### sec.375 Processes
A process undertaken under the repealed regulation before the commencement is taken to be a process undertaken under this regulation.
A process started under the repealed regulation that was not completed before the commencement may be continued under this regulation.
In this section—
process includes—
a practice; and
a measure; and
an investigation; and
a risk assessment; and
an election process.
(sec.375-ssec.1) A process undertaken under the repealed regulation before the commencement is taken to be a process undertaken under this regulation.
(sec.375-ssec.2) A process started under the repealed regulation that was not completed before the commencement may be continued under this regulation.
(sec.375-ssec.3) In this section— process includes— a practice; and a measure; and an investigation; and a risk assessment; and an election process.
- (a) a practice; and
- (b) a measure; and
- (c) an investigation; and
- (d) a risk assessment; and
- (e) an election process.