### sec.384 Preparation and submission of flood event interim report
This section applies if—
a flood event relating to a referable dam to which this part applies happens; and
the chief executive considers the flood event is likely to continue for at least 1 month.
The chief executive may give the owner of the dam a notice requiring the owner to—
prepare a report (a flood event interim report ) under this division; and
give it to the chief executive within 10 business days after receiving the notice.
If the chief executive gives the owner of the dam a notice under subsection (2) , the owner must comply with the notice unless the owner has a reasonable excuse.
Maximum penalty—1665 units.
s 384 ins 2012 No. 29 s 32
(sec.384-ssec.1) This section applies if— a flood event relating to a referable dam to which this part applies happens; and the chief executive considers the flood event is likely to continue for at least 1 month.
(sec.384-ssec.2) The chief executive may give the owner of the dam a notice requiring the owner to— prepare a report (a flood event interim report ) under this division; and give it to the chief executive within 10 business days after receiving the notice.
(sec.384-ssec.3) If the chief executive gives the owner of the dam a notice under subsection (2) , the owner must comply with the notice unless the owner has a reasonable excuse. Maximum penalty—1665 units.
- (a) a flood event relating to a referable dam to which this part applies happens; and
- (b) the chief executive considers the flood event is likely to continue for at least 1 month.
- (a) prepare a report (a flood event interim report ) under this division; and
- (b) give it to the chief executive within 10 business days after receiving the notice.