He said that the 1983 survey was approximate only and undertook to acquire a rough volume of material available in the quarry. It was undertaken using a compass for orientation and electronic measurement for distance and he estimated the accuracy of the survey to be plus or minus 3-4 metres.
34 In his affidavit of 28 September 2001 Mr Thompson said that he had been requested by the Council's solicitors to mark out a specific area of the quarry. He was provided with the aerial photograph of the quarry dated 19 January 1990 which showed the tree line of the quarry marked in red and "part of the same aerial photograph overlaid with an earlier photograph under the heading of 'Aerial photography 15/08/97 overlaid with Aerial Photography from 19/01/90' (sic)". The first photograph became annexure "A" and the second annexure "B". He placed fourteen survey marks on the site on 17 August 2001 which he said showed the approximate position of the red line on attachment "A". Annexed and marked "C" was a sketch plan overlay which could be superimposed onto annexure "A" to show the position of the survey marks placed on the site as they related to this aerial photograph. Annexure "D" was a composite plan combining the overlay and the 1990 photograph.
35 Mr Thompson described the methodology adopted to locate the pegs on the site as follows:
"(a) A field survey was carried out to locate the two bridges and the section of Palmwoods Road in between these bridges clearly visible features on 1990 aerial map and adjacent to the quarry;
(b) this field survey data was then scaled down to best fit the 1990 photograph using the computer surveying software packaging GEOCOMP;
(c) this enabled the position of the cleared area from the 1990 aerial photograph to be related by measurement to the identifiable features on the photograph, namely the bridges and the road;
(d) the position of the line defining the cleared area was then scaled in relation to the two bridges and the road formation. This scaled position was then input into the surveying software package; and
(e) the new file contains the existing bridge locations, road formation and line defining the cleared area was then re-scaled to ground distances for site markings."
36 This led to the calculation of the 6,500m². As his Honour said Mr Thompson acknowledged that the position of the pegs on site were approximate positions only and a margin of error of approximately 5 metres radius around each peg should be adopted. The area calculation was also an estimate and he adopted a 15 per cent margin of error for this figure.
37 Mr Loomes' 2001 survey plan showed "area quarry site by me and Archibald about 8,800m²." Another area to the south east of about 700m² was identified as "slip". Mr Loomes said that Mr Archibald had indicated that area to him. He was asked about the "areas on the southern end of the overall scar but within the dotted line" on the plan, that is to say the area excluding the slip and the area of quarry and said: "Well that's an area of some substantial trees but mostly regrowth. I don't - haven't been - hasn't been quarried to any great extent recently, if at all." Asked about the 8,800²m area, which excluded the area of the slip and "those access roads and so on at the southern end" he said: "it was just the area of the excavation area."
38 Under cross-examination Mr Loomes was asked by the trial Judge whether there was anything that made him believe that the area of the slip was being "mined, used for a quarry". He said: "I think there has been work done on the slip area since it's been slip but I have no knowledge really of what occurred and how it occurred. I think it might have been cleaned up. There is a track up there, a machinery track."
39 In his oral evidence Mr Loomes said this about the 1983 survey:
"Well it was a survey. We were instructed apparently by the council - it's a bit long ago for me to remember but we were instructed by the council I understand to work out a very rough volume of the material that was available in the quarry site and we did some contours, some very rough contours, some very rough levels, in order to try to do that. We abandoned that incidentally because we couldn't determine exactly what the final profile of the quarry was going to be so we never actually came to conclusion with that survey but that's what we anticipated it to be, a volume survey - a volumetric survey rather than a boundary survey."
40 In the course of cross-examination by the solicitor for the Council, Mr Loomes said that the tree which had been marked at the southern point of the quarry site in the 2001 survey plan was about where his colleague had marked the top of the quarry back in 1983.
41 Mr Loomes said this about Mr Thompson's affidavit:
"8. In paragraph 3 of the Thompson Affidavit certain photographs upon which Scott Thompson has relied are referred to. Photographs are in general inherently distorted by the fact they provide a perspective view only and are only 'scale' stable at the centre point of the photograph and cannot be used as a mapping or measuring tool unless rectified by a dedicated computer software programme or 3D photogrammetric transformation. Both these procedures require control points on the image to be co-ordinated in 3 dimensions. Areas to be mapped which have significant height differences, such as a quarry site, are most affected by distortion.
