 13 of the Supreme Court Rules on all issues. The Referee found against the appellant on all issues. The appellant applied to the Supreme Court for the rejection of the Report. The respondent cross-motioned for its acceptance. Nicholas J heard those applications and made an Order adopting the Referee's Report. The appellant successfully appealed: see Abigroup Contractors Pty Limited v Sydney Catchment Authority (2004) 208 ALR 630; [2004] NSWCA 270 (Abigroup No 1), and the matter was remitted for rehearing in accordance with the Court's reasons. 6 The remitted applications were heard by McDougall J. His Honour ordered that the Referee's Report be rejected in so far as (a) the Referee had found that the respondent had not engaged in misleading or deceptive conduct and (b) insofar as the Referee found that the appellant had not relied upon the misleading and deceptive conduct. His Honour ordered that the Report otherwise be adopted and ordered judgment for the respondent. 7 The appellant appeals against that part of his Honour's Orders adopting the Report. That gives rise to the damages issue before the Court. The respondent has cross-appealed against that part of the Order rejecting the Report in so far at it related to reliance and causation. The respondent abandoned its cross-appeal relating to the finding against the respondent in respect of misleading and deceptive conduct. 8 The effect of his Honour's judgment was that the appellant had failed before the Referee because it had failed to establish that it had suffered loss. In essence, on his Honour's reasoning, the appellant was required to prove that it had suffered loss on the whole of the contract. It had not done so. 9 The appellant had claimed damages on the basis that it had suffered loss on entering into the contract in circumstances where it was bound under the lump sum contract to do work in Folly Creek that was greater than the work for which it had allowed in its tender. The appellant contended that the appropriate measure of its loss was the actual cost of doing the extra work. That cost, including overheads and margin at a rate of 7.1 per cent, was $7,499,930. The appellant also claimed for the cost of finance (at an agreed rate of 9.5 per cent) plus interest. 10 The appellant further contended that, as a result of having to undertake a greater scope of work then that allowed for in its tender, it was delayed in the completion of the work. It claimed damages suffered as a result of the delay and also seeks to avoid the payment of liquidated damages for delay as required by the contract. 11 The respondent accepts that if, as a matter of principle, the appellant is entitled to damages on the basis of being entitled to a discrete loss on the additional Folly Creek work, then, subject to the issue of causation raised on the Notice of Contention, the appellant is entitled to succeed on its claim. The respondent contends, however, that that basis for claiming damages is not open to it as a matter of law and that the appellant is only entitled to damages if it proves a loss on the whole of the contract. It submits that the appellant failed to prove this case. 12 As the question of reliance and causation raised by the respondent on the cross-appeal is logically anterior to the question of damages, it will be convenient to deal with that issue first. Before doing so it is appropriate to refer to the nature of the appeal from a Pt 72 r 13 application. It is also necessary to provide a brief background of the facts.