### sec.295 Request for application of superseded planning scheme
This section applies if—
a request for the application of a superseded planning scheme under the old Act has been made but not decided before the commencement; and
after the commencement—
the local government is taken to have agreed to the request under the old Act, section 96(5); or
the local government gives a written notice under the old Act, section 97, agreeing to the request.
Section 29(9) and (10) applies to the agreement made, or taken to have been made, by the local government.
For dealing with applications, including requests, that are made but not decided before the commencement, see section 288.
However, if the agreement relates to a request to accept a request for compliance assessment for development, section 29(9) and (10) applies as if the agreement were an agreement to accept a development application for the development.
(sec.295-ssec.1) This section applies if— a request for the application of a superseded planning scheme under the old Act has been made but not decided before the commencement; and after the commencement— the local government is taken to have agreed to the request under the old Act, section 96(5); or the local government gives a written notice under the old Act, section 97, agreeing to the request.
(sec.295-ssec.2) Section 29(9) and (10) applies to the agreement made, or taken to have been made, by the local government. For dealing with applications, including requests, that are made but not decided before the commencement, see section 288.
(sec.295-ssec.3) However, if the agreement relates to a request to accept a request for compliance assessment for development, section 29(9) and (10) applies as if the agreement were an agreement to accept a development application for the development.
- (a) a request for the application of a superseded planning scheme under the old Act has been made but not decided before the commencement; and
- (b) after the commencement— (i) the local government is taken to have agreed to the request under the old Act, section 96(5); or (ii) the local government gives a written notice under the old Act, section 97, agreeing to the request.
- (i) the local government is taken to have agreed to the request under the old Act, section 96(5); or
- (ii) the local government gives a written notice under the old Act, section 97, agreeing to the request.
- (i) the local government is taken to have agreed to the request under the old Act, section 96(5); or