### sec.319 Termination of contracts
The detention centre contracts are terminated.
The State does not incur liability because of the termination.
In this section—
detention centre contracts means the following contracts entered into between the Queensland Corrective Services Commission and Queensland Corrections—
a contract dated 29 August 1997 for the operation and management of the John Oxley Youth Detention Centre;
a contract dated 29 August 1997 for the operation and management of the Sir Leslie Wilson Youth Detention Centre;
a contract dated 29 August 1997 for the operation and management of the Cleveland Youth Detention Centre.
s 319 ins 1998 No. 39 s 68
(sec.319-ssec.1) The detention centre contracts are terminated.
(sec.319-ssec.2) The State does not incur liability because of the termination.
(sec.319-ssec.3) In this section— detention centre contracts means the following contracts entered into between the Queensland Corrective Services Commission and Queensland Corrections— a contract dated 29 August 1997 for the operation and management of the John Oxley Youth Detention Centre; a contract dated 29 August 1997 for the operation and management of the Sir Leslie Wilson Youth Detention Centre; a contract dated 29 August 1997 for the operation and management of the Cleveland Youth Detention Centre.
- (a) a contract dated 29 August 1997 for the operation and management of the John Oxley Youth Detention Centre;
- (b) a contract dated 29 August 1997 for the operation and management of the Sir Leslie Wilson Youth Detention Centre;
- (c) a contract dated 29 August 1997 for the operation and management of the Cleveland Youth Detention Centre.