(2) Background circumstances
8The rights in question arose under the consulting agreement, to which there were four parties. Three, being the plaintiffs in the Court below, were National Australia Bank Ltd, Valenti Pty Ltd and AUSMAQ Ltd (collectively referred to below, as here, as "the NAB parties"). (Valenti is now known as National Markets Group Ltd ("NMG").) The agreement was to run for five years, unless extended by NMG: clause 8. Pursuant to the agreement, NMG was required to pay a "service fee" to Idoport, for the services of four nominated consultants (including Mr John Maconochie). The fee accrued in an amount of $85,000 per month, whether services were required or not. In addition, NMG was required to pay "performance bonuses" which were calculated as a percentage of gross operating revenue, fixed at 13.5% or 12.5% (depending upon the tax deductibility of the payment) while the cost-to-income ratio was under 45%, with a tapering reduction as the ratio rose to 85%: clause 7 and Schedule 2. The origin of the litigation which ensued was briefly identified by the primary judge at [7]:
"On 24 September 1998, Idoport and a related company, Market Holdings Pty Limited, commenced proceedings in this court against a number of companies in the NAB Group as well as several NAB executives. On 1 March 1999, Idoport and Market Holdings commenced further proceedings against NAB's former managing director, Mr Donald Argus. The plaintiffs in the two proceedings ... claimed damages totalling in excess of US$29 billion arising from alleged breaches of the Consulting Agreement, misleading or deceptive conduct and breach of fiduciary duty. The claims included a claim that the NAB Parties had delayed the commercialisation of the AUSMAQ service and, in doing so, had deprived Idoport of its performance bonus."
9Pursuant to the order made by Einstein J on 29 January 2002, the Idoport parties were barred from bringing fresh proceedings "concerning any cause of action or the whole or any part of any claim for relief by any of them in these proceedings, until costs in these proceedings have been paid in full". Idoport sought, unsuccessfully, to appeal the judgment of Einstein J, both in this Court and by way of application for special leave to appeal to the High Court.
10The consulting agreement not only set out the rights, Idoport's claims in respect of which remain in dispute, but also provided for the possibility of assignment, encumbrance or disposal, in the following terms:
"20.1 Assignment generally
The rights and obligations of each party under this Agreement are personal. They cannot be assigned, encumbered or otherwise dealt with and no party will attempt, or purport, to do so without the prior consent of the other parties (not to be unreasonably withheld)."
11The costs to be paid in order to lift the barring order were assessed on 14 February 2007 as in excess of $42 million. By the time the matter came before the primary judge the amount had increased to approximately $85 million: at [29].
12The agreements between the appellants and Idoport provided for Fulham to provide litigation funding to Idoport and for Portsmouth to subscribe to shares worth, at least in a first tranche, $1 million. The loan agreed to by Fulham was in an amount up to $10 million. Each agreement was secured by Idoport executing charges, "as beneficial owner, all of its right, title and interest in, to and under the Secured Property" (cl 3.1) in favour of each appellant. "Secured Property" was a defined term, cl 1.1 of each charge providing:
"Secured Property means, subject to clauses 3.2, 3.3 and 3.4, all the present and future rights, property and undertaking of the Chargor of whatever kind and wherever situated and includes Capital but does not include the Excluded Property unless and until the circumstances specified in clause 3.2 or clause 3.3 occur. A reference to Secured Property includes any part of it."
13The term "Excluded Property" was defined to mean the rights and obligations of Idoport "under the Consulting Agreement": cl 1.1. Thus the provisions at the heart of the dispute turned on the operation of cll 3.2, 3.3 and 3.4, which were in the following terms:
"3.2 Consent of NAB to charge over Excluded Property
If required by the Chargee, the Chargor must seek the written consent of NAB to the granting of a fixed charge in favour of the Chargee over the Excluded Property on the terms and conditions set out in this charge. If NAB consents to the granting of such a charge, then immediately upon the granting of such consent, the Secured Property shall be taken to include the Excluded Property and the Chargor shall be taken to have charged, as beneficial owner, all of its right, title and interest in the Excluded Property to the Chargee as security for payment of the Secured Money.
3.3 Notice extending charge over Excluded Property
Notwithstanding clause 3.2, whether or not NAB consents to the granting of such a charge, the Chargee may at any time by notice to the Chargor declare that the charge in 3.1 will extend to, and operate as a fixed charge over, the Chargor's right, title and interest in the Excluded Property. Immediately upon the giving of such notice, the Secured Property shall be taken to include the Excluded Property and the Chargor shall be taken to have charged, as beneficial owner, all of its right, title and interest in the Excluded Property to the Chargee as security for payment of the Secured Money.
3.4 No charge over Excluded Property until consent or notice given
For the avoidance of doubt, the Secured Property will not include the Excluded Property and nothing in this charge will operate as an Encumbrance over, or Security Interest in, the Excluded Property unless and until consent from NAB is received under clause 3.2 or the Chargee gives notice to the Chargor under clause 3.3."
