### sec.242 Continuing effect of existing approvals for waterway barrier works
This section applies to an approval to build or raise a waterway barrier works—
given under the unamended Act before the commencement of this section; and
in force immediately before the commencement.
From the commencement, the approval has effect as if—
the approval were a development permit for operational works, for which the chief executive was the assessment manager; and
any direction given, under section 116 of the unamended Act , in relation to the approval were a condition of the development permit; and
the currency period for the development permit started on the day the approval was given and ends on the day 2 years after the approval was given.
s 242 prev s 242 exp 27 January 1995 (see s 242(2))
pres s 242 ins 2003 No. 82 s 44
amd 2009 No. 36 s 872 sch 2 ; 2016 No. 27 s 258
(sec.242-ssec.1) This section applies to an approval to build or raise a waterway barrier works— given under the unamended Act before the commencement of this section; and in force immediately before the commencement.
(sec.242-ssec.2) From the commencement, the approval has effect as if— the approval were a development permit for operational works, for which the chief executive was the assessment manager; and any direction given, under section 116 of the unamended Act , in relation to the approval were a condition of the development permit; and the currency period for the development permit started on the day the approval was given and ends on the day 2 years after the approval was given.
- (a) given under the unamended Act before the commencement of this section; and
- (b) in force immediately before the commencement.
- (a) the approval were a development permit for operational works, for which the chief executive was the assessment manager; and
- (b) any direction given, under section 116 of the unamended Act , in relation to the approval were a condition of the development permit; and
- (c) the currency period for the development permit started on the day the approval was given and ends on the day 2 years after the approval was given.