Certification requirement
18Mrs Yule submitted that the words "still relevant" do not amount to a certification that physical commencement of the development has commenced, nor does it certify that the DA is still current. The word "certifying" means "to make a formal statement of, or to attest, or to declare by certificate". Thus, the document to be provided by the Council was to be a valid document that could be relied upon by attesting that the development consent was still on foot. It was submitted that the words used by the Council "that physical commencement of the above development is ongoing is still relevant" do not give any assurance that the Council has accepted that the original consent is still in force.
19She submitted that at the time, the relevant provision was s95(4) of the Environmental Planning and Assessment Act 1979: "Development consent for the erection of a building... does not lapse if building, engineering or construction work relating to the building.... is physically commenced on the land to which the consent applies before the date on which the consent would otherwise lapse....".
20She submitted that it is clear from the section that it is a question of fact as to whether building, engineering or construction work has been physically commenced on the land. Whether the consent has lapsed is probably a mixed question of fact and law: see Tobias JA in Hunter Development Brokerage Pty Ltd v Cessnock Council (2005) 63 NSWLR 124, at [19].
21There was evidence before me demonstrating the work that was done to achieve what was said to be substantial commencement of the development. Having regard to that evidence, this has been achieved. Mrs Yule's attitude to this issue was that it was not this court's task to decide that question even if the court had jurisdiction to do so. According to Mrs Yule all this court has to do is decide whether Mr Smith has complied with clause 2.2 of the Heads of Agreement such that it should order specific performance.
22It is clear that the correspondence does not use the word "certified". It is to be noted that there is no statutory obligation for the Gosford Council to so certify and that a consideration of the correspondence before and after the letter of 31 May 2010, details of which are set out above, makes it clear that Gosford Council was clearly of the opinion that physical commencement of the work contemplated by the development was achieved.
23It can hardly be suggested that in the context of the present case and the clause that it was incumbent on Mr Smith to obtain some declaratory order from the Land and Environment Court that the development consent had not lapsed in accordance with the Environmental Planning and Assessment Act 1979. Such a procedure was involved in St Basil's Homes & NSW Land and Housing Corporation v Randwick Council [2011] NSWLEC 72. However, that case was one where the agreement of the parties required the application as part of the agreement.
24Plainly the present clause does not require that. It requires something less.
25In my view, having regard to the available correspondence and noting that it is not suggested that the time limits in the Heads of Agreement are of the essence or have been made of the essence, there has been compliance with clause 2.2 and 2.3 of the Heads of Agreement.
26In my view, there has been compliance with the terms of the Heads of Agreement and the Court should make an order enforcing the Heads of Agreement.
27I direct the parties to bring in Short Minutes and argue costs.