### sec.99BRCZ Refund if water approval ceases
This section applies if—
a water approval subject to an additional payment condition no longer has effect; and
a payment has been made under the condition; and
construction of the infrastructure the subject of the condition has not substantially started before the water approval no longer has effect.
The distributor-retailer must refund the payer any part of the payment the distributor-retailer has not spent, or contracted to spend, on designing and constructing the infrastructure.
Timing of the refund is subject to terms agreed between the payer and distributor-retailer.
s 99BRCZ ins 2014 No. 36 s 45
(sec.99BRCZ-ssec.1) This section applies if— a water approval subject to an additional payment condition no longer has effect; and a payment has been made under the condition; and construction of the infrastructure the subject of the condition has not substantially started before the water approval no longer has effect.
(sec.99BRCZ-ssec.2) The distributor-retailer must refund the payer any part of the payment the distributor-retailer has not spent, or contracted to spend, on designing and constructing the infrastructure.
(sec.99BRCZ-ssec.3) Timing of the refund is subject to terms agreed between the payer and distributor-retailer.
- (a) a water approval subject to an additional payment condition no longer has effect; and
- (b) a payment has been made under the condition; and
- (c) construction of the infrastructure the subject of the condition has not substantially started before the water approval no longer has effect.