### sec.25 Notice about draft coastal plan
The Minister must publish a notice about a draft coastal plan prepared under section 24 in—
the gazette; and
a newspaper circulating generally in Queensland.
The notice must state the following—
that the draft plan is available for inspection and purchase;
where copies of the draft plan may be inspected and purchased, including, for example, the department’s website;
a contact telephone number for information about the draft plan;
that written submissions about any aspect of the draft plan may be given by any person to the Minister;
the period (the consultation period ) during which the submissions may be made;
the requirements for a properly made submission.
The consultation period must be at least 40 business days after the day the notice is gazetted.
The Minister must give a copy of the notice and draft plan to—
each local government, port authority and port operator within the area covered by the draft plan; and
any other group or person the Minister considers appropriate.
A local government, port authority or port operator receiving a copy of the draft plan must make the copy available for inspection by the public.
s 25 amd 2004 No. 48 s 5
sub 2011 No. 6 s 13
amd 2016 No. 27 s 136
(sec.25-ssec.1) The Minister must publish a notice about a draft coastal plan prepared under section 24 in— the gazette; and a newspaper circulating generally in Queensland.
(sec.25-ssec.2) The notice must state the following— that the draft plan is available for inspection and purchase; where copies of the draft plan may be inspected and purchased, including, for example, the department’s website; a contact telephone number for information about the draft plan; that written submissions about any aspect of the draft plan may be given by any person to the Minister; the period (the consultation period ) during which the submissions may be made; the requirements for a properly made submission.
(sec.25-ssec.3) The consultation period must be at least 40 business days after the day the notice is gazetted.
(sec.25-ssec.4) The Minister must give a copy of the notice and draft plan to— each local government, port authority and port operator within the area covered by the draft plan; and any other group or person the Minister considers appropriate.
(sec.25-ssec.5) A local government, port authority or port operator receiving a copy of the draft plan must make the copy available for inspection by the public.
- (a) the gazette; and
- (b) a newspaper circulating generally in Queensland.
- (a) that the draft plan is available for inspection and purchase;
- (b) where copies of the draft plan may be inspected and purchased, including, for example, the department’s website;
- (c) a contact telephone number for information about the draft plan;
- (d) that written submissions about any aspect of the draft plan may be given by any person to the Minister;
- (e) the period (the consultation period ) during which the submissions may be made;
- (f) the requirements for a properly made submission.
- (a) each local government, port authority and port operator within the area covered by the draft plan; and
- (b) any other group or person the Minister considers appropriate.