QLDIn ForceAct
Environmental Protection Act 1994
sec.154Submission period for application—mining activities
Start here
Get a plain-English read of sec.154
Turn the raw legal text into a practical explanation grounded in Environmental Protection Act 1994.
### sec.154 Submission period for application—mining activities
The submission period for an application for a mining activity must end on—
if there is only 1 relevant mining tenure application—the last objection day under the Mineral Resources Act for the application; or
if there is more than 1 relevant mining tenure application—the later of the last objection days under the Mineral Resources Act for the applications.
For the last objection day under the Mineral Resources Act , see section 252 of that Act.
s 154 prev s 154 om 2000 No. 5 s 461 sch 3
pres s 154 ins 2000 No. 64 s 6
amd 2002 No. 45 s 3 (2) sch ; 2004 No. 48 s 38 ; 2005 No. 53 s 46 ; 2007 No. 56 s 13 ; 2011 No. 3 s 5
sub 2012 No. 16 ss 7 – 8
amd 2014 No. 47 s 262 (amd 2016 No. 30 s 76 )
- (a) if there is only 1 relevant mining tenure application—the last objection day under the Mineral Resources Act for the application; or
- (b) if there is more than 1 relevant mining tenure application—the later of the last objection days under the Mineral Resources Act for the applications.