### sec.325 Temporary relaxation from s 59 measuring requirements for small site
Until the end of 30 June 2021, the operator of a small site is not obliged to measure waste as required under section 59 if—
the operator has, before the commencement, given the chief executive written notice of a proposed alternative methodology for measuring and recording waste at the site; and
the notice mentioned in paragraph (a) identifies the site and includes details of the proposed alternative methodology; and
the proposed alternative methodology enables the operator to fairly work out the total of the waste levy amount owing to the chief executive on waste delivered, or moved from stockpile to landfill, at the site; and
the operator is implementing the alternative methodology in accordance with its terms.
s 325 ins 2019 No. 2 s 19
- (a) the operator has, before the commencement, given the chief executive written notice of a proposed alternative methodology for measuring and recording waste at the site; and
- (b) the notice mentioned in paragraph (a) identifies the site and includes details of the proposed alternative methodology; and
- (c) the proposed alternative methodology enables the operator to fairly work out the total of the waste levy amount owing to the chief executive on waste delivered, or moved from stockpile to landfill, at the site; and
- (d) the operator is implementing the alternative methodology in accordance with its terms.