9. In order to provide aerial photographs which can be made relatively distortion free and used as a measuring tool, it is necessary that:
(a) the photography be dedicated to the purpose of the project - not a snap shot and be site specific;
(b) be taken from the vertical;
(c) be taken by a quality lens that has its calibration qualities known;
(d) have fiducial marks on the image, particularly the centre point or Principal Point; and
(e) be taken by a quality camera using fine film emulsion to allow better definition.
I am not aware of any of the above parameters being applied to these photographs (or any photocopies of the photographs).
10. In paragraph 2 of the Thompson Affidavit it is stated that he has been asked to mark out a specific area of the quarry. He has been instructed to mark lines depicted on the photographs and has attempted to rectify them by measuring between just two control points and therefore in one direction only, being basically east-west. No attempt has been made by him to provide a north-south control and the 'computer' programme he referred to in paragraph 7(b) of the Thompson affidavit is merely surveying and engineering based and is not capable of rectifying images. He does not indicate whether he applied a factor because of substantial height differences on the site and I believe his estimate of error quotient of + 5 metres is probably a minimum.
11. Without benefit of the history of the photographs it is my opinion that they generally portray a pictorial reference only and cannot be used as a measuring tool."
42 Mr Thompson was asked this in cross-examination:
"ATKIN: Mr Thompson I take it you have read Mr Loomes' affidavit? A. Yes.
Q. And you're aware of the matters that he raises in comment about your process? A. Yes.
Q. Mr Thompson the overlaying of the photographs that you've done, referred to in your affidavit, that's A and B, did you do the overlay or did someone else do that overlay-- A. This annexure?
Q. Yes? A. That one?
Q. Yes? A. I overlaid them and then they were colour photocopied down in the photocopy shop.
Q. The photographs that were taken, the original photographs A and B, that is the one taken in 1990 and the one taken in 1997, were you able to plot the centre point of those two photographs? A. No.
Q. Did you rectify the two photographs, in other words try to-- A. No.
Q. -reduce them to the same scale and the same-- A. No.
Q. You've located the two bridges and you've given some evidence about that and you've measured the line which is approximately an east west line? A. Yes.
Q. And you said that you couldn't do a north south line because you couldn't identify any particular reference points for that north south line? A. Well not reliable points, yeah, there's very - a lot of trees.
Q. Now you then said that the field survey data which you took, I assume, was scaled down to best fit the 1990 photograph and the way you did that was to use a geo comp program? A. Yes correct.
Q. That's a program that doesn't rectify the images? A. No definitely not.
Q. What's that program generally used for? A. It's just a surveying based software used for--
Q. Engineering or? A. It does have an engineering aspect to it.
Q. Yes? A. Just used for normal calculations and surveying associated types of number crunching.
Q. Have you allowed in your calculations anything for the height differences for example the level of the road and the top of the quarry? A. No.
Q. It's a fairly significant difference in height though isn't it, between the two points? A. Quite a deal, yes.
Q. You said in your affidavit that you had a margin of error of approximately five metre radius around each peg should be adopted. The pegs you're referring to, are they the points along the red line? A. They're the points that I placed on the site.
Q. That you placed on the site which is shown on your-- A. Shown on that overlay, annexure C I think.
Q. On the overlay? A. It appears on all of the plans. It's the line that I physically marked on the side.
Q. Yes I understand, yes, thank you. And you said you adopted a 15 per cent margin of error for this figure. When you say this figure, are you referring to the overall area calculations? A. Yeah.
Q. Or are you talking about the margin of error or some other figure? A. That was the area calculation.
Q. So the total area calculation for you is, that you've made, is 6,500 square metres? A. Yes that's correct.
Q. And there's a 15 per cent margin of error, that's plus or minus? A. Plus or minus.
Q. Thank you. Mr Loomes in paragraph 9 of his affidavit, provides certain comments as to how you would make distortion free aerial photographs? A. Yes.
