### sec.170Q Duration of declaration
A declaration of a monopoly water supply activity starts to operate on—
the day notice of the decision to declare the activity is published in the gazette; or
if a later day of operation is stated in the notice—the later day.
A declaration of a monopoly water supply activity continues in operation until its expiry date, unless it is earlier revoked.
s 170Q ins 2000 No. 15 s 39
(sec.170Q-ssec.1) A declaration of a monopoly water supply activity starts to operate on— the day notice of the decision to declare the activity is published in the gazette; or if a later day of operation is stated in the notice—the later day.
(sec.170Q-ssec.2) A declaration of a monopoly water supply activity continues in operation until its expiry date, unless it is earlier revoked.
- (a) the day notice of the decision to declare the activity is published in the gazette; or
- (b) if a later day of operation is stated in the notice—the later day.