White Rock Wind Farm Pty Ltd v Dulhunty
[2024] NSWCA 202
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2024-06-14
Before
Ward P, Adamson JA, Robb J
Source
Original judgment source is linked above.
Judgment (23 paragraphs)
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] The proceedings concern various agreements, including Leases, primarily between White Rock Wind Farm Pty Ltd (White Rock) and each of the five respondents, namely Mr Dulhunty, Mr Wood, John Wood (Harvesting) Pty Ltd (JWH), Mr Cameron and Mr Nugent (the Landowners), for the purpose of the construction and operation of a wind farm, including an electricity substation. The infrastructure most relevant to these proceedings was the access road from the Gwydir Highway to the electricity substation, which was ultimately built on Mr Wood's land (the access road). On 16 September 2014, White Rock entered into a suite of agreements with the Landowners, including: (1) An agreement to lease entered into between White Rock and each of the Landowners. Annexed to those agreements were the terms of a draft lease, rent agreement and royalty payment deed. (2) Two option agreements to purchase land on which the substation might be located, entered into between White Rock and each of Mr Wood and JWH. (3) Three option agreements for the transfer of easements entered into between White Rock and each of Mr Wood, JWH and Mr Nugent for the grant of two easements: one for the high voltage transmission line and the other for access to the substation from the Gwydir Highway. On 10 July 2015, White Rock entered into a project agreement with the Electricity Transmission Ministerial Holding Corporation (TransGrid). Under that agreement White Rock was obliged to ensure that title to the substation land passed to TransGrid and that easements for access to the substation and over the transmission line were granted to TransGrid. White Rock issued notices to proceed under each of the agreements to lease and the Leases were subsequently executed on 11 April 2016. On 10 July 2017, all the option agreements expired without White Rock having exercised any of them. White Rock provided no explanation as to why the options were allowed to expire, which consequently created the need for TransGrid to be granted access to the substation some other way. White Rock sought to do so by seeking consent from the Landowners under cl 8.5 of the Leases to enter into a non-exclusive licence with TransGrid for a right of access over the access road to the substation. The Landowners declined to do so and instead expressed their willingness to grant an access easement to TransGrid in return for additional payment. The case below was conducted and determined on the basis of whether the Landowners were obliged, under cl 8.5 of the Leases, without the payment of additional consideration, to consent to White Rock entering into the proposed licence deed with TransGrid. On appeal, however, the primary position of all parties was that cl 8.5 of the Leases had no application to the proposed draft licence deed. On appeal, the principal issues were: (i) Did cl 8.5 of the Leases apply to the draft licence deed? (ii) If cl 8.5 was not applicable, was White Rock permitted under the Leases to grant a licence to TransGrid to access the substation? (iii) If cl 8.5 was applicable, did the Landowners unreasonably withhold their consent under that clause? The Court (Griffiths AJA, Ward P and Adamson JA agreeing) held, dismissing the appeal: As to issue (i): (1) The object of cl 8.5 was to prevent White Rock from circumventing the restrictions in cl 8 as to assignment of the Leases without the Landowners' consent, by entering into an arrangement akin to an assignment, in the sense of transferring an existing proprietary right to an assignee: at [135]. Clause 8.5 had no application to the grant of the licence deed to TransGrid because this would not involve the transfer of any of White Rock's existing proprietary rights or obligations under the Leases: at [134], [138]. As to issue (ii): (2) White Rock could not validly grant TransGrid access to the substation, as proposed in the draft licence deed. Any such access arrangement or agreement had to involve the Landowners: at [152]. Objectively viewed, it could not have been the intention of the parties that the negotiated balance between their competing rights and interests reflected in the option agreements could effectively be circumvented in the way proposed by White Rock: at [151]. As to issue (iii): (3) The primary judge did not err in concluding that the Landowners' refusal to consent to the proposed licence deed was not unreasonable: at [154].