Q. And he listed a number of things. Do you disagree with those suggestions? A. No not at all."
43 On its face, and in the light of what was put to Mr Loomes in cross-examination, it would be hard to deny that in August 2001 the excavated area of the quarry was the 8,800m² shown in his survey plan. This is by far the surest foundation for determining whether that excavated area included any lateral expansion of the excavated site which had taken place after 1990 as the trial Judge had found.
44 The survey plan is, of course, inconsistent with Dr Button's conclusion that by 1995 11,100m² was being quarried unless the area determined by Dr Button included the slip area and some other unspecified areas where there were no trees but no quarrying.
45 The 1997 aerial photograph (Exhibit B) showed a cleared area which on its face appears to accord with Mr Loomes' quarry site area and slip area. The slippage may extend further south but that is difficult to tell.
46 Another exhibit was Exhibit K prepared by Mr Thompson. It purported to overlay Mr Loomes' survey to demonstrate graphically, as I understand it, that while in 2001 the excavated area was 8,800m², in 1990 it was the 6,500m² calculated by Mr Thompson. Of course this calculation is inconsistent with Dr Button's calculation that by that time the quarry area was between 8,500 and 8,700m². Furthermore, the exhibit is suspect because it depends upon the work of Mr Thompson which had been criticised by Mr Loomes and seems to show the 1990 excavation work as extending north of the northern boundary road, Palmswood Road. Furthermore, there is the evidence from Mr Loomes that in 1983 the quarrying had extended as far south as the tree which is well south of the southern line suggested by Mr Thompson.
47 In his reasons for judgment Cowdroy J said that to establish that the area of the quarry had "substantially increased" since 11 September 1987 the Council relied upon Dr Button's evidence. He said that Dr Button used "commercially available satellite imagery of 'infra-red reflectivity' to determine whether there had been any lateral expansion of the quarry since February 1986." Dr Button had interpreted the results of satellite imagery of the area which had been recorded by satellite and processed by computer.
"Using such data, he concluded that there were two periods of significant expansion in the area of the quarry. The first was during the period between January and September 1990 in which the shape of the quarry 'grew from an almost triangular shape to a regular shape trapezoid to quadrilateral plane figure of which two sides are parallel'. Dr Button said that the area of the quarry increased mainly towards the south east."
48 His Honour next referred to the second period of expansion which Dr Button considered occurred between 1993 and 1995 "when there was a considerable increase in the land cleared for the quarry area which is unmistakable upon visual as well as statistical analysis." This area of expansion was also in a south-south-easterly direction. The trial Judge added: "Significantly, Dr Button's assessment did not rely upon personal observation or assessment. Rather, Dr Button's conclusions were based upon the result of calculations by computer of the data derived from satellite observation." That was the trial Judge's description of the complex technical evidence given by Dr Button. His Honour made no mention of extensive cross-examination of Dr Button directed to the limitations and unreliability of his conclusions.
49 For example, of the 29 per cent expansion of the quarry derived from the difference between 8,600m² and 11,100m² said to have occurred and to have been the major change between 1993 and 1995, Dr Button said:
"So my clear conclusion is most of that 29 per cent, by far the majority, is due to expansion of the quarry. And in a particular direction, it is not just expansion outwards, it is virtually solely expansion in the south south easterly direction."
50 That was an expansion into what was described by Mr Loomes as the slip area. Dr Button had never been to the site. He accepted in cross-examination that if the area had been the subject of a landslip his methods did not establish that the apparently cleared area was actively working as a quarry.
51 I have quoted paragraphs 16, 17 and 18, the parts of the reasons for judgment in which the trial Judge sought to explain the finding contained in paragraph 19. The trial Judge, with due respect to him, never came to grips with the technical arguments supporting or throwing doubt upon the expert evidence. Mr Thompson had not concluded that the cleared area was extended by 6,500m². Had he done so, as his Honour thought, that conclusion was irreconcilable with what Dr Button said. The impression I have is that the trial Judge regarded it as sufficient that he found there was some expansion. But, as I have indicated, the Council was seeking injunctive relief in the form of an order restraining Mr Archibald from using or causing or permitting the use of that part of the land outside the area actually physically used immediately before 3 February 1986 for the purposes of an extractive industry unless and until consent had been obtained.