14Idoport's first request for consent, pursuant to cl 3.2, made in March 2006 attached copies of the charges, dated 30 March 2005, and noted that the charges did not extend to the excluded property. Idoport sought consent from the NAB parties to the granting of the charges over the excluded property. Although the appellants challenged the use made in evidence of two letters from the NAB parties in response dated 7 and 12 February 2007, that challenge should be dismissed, for reasons set out below. It is convenient to refer to that material to explain the fate of the request.
15On 27 April 2006, the NAB parties expressed concern that Idoport had purported to charge its property "in favour of third parties resident outside the jurisdiction and with no prior notice to [the NAB parties]". In particular, the NAB parties referred to clause 3.3 by which Idoport "has purported to permit third parties to acquire or deal with Idoport's rights under the Consulting Agreement in breach of clause 20.1". They sought reasons from Idoport as to why it had taken that course and why it was now seeking written consent.
16Idoport did not respond until 22 November 2006. Its response was non-committal and largely uninformative, but confirmed that the appellants had requested that Idoport seek consent from the NAB parties.
17On 9 January 2007, before a response had been received from the NAB parties, each of the appellants sought to exercise its rights under clause 3.3 to extend the respective charges to the excluded property.
18On 7 February 2007, NMG and AUSMAQ responded to Idoport in terms which were replicated in a letter from the Bank, dated 12 February 2007. The NAB parties expressed their continuing concern with respect to the effect of clause 3.3 and reserved their rights with respect to Idoport's conduct in that regard. The NAB parties declined consent to the proposed extension of the charges, noting that they had taken into account the following matters:
- the terms of the Consulting Agreement;
- that Idoport has purported to charge its property in favour of third parties resident outside the jurisdiction and with no prior notice to NMG and AUSMAQ or the other party to the Consulting Agreement;
- that there has been a long-running dispute between the parties as to the proper construction of the Consulting Agreement and as to the respective parties' entitlements in relation to the Consulting Agreement;
- that NMG and AUSMAQ are major unsecured creditors of Idoport;
- that the amount of funds that Idoport can access under the Loan Agreement and the Share Subscription Agreement are not sufficient to discharge the likely quantum of Idoport's total indebtedness to NMG and AUSMAQ;
- that there has been an Event of Default under the Loan Agreement between Idoport and Fulham as a result of NSW Supreme Court Equity Division proceedings 50046 of 2005 having been dismissed and Idoport has given no details of what moneys have been drawn down under the Loan Agreement or whether that Event of Default has been waived, or whether a demand has been made for repayment or whether Fulham has given notice to Idoport that Fulham's obligations under the Loan Agreement have been terminated;
- that there has been an Event of Default under the Share Subscription Agreement between Idoport and Portsmouth as a result of NSW Supreme Court Equity Division proceedings 50046 of 2005 having been dismissed and Idoport has given no details of whether that Event of Default has been waived or whether Portsmouth has given notice to Idoport that Portsmouth's obligations under the Share Subscription Agreement have been terminated;
- that the circumstances surrounding, and the reasons for, Fulham and Portsmouth requesting Idoport to seek NMG's and AUSMAQ's consent to the extension of the Charges have not been explained.
19As noted in recounting the procedural history, on 3 September 2008, White J granted an application brought by the NAB parties and other parties as creditors of Idoport, seeking its winding up on the basis of its insolvency.
20By deeds of appointment dated 20 November 2008 (and accepted on 25 November 2008) each of the appellants purported to appoint Mr MJM Smith (of Smith Hancock, Chartered Accountants) as receiver of the property covered by their respective charges.
21On 16 December 2009 Mr Smith wrote to the NAB parties, on behalf of Idoport, requesting consent to the extension of the charges to cover the excluded property. The letter noted that Idoport was entitled to charge its property, other than the excluded property, without prior notice to the NAB parties. The letter stated that prior notice of its intention to extend the charges to cover the excluded property had been given, by the letter seeking the NAB parties' consent. (There was no real attempt to deal with the effect of entering into the charges, including clause 3.3.) The expressed purpose for seeking consent (apart from the removal of a risk that a court might find consent was necessary) was said to be to allow the receiver to assign the rights under the consulting agreement to a third party "for appropriate consideration". The receiver said he expected that Idoport "would then receive a surplus of funds after repaying its secured creditors". (The NAB parties were not secured creditors.) There was no suggestion that sufficient funds would be available to pay the outstanding costs order and it appears to have been assumed that Idoport itself would not be able to sell its rights under the consulting agreement as an assignee "would have to deal with the blocking effect of the gross sum costs order".
22The solicitors for the NAB parties responded on 5 February 2010. The letter denied the receiver's capacity to exercise any power of Idoport or take any step with respect to Idoport's rights under the Consulting Agreement. It referred to the letters of 7 and 12 February 2007 in which consent had been refused to Idoport (before the appointment of the receiver).
23The original receiver was replaced on 2 August 2010 with Messrs Sheahan and Lock, who became the first and second defendants in the current proceedings (and the fifth and sixth respondents on the appeal).