Q. So ultimately it comes down to what somebody did or didn't tell you, is that right?
A. No, as far as I am concerned, we had the contract with Sydney G & F and he was working as their team of renderers. I wasn't told that he was independent. I was told that he was working as their team of renderers.
77 I accept the tenor of Mr Dean's evidence as to his belief about Mr El Mahrbani working as part of the defendants' team of renderers.
78 Occurring as they did prior to Mr El Mahrbani's accident on 1 October 2003, counsel for the defendants pointed in particular to the payments made to SFSA and Mr Ivan De Sousa as evidence that Forcon did engage subcontractors without written contractual agreements in place. Such evidence, it was contended, pointed to a conclusion that there was no administrative process in place, as asserted by Mr Forsyth and, to a lesser extent, Mr Dean, to ensure all subcontractors were subject to written contractual agreements. Further, it was contended, the absence of any written contractual agreement between Forcon and Mr El Mahrbani cannot, by itself, be seen as evidence that the work undertaken by Mr El Mahrbani at the Forcon site was done pursuant to the contract as between Forcon and the Dadoun partnership and therefore formed part of the undertaking and place of work of the partnership.
79 In further support of that contention, counsel for the defendants pointed to the haphazard and unsatisfactory nature of the record keeping of Forcon in relation to it's written contractual arrangements with the defendants as evidence pointing to the conclusion that Forcon may well have engaged subcontractors from time to time and simply failed to effect written contractual arrangements.
80 I have to say, the evidence relied upon by the defendants in support of it's overall submission on this issue is not as strong as the submission made would suggest. That is, while there was evidence before me of invoices rendered and paid prior to 1 October 2003, particularly to SFSA and Ivan De Sousa, for 'rendering' work done, there is no evidence before me by way of a subpoena issued by the defendants for Forcon to produce copies of any written contractual agreements between it and SFSA and Mr De Sousa for that period. In other words, simply pointing to the payment of invoices and cheque butts does not satisfy the evidentiary onus of establishing that Forcon did not have written contractual agreements with SFSA and Mr De Sousa - or with other subcontractors.
81 Further, a sloppy and haphazard approach to written documentation does not, by itself, point to the conclusion the defendants contend. On the evidence I have, and notwithstanding my critical comments as to Forcon's approach to it's responsibilities in this area, I am satisfied that, as a general proposition, it was part of Forcon's worksite management policy to have written contracts with subcontractors.
82 That conclusion alone, together with Mr Dean's evidence, does not necessarily establish that the work being undertaken by Mr El Mahrbani was part of the defendants' undertaking. Other factual matters arise for consideration.
83 Mr Carforio, the building supervisor for Forcon at the site gave evidence as to his knowledge of the relationship between Mr El Mahrbani and the Dadoun partnership at the worksite.
84 For the reasons earlier stated, I found Mr Carforio to be an unimpressive witness. As well, in his evidence before me, he contradicted evidence he had given in his statements to Inspector Macready. He also had a tendency, on occasions, to give his evidence on the basis of what he believed to be the case rather than any evidence going directly to his recollection of the issue in question. In some respects, his recollection was clearly incorrect. For example, he gave evidence that Mr El Mahrbani was introduced to the Forcon site some two months after the defendants had commenced work there. All the evidence is clearly to the contrary. That is, Mr El Mahrbani commenced work at the Forcon site some weeks before the Dadoun brothers started work at the site. This was because of the inability of the defendants to start work at the site at the time Forcon initially requested as they were engaged elsewhere. It was because of that unavailability that the Dadoun partnership introduced Mr El Mahrbani to the Forcon project.
85 That Mr El Mahrbani commenced work at the site before the defendants is borne out by the first invoice ever rendered by Mr El Mahrbani for work undertaken by him. That invoice (exhibit 14) is dated 26 May 2003 whereas the evidence points to the defendants commencing work on the site sometime in early June. The first invoice rendered for work undertaken by them was 16 June 2003. That was also the day the subcontract agreement between Forcon and the Dadoun partnership was returned to Mr Dean, completed as requested.
86 As the building supervisor, Mr Carforio gave evidence that the cement rendering work was done intermittently as required. Significantly, he says, when such work was required, he always rang 'Ghaleb or Fawaz' - the El Dadoun brothers. Further, he says, he was told by Ghaleb and Fawaz, if they were not on site and any problems arose, he was to contact or deal with Mr El Mahrbani. Finally, on the relationship as between the defendants and Mr El Mahrbani, Mr Carforio gave evidence that in measuring up rendering work for billing purposes, done either by Ghaleb or Fawaz El Dadoun or Mr El Mahrbani, such measuring work was always undertaken by him accompanied by Mr Ghaleb El Dadoun. His evidence on these issues was not challenged.
