### sec.99BRCW Restriction if connection completely in connection area and future connection area
This section applies for an additional payment condition imposed by a distributor-retailer for a connection completely inside the connection area and future connection area.
The additional payment condition may require a payment only as follows—
for trunk infrastructure to be provided earlier than planned in the water netserv plan—the additional establishment cost that would be incurred by the distributor-retailer in providing the trunk infrastructure earlier than planned;
for infrastructure associated with a different type, scale or intensity of future development from that assumed in the water netserv plan—the establishment cost of any additional trunk infrastructure made necessary by the connection.
s 99BRCW ins 2014 No. 36 s 45
amd 2014 No. 64 s 51H
(sec.99BRCW-ssec.1) This section applies for an additional payment condition imposed by a distributor-retailer for a connection completely inside the connection area and future connection area.
(sec.99BRCW-ssec.2) The additional payment condition may require a payment only as follows— for trunk infrastructure to be provided earlier than planned in the water netserv plan—the additional establishment cost that would be incurred by the distributor-retailer in providing the trunk infrastructure earlier than planned; for infrastructure associated with a different type, scale or intensity of future development from that assumed in the water netserv plan—the establishment cost of any additional trunk infrastructure made necessary by the connection.
- (a) for trunk infrastructure to be provided earlier than planned in the water netserv plan—the additional establishment cost that would be incurred by the distributor-retailer in providing the trunk infrastructure earlier than planned;
- (b) for infrastructure associated with a different type, scale or intensity of future development from that assumed in the water netserv plan—the establishment cost of any additional trunk infrastructure made necessary by the connection.