### sec.176 Fee for changing anniversary day applications
For section 316L (2) of the Act , the fee payable for an anniversary changeover application for an environmental authority is worked out using the following formula—
where—
F is the amount of the fee.
U is 358.70 fee units.
A is the amount of the annual fee for the environmental authority.
N is the number of days in the interim year.
In this section—
anniversary changeover application , for an environmental authority, means an application under section 316L of the Act to change the anniversary day for the authority to a new day.
interim year , for a proposed change of anniversary day, means the period—
starting on the old anniversary day for the environmental authority; and
ending on the new anniversary day in the following year after the proposed change.
If the old anniversary day was 1 June and the new anniversary day is 1 July, the period will be 31 days.
s 176 amd 2020 SL No. 110 s 9 ; 2021 SL No. 90 s 8 ; 2022 SL No. 17 s 9
(sec.176-ssec.1) For section 316L (2) of the Act , the fee payable for an anniversary changeover application for an environmental authority is worked out using the following formula— where— F is the amount of the fee. U is 358.70 fee units. A is the amount of the annual fee for the environmental authority. N is the number of days in the interim year.
(sec.176-ssec.2) In this section— anniversary changeover application , for an environmental authority, means an application under section 316L of the Act to change the anniversary day for the authority to a new day. interim year , for a proposed change of anniversary day, means the period— starting on the old anniversary day for the environmental authority; and ending on the new anniversary day in the following year after the proposed change. If the old anniversary day was 1 June and the new anniversary day is 1 July, the period will be 31 days.
- (a) starting on the old anniversary day for the environmental authority; and
- (b) ending on the new anniversary day in the following year after the proposed change.