### sec.576D Injury data for construction projects
WorkCover may—
compile injury data for a construction project, to the extent the data relates to relevant contractors for the construction project who are not self-insurers; and
give the injury data to the principal contractor for the construction project.
The Regulator may, on the request of the principal contractor for the construction project, give the principal contractor injury data for the construction project, to the extent the data relates to relevant contractors who are self-insurers.
In this section—
injury data , for a construction project, means the following information about each relevant contractor for the construction project—
the relevant contractor’s name;
the number and type of injuries sustained by workers on the project for which applications for compensation have been made under section 132 ;
the date the injuries were sustained;
the address of the site at which the injuries were sustained.
s 576D ins 2011 No. 18 s 408
amd 2013 No. 52 s 114 sch 2
(sec.576D-ssec.1) WorkCover may— compile injury data for a construction project, to the extent the data relates to relevant contractors for the construction project who are not self-insurers; and give the injury data to the principal contractor for the construction project.
(sec.576D-ssec.2) The Regulator may, on the request of the principal contractor for the construction project, give the principal contractor injury data for the construction project, to the extent the data relates to relevant contractors who are self-insurers.
(sec.576D-ssec.3) In this section— injury data , for a construction project, means the following information about each relevant contractor for the construction project— the relevant contractor’s name; the number and type of injuries sustained by workers on the project for which applications for compensation have been made under section 132 ; the date the injuries were sustained; the address of the site at which the injuries were sustained.
- (a) compile injury data for a construction project, to the extent the data relates to relevant contractors for the construction project who are not self-insurers; and
- (b) give the injury data to the principal contractor for the construction project.
- (a) the relevant contractor’s name;
- (b) the number and type of injuries sustained by workers on the project for which applications for compensation have been made under section 132 ;
- (c) the date the injuries were sustained;
- (d) the address of the site at which the injuries were sustained.