### sec.97 Taking proposed action
Proposed action under section 96 may be taken only if—
the stated period under section 96 has ended; and
either—
the holder has not made an appropriate petroleum lease application under section 96 ; or
any appropriate lease application under section 96 made by the holder has been refused; and
the Minister has considered any submissions lodged by the holder within the period.
The decision does not take effect until the holder is given an information notice about the decision.
A refusal of the application takes effect at end of the appeal period for the decision to refuse.
s 97 amd 2011 No. 2 s 121
(sec.97-ssec.1) Proposed action under section 96 may be taken only if— the stated period under section 96 has ended; and either— the holder has not made an appropriate petroleum lease application under section 96 ; or any appropriate lease application under section 96 made by the holder has been refused; and the Minister has considered any submissions lodged by the holder within the period.
(sec.97-ssec.2) The decision does not take effect until the holder is given an information notice about the decision.
(sec.97-ssec.3) A refusal of the application takes effect at end of the appeal period for the decision to refuse.
- (a) the stated period under section 96 has ended; and
- (b) either— (i) the holder has not made an appropriate petroleum lease application under section 96 ; or (ii) any appropriate lease application under section 96 made by the holder has been refused; and
- (i) the holder has not made an appropriate petroleum lease application under section 96 ; or
- (ii) any appropriate lease application under section 96 made by the holder has been refused; and
- (c) the Minister has considered any submissions lodged by the holder within the period.