### sec.99BRCV Content of additional payment condition
An additional payment condition must state all of the following—
why it was imposed;
the amount of the payment to be made under the condition;
details of the trunk infrastructure for which the payment is required;
when the amount becomes payable (the payment time );
that the applicant may, instead of making the payment, elect to provide part or all of the trunk infrastructure;
if the applicant so elects—
any requirements for providing the trunk infrastructure; and
when it must be provided.
Unless the applicant and the distributor-retailer otherwise agree, the payment time is—
if the trunk infrastructure is necessary to service the premises—by the day the connection, or work associated with the connection, starts; or
if the trunk infrastructure is not necessary to service the premises—
for a connection associated with reconfiguring a lot—when the network connection is made; or
for other connections—when the property service connection is made.
s 99BRCV ins 2014 No. 36 s 45
(sec.99BRCV-ssec.1) An additional payment condition must state all of the following— why it was imposed; the amount of the payment to be made under the condition; details of the trunk infrastructure for which the payment is required; when the amount becomes payable (the payment time ); that the applicant may, instead of making the payment, elect to provide part or all of the trunk infrastructure; if the applicant so elects— any requirements for providing the trunk infrastructure; and when it must be provided.
(sec.99BRCV-ssec.2) Unless the applicant and the distributor-retailer otherwise agree, the payment time is— if the trunk infrastructure is necessary to service the premises—by the day the connection, or work associated with the connection, starts; or if the trunk infrastructure is not necessary to service the premises— for a connection associated with reconfiguring a lot—when the network connection is made; or for other connections—when the property service connection is made.
- (a) why it was imposed;
- (b) the amount of the payment to be made under the condition;
- (c) details of the trunk infrastructure for which the payment is required;
- (d) when the amount becomes payable (the payment time );
- (e) that the applicant may, instead of making the payment, elect to provide part or all of the trunk infrastructure;
- (f) if the applicant so elects— (i) any requirements for providing the trunk infrastructure; and (ii) when it must be provided.
- (i) any requirements for providing the trunk infrastructure; and
- (ii) when it must be provided.
- (i) any requirements for providing the trunk infrastructure; and
- (ii) when it must be provided.
- (a) if the trunk infrastructure is necessary to service the premises—by the day the connection, or work associated with the connection, starts; or
- (b) if the trunk infrastructure is not necessary to service the premises— (i) for a connection associated with reconfiguring a lot—when the network connection is made; or (ii) for other connections—when the property service connection is made.
- (i) for a connection associated with reconfiguring a lot—when the network connection is made; or
- (ii) for other connections—when the property service connection is made.
- (i) for a connection associated with reconfiguring a lot—when the network connection is made; or
- (ii) for other connections—when the property service connection is made.