### sec.27A Lapsing of declaration if EIS required
This section applies to a coordinated project if an EIS is required for the project.
The declaration for the project lapses if, within 18 months of the terms of reference being finalised, the Coordinator-General has not, under section 34A (1) (b) , accepted a draft EIS for the project as the final EIS.
Despite subsection (2) , if before the declaration lapses, the Coordinator-General gives written notice to the proponent stating a later time for the declaration to lapse, the declaration does not lapse until the later time.
s 27A ins 2005 No. 57 s 21
amd 2012 No. 43 s 293
sub 2014 No. 40 s 31
(sec.27A-ssec.1) This section applies to a coordinated project if an EIS is required for the project.
(sec.27A-ssec.2) The declaration for the project lapses if, within 18 months of the terms of reference being finalised, the Coordinator-General has not, under section 34A (1) (b) , accepted a draft EIS for the project as the final EIS.
(sec.27A-ssec.3) Despite subsection (2) , if before the declaration lapses, the Coordinator-General gives written notice to the proponent stating a later time for the declaration to lapse, the declaration does not lapse until the later time.