### sec.400 Compliance with approved baseline assessment plan
A resource tenure holder must, unless the holder has a reasonable excuse—
undertake a baseline assessment of a water bore in a priority area for the tenure on or before the day stated in the baseline assessment timetable in the baseline assessment plan for the area of the resource tenure; and
comply with each condition of its approved baseline assessment plan.
Maximum penalty—500 penalty units.
s 400 prev s 400 ins 2006 No. 59 s 82
amd 2007 No. 57 s 88
om 2008 No. 34 s 714
pres s 400 ins 2010 No. 53 s 195
sub 2014 No. 64 s 104
- (a) undertake a baseline assessment of a water bore in a priority area for the tenure on or before the day stated in the baseline assessment timetable in the baseline assessment plan for the area of the resource tenure; and
- (b) comply with each condition of its approved baseline assessment plan.