### sec.133 Extra payment conditions for development outside PIA
An extra payment condition that a local government imposes for development completely or partly outside the PIA may require the payment of—
the establishment cost of trunk infrastructure that is—
made necessary by the development; and
if the local government’s planning scheme indicates the premises are part of an area intended for future development for purposes other than rural or rural residential purposes—necessary to service the rest of the area; and
either or both of the following establishment costs of any temporary trunk infrastructure—
costs required to ensure the safe or efficient operation of infrastructure needed to service the development;
costs made necessary by the development; and
any decommissioning, removal and rehabilitation costs of the temporary infrastructure; and
the maintenance and operating costs for up to 5 years of the infrastructure and temporary infrastructure as stated in paragraphs (a) and (b) .
- (a) the establishment cost of trunk infrastructure that is— (i) made necessary by the development; and (ii) if the local government’s planning scheme indicates the premises are part of an area intended for future development for purposes other than rural or rural residential purposes—necessary to service the rest of the area; and
- (i) made necessary by the development; and
- (ii) if the local government’s planning scheme indicates the premises are part of an area intended for future development for purposes other than rural or rural residential purposes—necessary to service the rest of the area; and
- (b) either or both of the following establishment costs of any temporary trunk infrastructure— (i) costs required to ensure the safe or efficient operation of infrastructure needed to service the development; (ii) costs made necessary by the development; and
- (i) costs required to ensure the safe or efficient operation of infrastructure needed to service the development;
- (ii) costs made necessary by the development; and
- (c) any decommissioning, removal and rehabilitation costs of the temporary infrastructure; and
- (d) the maintenance and operating costs for up to 5 years of the infrastructure and temporary infrastructure as stated in paragraphs (a) and (b) .
- (i) made necessary by the development; and
- (ii) if the local government’s planning scheme indicates the premises are part of an area intended for future development for purposes other than rural or rural residential purposes—necessary to service the rest of the area; and
- (i) costs required to ensure the safe or efficient operation of infrastructure needed to service the development;
- (ii) costs made necessary by the development; and