### sec.119 General time requirement for making recommendation
The Land Court must take all reasonable steps to make sure that its recommendation about the cultural heritage management plan is given to the Minister within 4 months after the objection or referral is filed with the Land Court.
If the recommendation is not made within the 4 months, the Land Court must, as soon as practicable after the 4 months ends, give a written notice to the Minister—
advising why the recommendation has not yet been made; and
giving an estimate of when the recommendation is likely to be made.
s 119 amd 2007 No. 39 s 41 sch
(sec.119-ssec.1) The Land Court must take all reasonable steps to make sure that its recommendation about the cultural heritage management plan is given to the Minister within 4 months after the objection or referral is filed with the Land Court.
(sec.119-ssec.2) If the recommendation is not made within the 4 months, the Land Court must, as soon as practicable after the 4 months ends, give a written notice to the Minister— advising why the recommendation has not yet been made; and giving an estimate of when the recommendation is likely to be made.
- (a) advising why the recommendation has not yet been made; and
- (b) giving an estimate of when the recommendation is likely to be made.