87 Mr Carforio stated, when on site, Mr El Mahrbani and his team of employees always worked at different parts of the site from the team overseen by Mr Ghaleb and Fawaz El Dadoun. That is, they worked at different parts of the site, often at the same time.
88 The misgivings I felt about some aspects of Mr Carforio's evidence were reinforced when one has regard to the evidence he gave in relation to the initial allegation that, at the time of the accident, he saw Mr El Mharbani standing on two milk crates. When spoken to by Inspector Macready on 9 March 2004, he was asked:
Q95: What was Omar El Mahrbani standing on at the time of the incident?
A: He was working off two milk crates on top of each other at the time of the accident.
89 In his evidence before me, Mr Carforio stated he had never seen Mr El Mahrbani 'actually standing on milk crates'. Rather, that was what he believed Mr El Mahrbani was doing.
90 There is also inconsistency in Mr Carforio's evidence and his entries in the Forcon site diary as building supervisor. For example, in relation to the circumstances existing on the day of the accident, it was Mr Carforio's evidence that, on that day, there was no scaffolding in place in relation to the work being performed on the balcony of unit 7 by Mr El Mahrbani and, as a fall protection measure, he ensured timber handrails were put in place across the edge of the balcony with uprights 1100mm high and a timber handrail on top. Further, Mr Carforio stated, at the time the accident occurred, Mr El Mahrbani or one of his workers had removed the handrail on a number of occasions during the course of the day because he was told it was easier for them to perform their work.
91 Much was made of the absence of scaffolding on 1 October 2003 and when it had been removed. According to the site diary entries made by Mr Carforio, the scaffolding in front of the balcony on unit 7 was pulled down by the renderers on 30 September 2003 - the day before the accident. According to his entry in the site diary, the workers were told not to. It was, he said, because of the absence of the scaffolding on 1 October 2003, that the handrail fall protection measure was put up on the balcony of unit 7. However, Mr Carforio's entry in the site diary for 26 September 2003, confirmed in his statement to Inspector Macready on 9 June 2005, was that it was on 26 September, some four days before the accident, that the renderers pulled down the handrail on unit 7 and were asked to put it back on. Indeed, on the day of the accident, 1 October 2003, there is no mention in the site diary of any handrails being removed by the renderers from the balcony of unit 7.
92 If one has regard to the photographs taken by Mr Ghaleb El Dadoun on the day of the accident, two wooden uprights are evident on the balcony of the unit where Mr El Mahrbani fell. There is no evidence of any handrail.
93 Mr Carforio was challenged on the veracity of his evidence on this point and he adhered to it but, in all the circumstances, I found aspects of his evidence on this issue unreliable.
94 The evidence of Mr El Mahrbani is that the removal of scaffolding occurred about four days before his accident on 1 October 2003. As well, in his statement to Inspector Macready on 1 March 2004, Mr El Mahrbani indicated there was no handrail in place on the balcony of unit 7 on the day of his accident. As he explained to Inspector Macready, in removing the scaffolding from the wall on the south side of unit 7, he did so because, he said, he had been promised by the two Forcon foremen that wooden handrails would be put up on all the balconies to prevent falls and that he had spoken to the Forcon supervisors about this prior to starting work. According to him, scaffolding was not used as fall protection while he was working on the balcony of unit 7 because, he said, it was not his job to install the scaffolding to the balconies.
95 In relation to the issue of scaffolding, I prefer the evidence of Mr El Mahrbani to that of Mr Carforio. The evidence given by Mr El Mahrbani on this issue was consistent, both in his statement to Inspector Macready and before the Court. That is, scaffolding had been removed some four days or so prior to the accident and there was no handrail in place on the day he fell.
96 Mr El Mahrbani said that he was introduced to the worksite by one or other of the Dadoun brothers and that he gave a verbal quote for the rendering work he was to do to 'Jiff' who I understand to be Mr Jeff Forsyth, one of the other building supervisors on the site. Mr Jeff Forsyth was not called to give evidence.
97 His understanding as to the basis of the work undertaken by him at the site was expressed by him as follows:
Q. You were first introduced to the site and the company by Fawaz or Ghaleb El Dadoun, is that right?
A. Yes.