52 It is trite law that an injunction should not be granted unless couched in completely unambiguous language whereby the recipient can know exactly what that recipient is obliged to do or may not do; see generally Meagher, Gummow and Lehane, Equity Doctrines and Remedies, 4th ed, page 813. Such relief could only be granted if his Honour defined with precision the area of quarrying said to extend beyond the area of permitted use. This in turn required the trial Judge to choose, if he accepted any of the experts' evidence on this, which he accepted and why. With due respect, simply to recite passages of inconsistent evidence, in one case entirely misunderstood, and then make a finding, is not sufficient. Further it places this Court in the invidious position of being asked itself to weigh that evidence and make findings about it. This difficulty raises the question of whether this Court had any choice but to send the matter back for re-trial.
53 In Moylan & Ors v Nutrasweet Company & Ors [2000] NSWCA 337, in a judgment with which both Beazley and Giles JJA agreed, and also in Mistral International Pty Ltd (formerly known as Ringgrip Pty Ltd) v Polstead Pty Ltd [2002] NSWCA 321, in a judgment with which both Meagher and Beazley JJA agreed, I referred to what was said in the English Court of Appeal in Flannery v Halifax Estate Agencies Ltd [2000] 1 WLR 377 and Eckersley v Binnie [1988] 18 ConLR 1 at 77-8. In Moylan at para 64 the trial Judge was criticised for saying:
"I have had the advantage not only of hearing the various witnesses give evidence but also of seeing the way in which they reacted to the questions that they were asked. Having done so, I prefer the expert evidence that was given for the defendants to that which was given for the plaintiff."
54 Where a dispute, such as this one, involves something in the nature of an intellectual exchange with reasons and analysis advanced on either side, the parties are entitled to have the judge enter into the issues canvassed before the Court and to an explanation by the judge as to why the judge prefers one case over the other. This is particularly so where there is disputed expert evidence. In the present case, the parties were entitled to be told if Dr Button's estimates were to be accepted, on what basis they were to be accepted, in preference to those of Mr Loomes and Mr Thompson. This had to be done if the Court was properly to perform the duty of stating with certainty the extent to which the respondent was entitled to rely upon continued use.
55 However, like Meagher JA, I am persuaded that the evidence of Mr Loomes, largely unchallenged, as to the area of excavation by August 2001, had to be accepted. That evidence demonstrated that there had been no expansion in the quarry to the south since 1983. What may have been treated, particularly by Dr Button who had never visited the site, to an expansion was an area denuded of trees by a landslide.
56 Although some belated attempt was made on behalf of the Council to rely on the fact that in the course of re-conditioning the slip area as required by the Department of Mineral Resources and Mining some material had been extracted and sold - the extent to which that occurred, and where it occurred, is unknown and there was no suggestion that it was continuing at the time these proceedings were begun. As I have said the trial Judge made no finding about it.
57 In my opinion, the evidence of both Dr Button and Mr Thompson should have been rejected as unreliable and inconsistent with Mr Loomes' unchallenged evidence. I do not understand from any of the material how it could be said that Mr Loomes "could not dispute the conclusion of Dr Button and Mr Thompson that there had been a major expansion of the quarry." This comment is unfounded.
58 The Council filed a notice of contention that the decision and orders of the trial Judge should be affirmed on grounds other than that the expansion of the quarry may have occupied the entire area of 6,500m². These grounds were that the area was the difference between the area of the quarry on 3 February 1986 and the area as at the date of commencement of the proceedings. It was contended that Cowdroy J should have held that the expansion was the area beyond that which was used for the purposes of the quarry on 3 February 1986 and that the cleared area of the quarry was extended by the amount shown in the aerial photograph taken on 19 January 1990 compared to that taken on 15 August 1997 (plus or minus 15 per cent). In my opinion, such a finding is not open on the evidence before the Court particularly having regard to Mr Loomes' evidence, which was uncontradicted and unchallenged.