Woollahra Council v Duarte
[2013] NSWLEC 218
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2013-06-24
Before
Sheahan J, Biscoe J
Catchwords
- (2013) 193 LGERA 203 House of Peace Pty Ltd v Bankstown City Council (2000) 48 NSWLR 498
- (2000) 106 LGERA 440 Mosman Municipal Council v Denning [2002] NSWLEC 227 Project Blue Sky Inc v Australian Broadcasting Authority [1998] HCA 28
- (1998) 194 CLR 355 Reysson Pty Ltd v Roads and Maritime Services [2012] NSWLEC 17
Source
Original judgment source is linked above.
Catchwords
Judgment (12 paragraphs)
Introduction 1This judgment deals with questions ordered to be decided separately in these class 4 proceedings (see judgment and orders of Biscoe J on 21 September 2012 - [2012] NSWLEC 223). 2The Council by its Second Amended Summons ('SAS'), filed in court on 21 September 2012, sought three declarations and several orders in respect of works done on a terrace dwelling house located at 28 Edgecliff Road, Woollahra (Lot 8 in DP 34035). 3Before the court is an aerial photograph (Jenner bundle, p5), which places No 28 in a row of like developments from No 14 to No 32, with No 14 having a side boundary with Tindale Lane and all of them backing on to Icasia Lane. 4No 28 is located within the Residential (2b) zone under the Woollahra Local Environmental Plan 1995 ('the LEP'). Development is also regulated by Council's 2000 Development Control Plan ('DCP') for Exempt and Complying Development (Exhibit D1), and the Woollahra Heritage Conservation DCP 2003 ('2003 DCP') (Exhibit W2). 5The first respondent is the sole proprietor of the subject property, but the second respondent (her estranged husband) was joined in the matter because of some alleged involvement in the works of which the Council complains. He filed a submitting appearance, save as to costs, and the first respondent argues that, as the second respondent has no interest in the subject land, the relief sought against him would have no utility, as he would not be in a position to comply with any of the substantive orders which were sought against him in the summons. 6Attempts to mediate the matter in August 2012 were unsuccessful, and the issues between the parties as at the appointment of the hearing on 24 June 2013, remained those in the SAS, the Amended Points of Claim ('APOC'), also filed on 21 September 2012, and the first respondent's Points of Defence ('POD'), filed on 7 January 2013. 7The two questions separated by Biscoe J were: (a) Whether development consent ('DC') No DA502/2002 (as modified) granted by the applicant Council lapsed as at 8 July 2008. (b) If the DC has not lapsed, whether the respondents have complied with the DC and the construction certificate ('CC' - including condition 2 of the consent). 8Answers favourable to the respondents would conclude the proceedings, but if either question were answered favourably for the Council, the major issue remaining to be litigated would be whether the court should, in its discretion, grant any of the relief Council sought. However, in this respect, Biscoe J noted (in par [5] of his judgment) that it seemed possible that the parties could reach agreement on the further disposition of the proceedings. 9The active parties were ordered to negotiate a Statement of Agreed Facts ('SAF'), and, in the course of doing so, they reached a substantial degree of common ground in the proceedings. Council is prepared, after this judgment is delivered, to entertain a (further) s 96 modification application by the first respondent, if appropriate. 10As a result of that agreement, the Council conceded that the DC has not lapsed, and, following the luncheon adjournment during the hearing, formally sought leave to further amend the summons (Tp17, LL6-7). 11Council eventually deleted paragraphs 1-5 of the SAS, dispensing with any need for this court to deal with the lapsing issue. Its amended Findings and Directions document and its Third Amended Summons ('TAS') were filed with my Chambers on 27 June 2013 (see below [44]). 12The only remaining question before the court in this hearing is, therefore: Whether the following work has been carried out by the first respondent not in accordance with the development consent/construction certificate:- (a) the ridge line of the roof of the building is 0.468mm [sic - 0.468m] higher than a ridge line level of RL88.682 for the roof of the building.